Normandy Outline Plan

Page 1

Normanby Road Early Works Outline Plan CRL-MTE-RME-LKA-PLN-800002

Revision: 000 Date: 18 December 2019

Page 1

| Normanby Road Early Works



Outline Plan of Works

Table of contents 1. Introduction ............................................................................................. 5 1.1

Structure of the Application........................................................................................... 5

1.2

City Rail Link Project ...................................................................................................... 5

1.3

Overview of CRL works in Mt Eden ................................................................................ 5

1.4

Statutory Approvals Overview ....................................................................................... 6

1.4.1.

CRL Designation 2500-6 .................................................................................................. 7

1.4.2.

KiwiRail Designation 6300 ............................................................................................... 8

1.4.3.

Regional Resource Consents ........................................................................................... 8

1.4.4.

Consents under National Environmental Standards ....................................................... 9

1.4.5.

Archaeological Authority ................................................................................................ 9

1.4.6.

Works Outside the Designation ...................................................................................... 9

1.5

Outline Plan Supporting Documents .............................................................................. 9

1.6

Requiring Authority and Site Details ............................................................................ 11

2. Statutory Framework ............................................................................. 12 2.1

Section 176A RMA - Outline Plan Requirements ........................................................... 12

2.2

Designation Conditions................................................................................................ 12

3. Site Description...................................................................................... 16 4. Description of Proposed Works .............................................................. 17 4.1

Overview .................................................................................................................... 17

4.2

Staging ........................................................................................................................ 17

4.3

Vegetation Removal .................................................................................................... 18

4.4

Relocation of Network Utilities .................................................................................... 19

4.5

Construction Support Area .......................................................................................... 19

4.6

Hours of Work ............................................................................................................. 20

5. Outline Plan Requirements .................................................................... 21 5.1

Height, Shape and Bulk of the Works ........................................................................... 21

5.2

Location of the Site ..................................................................................................... 23

5.3

Likely Finished Contour of the Site ............................................................................... 23

5.4

Vehicular Access, Circulation and Parking .................................................................... 23

5.5

Landscaping ................................................................................................................ 24

6. Other Matters to Avoid, Remedy or Mitigate Adverse Effects on the Environment ................................................................................................ 25 Page 3

| Normanby Road Early Works


Outline Plan of Works 6.1

Access and Parking ...................................................................................................... 25

6.2

Construction Noise and Vibration ................................................................................ 26

6.3

Network Utilities ......................................................................................................... 27

6.4

Built Heritage and Archaeology ................................................................................... 27

6.5

Trees and Vegetation .................................................................................................. 28

6.6

Contamination ............................................................................................................ 28

6.7

Air Quality .................................................................................................................. 28

6.8

Social Impact and Business Disruption ......................................................................... 29

6.9

Erosion and Sediment Control ..................................................................................... 30

6.10 Building Condition Surveys .......................................................................................... 30 6.11 Environmental Monitoring .......................................................................................... 30

7. Consultation .......................................................................................... 32 7.1

Community and Business Liaison Group ....................................................................... 32

7.2

New Zealand Transport Agency ................................................................................... 32

7.3

Auckland Council ......................................................................................................... 33

7.4

Auckland Transport ..................................................................................................... 33

7.5

Network Utility Operators ........................................................................................... 33

7.6

Mana Whenua ............................................................................................................ 33

7.7

Heritage New Zealand Pouhere Taonga ....................................................................... 34

7.8

Department of Corrections .......................................................................................... 34

7.9

Other parties............................................................................................................... 34

Appendix A:

Cover Letters ........................................................................ 35

Appendix B:

Planning Maps ..................................................................... 36

Appendix C: Designation Conditions & Spatial Map showing the interaction between the KiwiRail and CRL designations ................................................. 37 Appendix D:

Construction Environmental Management Plan ................... 38

Appendix E:

Construction Staging Drawings ............................................. 39

Appendix F:

Design Drawings................................................................... 40

Page 4

| Normanby Road Early Works


Outline Plan of Works

1.

Introduction

This Outline Plan relates to the Normanby Road early works in the vicinity of Normanby and Boston Roads, Mt Eden, which are required in advance of the main construction works along the Mt Eden Section of the City Rail Link (CRL). The works are authorised and provided for by CRL Designation 25006 in the Auckland Unitary Plan (AUP), for which City Rail Link Limited (CRLL) is the requiring authority, and the North Auckland Railway Line (NAL) Designation 6300, for which KiwiRail Holdings Ltd (KiwiRail) is the requiring authority (refer to Section 1.4 for further detail).

1.1 Structure of the Application We attach copies of the cover letters in Appendix A and a copy of the relevant Planning Maps in Appendix B.

1.2 City Rail Link Project The CRL project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the NAL in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape, and a redeveloped station at Mt Eden (refer to Figure 1-1).

Figure 1.1: Alignment of CRL

1.3 Overview of CRL works in Mt Eden The CRL main works in the Mt Eden area involve the construction of the southern section of the rail tunnel structures and the tie-in to the existing NAL, including the construction of the redeveloped Mt Eden Station. The Mt Eden Active Construction Zone (ACZ) and Construction Support Areas (CSA) are generally located between State Highway 1 (SH1) to the east and Dominion Road to the west.

Page 5

| Normanby Road Early Works


Outline Plan of Works The main works in this area include: • • • • • • •

Construction of an underground grade separation structure near Mt Eden Station; A new Mt Eden Station building incorporating passenger linkages; Modifications to the existing Mt Eden Station platforms; Road over rail bridges at Mt Eden Road, Normanby Road and Ruru Street with sections of road realignment; Grade separation structures and the east- and west-facing connections for the existing and new rail lines to pass-over and connect with each other; Pedestrian and cyclist bridge structures at Fenton Street and Porters Avenue; and New road linkages within the reinstated area post-construction.

Given the nature and scale of CRL works at Mt Eden, construction will be undertaken in a staged manner. This Outline Plan relates to one component of the CRL Mt Eden works, namely the Normanby Road early works, as described below. The Normanby Road early works involve: • • • •

• • •

Initial establishment of the Construction Support Area (CSA) at 14-22 Boston Road, 11 Water Street and partly within 28 Mt Eden Road; Diversion of a permanent 150mm diameter (dia.) south wastewater line along Normanby Road; Diversion of a permanent 150mm dia. north wastewater line from the Normanby Road / Boston Road roundabout to Water Street; Diversion of a permanent 450mm dia. stormwater (SW) line across Normanby Road from the Mt Eden Corrections Facility to 32 Normanby Road; and construction of new private SW connections from the premises at 32 Normanby Road to the new SW line located on the site; Construction of one retaining wall (approximately 1.5m high) to the south of the vehicle access of 32 Normanby Road; Construction of the retaining wall BST-01 (approximately 3.2m high) in the south-western corner of the Normanby Road / Boston Road roundabout; and Construction of a temporary pedestrian and utility bridge across the Normanby Road rail crossing and temporary utility (water, gas, power and communication) diversions.

1.4 Statutory Approvals Overview The works described in this Outline Plan are authorised by CRLL’s Designation 2500-6 and KiwiRail’s Designation 6300 in the AUP, and the CRL Aotea to North Auckland Line (A2N) resource consents. The boundaries for the CRL and KiwiRail designations are shown in Figure 1.2.

Page 6

| Normanby Road Early Works


Outline Plan of Works

Figure 1.2: KiwiRail (6300 – blue line) and CRL (2500 – yellow line) designations (Source: Auckland Council GeoMaps)

1.4.1. CRL Designation 2500-6 The CRL is provided for by six separate designations (2500-1 to 2500-6 in the AUP) and the Normanby Road early works are located within Designation 2500-6. Designation 2500-6 is a “surface designation for the construction, operation and maintenance of the CRL – including the rail tunnels and connections required to join the CRL to the North Auckland Railway Line (NAL). This designation is located generally between New North Road, Mt Eden Road and Boston Road in the north and the NAL in the South. It also includes land located on the southern side and adjacent to the NAL between Normanby Road and Mt Eden Road, and to the immediate east and west of Porters Avenue1”. The conditions relating to Designation 2500-6 are provided in Appendix C and addressed further in Section 2.2.

1

Auckland Unitary Plan (Operative in Part) – 2500 City Rail Link Limited Page 7 | Normanby Road Early Works


Outline Plan of Works

1.4.2. KiwiRail Designation 6300 The Normanby Road early works will also require works within KiwiRail Designation 6300 which applies to the North Auckland Railway Line from Portage Road, Otahuhu to Ross Road, Topuni. The purpose of Designation 6300 is to “develop, operate and maintain railways, railway lines, railway infrastructure, and railway premises as defined in the Railways Act 2005”. The works, as show in Figure 1.3 that are within the KiwiRail designation include: •

The retaining wall for the southern foundation for the temporary services bridge.

The conditions relating to Designation 6300 and the spatial map showing the interaction between the KiwiRail and CRL designations are provided in Appendix C.

Figure 1.3: Location of temporary services bridge in relation to KiwiRail designation (Source: Aurecon)

1.4.3. Regional Resource Consents A suite of regional resource consents (known as the Aotea to North Auckland Line (A2N) consents) provide for the construction of CRL between Wyndham Street in the City Centre and Mt Eden. It is noted that the relevant resource consent conditions are not addressed as part of this Outline Plan, other than by way of inclusion of relevant environmental management plans required by both the resource consent and designation conditions (refer to Section 1.5 below).

Page 8

| Normanby Road Early Works


Outline Plan of Works

1.4.4. Consents under National Environmental Standards The A2N consents include consent under the Resource Management (National Environmental Standard for Assessing and Managing Contaminants in Soil to protect Human Health) Regulations 2011 (NESCS).

1.4.5. Archaeological Authority An Archaeological Authority (Authority no. 2017/793) is held for the construction of the CRL Aotea to NAL works, which specifies how archaeological remains or artefacts encountered during construction are to be managed. The Normanby Road early works are covered by this authority.

1.4.6. Works Outside the Designation The Normanby Road early works are predominantly contained within the designation boundaries. However, a small portion of the early works are located outside the boundaries of Designations 2500-6 and 6300, including: • • • •

north sewer diversion at 8-10 Water Street and the road reserve of Water Street; south sewer diversion at 22-24 Normanby Road and road reserve of Normanby Road; private stormwater connections at 32 Normanby Road; construction of a retaining wall along the southern boundary of the vehicle entrance to 32 Normanby Road.

For the proposed sewer diversions, these works are occurring within the legal road corridor, and so are considered to be a permitted activity under Chapter E26, Rule A1 of the AUP. The proposed private stormwater connection and the small section of the southern driveway retaining wall at 32 Normanby Road are outside the boundaries of Designations 2500-6 and 6300 and resource consent is required under the AUP (Chapter E36 Natural hazards and flooding – Rule E36.4.1 (A56)) as the two structures are within the 1 per cent annual exceedance probability (AEP) floodplain. A separate resource consent will be lodged with Auckland Council to cover off these minor infringements.

1.5 Outline Plan Supporting Documents This Outline Plan has been prepared by the Link Alliance on behalf of CRLL and KiwiRail, in accordance with section 176A (s176A) of the Resource Management Act 1991 (RMA) and Condition 10 of Designation 2500-6. As required under designation Condition 10.1, this Outline Plan includes: • • •

a Communication and Consultation Plan; a Construction Environmental Management Plan (CEMP); and a suite of Delivery Work Plans (DWPs) that sit as sub-plans to the CEMP.

The CEMP and sub-plans that form part of this Outline Plan are identified in Table 1.1, along with reference to the specific designation and resource consent conditions that set out the requirements for the individual plans. Some plans are required by both designation and Page 9

| Normanby Road Early Works


Outline Plan of Works resource consent conditions (refer Table 1.1), in which case a single plan has been produced to address all relevant designation and consent requirements. Table 1.1: CEMP and Sub-plans

Plan2

Relevant Conditions CRL Designation

Resource consents

Normanby Road Early Works Construction Environmental Management Plan (CEMP) – Appendix D to this Outline Plan

C 20-21

C 35 - 36

Normanby Road Early Works Social Impact and Business Disruption DWP (SIBD DWP) – Appendix F of the CEMP

C 61

-

Normanby Road Early Works Communication and Consultation Plan – Appendix G of the CEMP

C 15

C 25

Normanby Road Early Works Erosion and Sediment Control Plan (ESCP) – Appendix H to the CEMP

-

C 53

Normanby Road Early Works Air Quality DWP / Air Quality Management Plan – Appendix I of the CEMP

C 59

C 222

Normanby Road Early Works Trees and Vegetation DWP (TV DWP) – Appendix J of the CEMP

C55

Normanby Road Early Works Transport, Access and Parking DWP (TAP DWP) – Appendix K of the CEMP

C 25

-

Normanby Road Early Works Construction Noise and Vibration DWP (CNV DWP) (including Site Specific Construction Noise and Vibration Management Plans (SSCNVMPs)) – Appendix L of the CEMP

C 36

-

Normanby Road Early Works Contamination DWP / Contaminated Soils Management Plan – Appendix M of the CEMP

C 57

C 131

The plans listed in Table 1.1 have been prepared in consultation with the Mt Eden Community and Business Liaison Group (CLG) (refer to Section 7.1 of this Outline Plan) and the DWPs have also been reviewed by an Independent Peer Review Panel and Auckland Council. In accordance with Designation Condition 10.2, the CEMP and sub-plans clearly document the comments and inputs received during this process, along with a clear explanation of where comments or recommendations have been incorporated in the plans, or where they have not been incorporated, the reasons for this. All works undertaken as part of the early works will be carried out in general accordance with this Outline Plan and supporting documents listed in Table 1.1 as required by designation Condition 10.6.

2

The Urban Design DWP required under designation condition 47 and the Public Art DWP required under designation condition 56 are not required with this Outline Plan as the early works do not include public realm reinstatement or any impacts on public art as identified in the conditions. Page 10 | Normanby Road Early Works


Outline Plan of Works

1.6 Requiring Authority and Site Details Tables 1.2 and 1.3 provide the details of the requiring authorities and sites for the Normanby Road early works. Table 1.2: Requiring authority and property details – CRL Designation

Requiring Authority

City Rail Link Limited

Owner of site

City Rail Link Limited and Auckland Transport

Site address / map reference

Normanby Road, Water Street, Boston Road

Legal descriptions

Normanby Road Road Reserve, 32 Normanby Road Lot 1 DP 64473 Water Street Road Reserve 11 Water Street Lot 1 DP 46192 Boston Road Road Reserve, 14-22 Boston Road Lot 2 DP 140685, Lot 1 DP 159651 28 Mt Eden Road Lot 3 DP 140685

Record of Title references

Normanby Road Road Reserve 32 Normanby Road 561508, NA20B/1231 Water Street Road Reserve 11 Water Street NA1800/17 Boston Road Road Reserve 14-22 Boston Road NA96A/123 28 Mt Eden Road NA83C/306

Relevant Plans

Auckland Unitary Plan (Operative in Part) (AUP)

Designation reference

CRL designation – 2500-6 of the AUP – confirmed 10 November 2015

Underlying zoning

Business – Mixed Use

Address for service

City Rail Link Limited Attention: Richard Jenkins – Principal Planner Phone: 021 870 124 Email: richard.jenkins@cityraillink.govt.nz

Page 11

| Normanby Road Early Works


Outline Plan of Works Table 1.3: Requiring authority and property details – KiwiRail Designation

Requiring Authority

KiwiRail Holdings Ltd

Owner of site

City Rail Link Limited and Auckland Transport

Site address / map reference

Normanby Road

Legal descriptions

Railway

Record of Title references

N/A

Relevant Plans

Auckland Unitary Plan (Operative in Part) (AUP)

Designation reference

KiwiRail designation- 6300, North Auckland Railway Line from Portage Road, Otahuhu to Ross Road, Topuri

Underlying zoning

Business – Mixed Use

Address for service

City Rail Link Limited Attention: Rebecca Beals – RMA Team Leader Phone: (04) 498 3389 Email: Rebecca.Beals@kiwirail.co.nz

2.

Statutory Framework 2.1 Section 176A RMA - Outline Plan Requirements

Under s176A of the RMA, the requiring authorities (CRLL and KiwiRail) are required to submit an Outline Plan to Auckland Council for the works that are to be undertaken within their designations. Section 176A(3) of the RMA requires that an Outline Plan must show: • • • • • •

The height, shape and bulk of the works; The location of the work on the site; The likely finished contour of the site; The vehicular access, circulation, and the provision for parking; Proposed landscaping; and Any other matters to avoid, remedy or mitigate adverse effects on the environment.

These matters are addressed in Section 5 below.

2.2 Designation Conditions In addition to the matters set out in s176A(3) of the RMA, this Outline Plan must also address the conditions of CRL Designation 2500-6 and KiwiRail Designation 6300. Table 2.1 and 2.2 identify the relevant conditions and of the respective designations and where they are addressed in this Outline Plan. The full set of designation conditions is included as Appendix C.

Page 12

| Normanby Road Early Works


Outline Plan of Works

Table 2.1: CRL designation conditions relevant to this Outline Plan

Condition No.

Condition

Section in Outline Plan

9.2

A summary of the communication and consultation undertaken between the Requiring Authority and Network Utility Operators prior to construction commencing shall be provided as part of the Outline Plan.

Section 7

10.1

The Requiring Authority shall submit an Outline Plan to the Auckland Council for the construction of the City Rail Link in accordance with section 176A of the RMA. The Outline Plan shall include: a) The Communications and Consultation Plan (Condition 15);

Appendix D

b) The Construction Environmental Management Plan (CEMP);

Appendix D

c) Delivery Work Plans (DWPs);

Appendix D

d) Site Specific Construction Noise/Vibration Management Plans(SSCNVMPs) and Notable Received Management Plans; and

Appendix D

e) Any other information required by the conditions of this designation associated with the construction of the City Rail Link.

This document and Appendix D

10.2

The plans listed in Condition 10.1 above must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, and any recommendations received as part of the Independent Peer Review Panel process (where applicable), along with a clear explanation of where any affected party comments or peer review recommendations have not been incorporated, and the reasons why not.

Appendix D

10.4

These plans should clearly show how the part integrates with adjacent City Rail Link construction works and interrelated activities. This particularly applies where the Urban Design DWP is submitted as a number of plans.

Sections 1.3 and 4

10.5

Early engagement will be undertaken with Auckland Council in relation to preparation and submission of the Outline Plan to establish a programme for the Outline Plan process to ensure achievable timeframes for both parties.

Section 7.3

10.6

All works shall be carried out in accordance with the Outline Plan(s) required by this condition.

Section 1.4

11.1

Prior to submitting the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) to Auckland Council for the construction of the City Rail Link, the Requiring Authority shall engage suitably qualified independent specialists agreed to by Auckland Council to form an Independent Peer Review Panel. The purpose of the Independent Peer Review Panel is to undertake a peer review of the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) and provide recommendations on whether changes are required to those plans in order to meet the objective and other requirements of these conditions.

Appendix D

Page 13

| Normanby Road Early Works


Outline Plan of Works

Condition No.

Condition

Section in Outline Plan

11.2

The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included on the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) provided to both the independent peer reviewer and Auckland Council as part of this condition.

Appendix D

11.3

The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) submitted to Auckland Council shall demonstrate how the recommendations from the independent peer reviewers have been incorporated, and, where they have not, the reasons why not.

Appendix D

Table 2.2: KiwiRail designation conditions relevant to this Outline Plan

Condition No.

Condition

Comment

1

See Diagram B09-06 for strata diagram for land adjacent to Broadway, Newmarket.

Do not apply (relate only to specific sites at Newmarket and Remuera).

2

No additions or alterations shall be made to the building scheduled in the District Plan (Map Reference E10-23 Remuera Railway Station and Signal Box) other than in accordance with an outline plan submitted and processed in terms of Section 176A of the Resource Management Act 1991. This provision shall also apply to the interior of the building and the site surrounds as dimensioned in the Plan

Do not apply (relate only to specific sites at Newmarket and Remuera).

3

3. Where an outline plan of works is submitted in accordance with s176A of the Resource Management Act 1991, prior to commencing the project or work, that plan shall be accompanied by: a. A statement outlining the District Plan objectives and policies relevant to the works proposed; and b. An assessment of the effects the works described in the outline plan will have on the environment

Noted

4

Appropriate sedimentation and erosion control measures shall be employed for any new earthworks on the designated site

This is covered by the ESCP provided as part of this Outline Plan

5

Where an outline plan of works is submitted in accordance with s 176A of the Resource Management Act 1991 in relation to the installation of new track, that plan shall confirm: a. that, except as provided for in (c), all track to be installed in these locations will be continuously welded rail; b. that the track in these locations will be inspected by an EM80 inspection train (or similar) at least every six months, and, if results show

Does not apply – this is the new condition added as part of the 2017 direct referral proceedings. It only applies to new track work – which we are

Page 14

| Normanby Road Early Works


Outline Plan of Works

Condition No.

Page 15

Condition

Comment

track corrugation, that maintenance will be undertaken to remove the corrugations as soon as practicable; and c. where a turnout or break in the rail is proposed in these locations, the measures that are to be undertaken (including the use of low vibration turnouts) to ensure that vibration will be no greater than the standard set out below, at the measurement point. i. The standard is 0.14mm/s RMS between 8 and 80Hz, in accordance with ISO2631-2:2003, for 95% of any 20-consecutive freight train pass-bys. ii. The measurement point is to be within 500mm above the ground at the foundation of any building containing residential unit(s) existing as at 1 December 2017, located within 25m of the turnout or break in the rail

not doing as part of the Normanby Road early works.

| Normanby Road Early Works


Outline Plan of Works

3.

Site Description

The early works will be undertaken in the vicinity of Normanby Road. The indicative works areas are shown in Figure 3.1 below. Staging drawings of the works are included in Appendix E.

Figure 3.1: Normanby Road early works indicative work area

Works will largely be undertaken within the road reserves of Normanby Road, Boston Road and Water Street, with the exception of the Construction Support Area (CSA) to be established at 14-22 Boston Road, 11 Water Street and partly within 28 Mt Eden Road. The properties over which the CSA will be established are owned by CRLL. The CSA area is sealed and flat and it extends to the west of the intersection of Normanby Road and Boston Road, towards Water Street. The area around Normanby Road is characterised as a dense urban environment with a mixture of residential and business land uses, together with the Mt Eden Corrections Facility at Lauder Road. Street trees and small green spaces are present around the Normanby Road / Boston Road roundabout, and present along the northern boundary of the carpark at 32 Normanby Road. Normanby Road and Boston Road are important transport corridors for both private and public transport.

Page 16

| Normanby Road Early Works


Outline Plan of Works

4.

Description of Proposed Works 4.1 Overview

Normanby Road early works will be undertaken between February 2020 and September 2020, in advance of the main CRL construction works. In summary, the Normanby Road early works described in this Outline Plan involve demolition of the building at 11 Water Street3, establishment of a Construction Support Area (CSA) to support the early works and subsequent main construction works, utility diversions through trenching, tree removal, construction of two retaining walls and the placement of a temporary utility and pedestrian bridge in the vicinity of Normanby Road. A detailed description of the early works is included in the CEMP (Appendix D), with a summary provided in Section 1.3 of this Outline Plan.

4.2 Staging The indicative construction staging of the early works is outlined in Table 4-1 and shown in the staging drawings included as Appendix E of this Outline Plan. It is noted that the order of the construction is subject to change. Table 4.1: Indicative Normanby Road Early Works Construction Staging

Stage

Description

Approximate Duration

Stage 0 – Demolition of the building at 11 Water Street

Demolition of the building at 11 Water Street.

February – March 2020

2 weeks

Stage 1 – Tree Removal and Utility Relocation

Establishment of CSA at 14-22 Boston Road, 11 Water Street and partly within 28 Mt Eden Road. Establishment of alternative car park at 14-22 Boston Road for premises at 32 Normanby Road. Demolition of northern boundary fence and kerb, tree removal and construction of retaining walls at 32 Normanby Road. Excavation of utility trench and installation of permanent south sewer line and stormwater line along Normanby Road, 22-24 Normanby Road and 32 Normanby Road. Installation of private stormwater connections from premises at 32 Normanby Road to the public stormwater line. Regrade car park area at 32 Normanby Road. Construction of piling platforms and piling for the temporary bridge at 32 Normanby Road and 14-22 Boston Road.

March – April 2020

2 months

April – May 2020

2 months

• Stage 2 – Utility Relocation and Temporary 3

Indicative Dates

Demolition of the building at 28 Mt Eden Road has been addressed as part of the Outline Plan for C6 Nikau St Stormwater Main Realignment. Page 17 | Normanby Road Early Works


Outline Plan of Works

Stage Pedestrian and Utility Bridge

Description • • •

• Stage 3 Temporary Pedestrian and Utility Bridge, Retaining Wall and Utility Diversion

• •

• Stage 4 – Utility Diversion

Construction of pile caps and removal of piling platforms upon completion. Complete installation of permanent stormwater line at 32 Normanby Road. Excavation and installation of permanent north sewer line across 14-22 Boston Road, 11 Water Street and 8-10 Boston Road. Reinstatement of car park surface and line marking at 32 Normanby Road. Construction of temporary bridge foundations at 14-22 Boston Road and 32 Normanby Road. Construction of retaining wall at the southwestern corner of the Normanby Road / Boston Road / Nugent Street roundabout. Installation of span columns and span truss (with temporary utilities attached) across the NAL rail corridor. Installation of temporary utilities on span columns. Excavation of utility trench and installation of temporary gas, water, power and communication lines from the temporary bridge to existing lines. Reinstatement of pavement. Installation of screens on the temporary bridge.

Indicative Dates

Approximate Duration

April – July 2020

4 months

August – September 2020

2 months

4.3 Vegetation Removal The early works will affect 50 trees and require the removal of 48 trees located within private properties (14-22 Boston Road and 32 Normanby Road), as shown in Figure 4.1. A Flame tree (scheduled as a Notable Tree in the AUP) and a mature English Oak tree will not need to be removed as part of the early works and will be protected during construction (refer N1 and T24 in Figure 4.1). Works within the root zone of the Flame tree are however anticipated. The method for removal of trees will be informed by a qualified practitioner in accordance with site observations, such as the proximity of surrounding buildings, tree size and overall condition. Works will generally involve setting up fencing around the area of trees that require removal, trimming of branches and cutting of the trunk, excavation or grinding of the stump (dependant on location of network utilities) and subsequent clean-up of the work area. Replacement planting will be undertaken as part of the public realm reinstatement on completion of construction for the CRL Mt Eden works, including works in the Normanby Road area. More detail of the trees and vegetation within the Normanby Road early works area is provided in the TV DWP included as Appendix J of the CEMP.

Page 18

| Normanby Road Early Works


Outline Plan of Works

Figure 4.1: Trees within or in close proximity to the project area (Red circle – trees for removal/ Green Circle – trees retained)

4.4 Relocation of Network Utilities The relocation of network utilities is required to enable the grade separation of Normanby Road and the North Auckland Railway Line. Works will include the relocation of stormwater, wastewater, potable water, gas, telecommunications and electrical utilities as outlined in Section 2.2 of the CEMP and detailed in the construction staging drawings included in Appendix E of this Outline Plan. It is noted that the relocation of stormwater and wastewater services as per the construction staging, are permanent. All other utilities will be diverted via the temporary services bridge, which is described in more detail in Section 5.1 below, over the existing railway corridor. All works relating to network utilities will be managed in accordance with operational requirements, safety and integrity of network utilities that are within, or are in close proximity to the works area. Co-ordination and consultation with Network Utility Operators (NUO) has been undertaken throughout the development of the works methodology and will continue during the early works. Utility relocations will be undertaken by trenching, and include potable water, wastewater, stormwater, gas, telecommunications and electrical utilities. Further detail on the utility relocation works is included in the CEMP (Appendix D).

4.5 Construction Support Area The early works will include the initial establishment of a CSA in the south-western corner of the Normanby Road and Boston Road roundabout. The CSA (also known as CSA 5 under the A2N resource consents) will be located at 14-22 Boston Road, 11 Water Street and part of 28 Mt Eden Road. This CSA will be utilised as part of the Normanby Road early works and the subsequent main CRL construction works. Page 19

| Normanby Road Early Works


Outline Plan of Works The CSA establishment works will include earthworks for the construction of the retaining wall in the north-eastern corner of the carpark (BST-01), the north sewer diversion and the establishment of site offices and staff facilities. This includes the establishment of carparking, stockpile and spoil areas and manoeuvring areas for heavy vehicles and machinery. The indicative site layout for the CSA is shown in the staging drawings included as Appendix E. The CSA will be progressively established from February 2020 through to September 2020. Further detail of the CSA establishment is included in the CEMP (Appendix D).

4.6 Hours of Work It is anticipated that construction work will generally be undertaken between 0700hrs to 2200hrs Monday to Saturday, in accordance with the CRL construction noise and vibration standards (designation Conditions 31 and 34). Piling and road cutting works will be restricted to 0700 to 1900 from Monday to Saturday. Limited construction works (including lifting the temporary bridge span across the NAL, sewer tie-in and installation of stormwater line along the vehicle access of 32 Normanby Road) may be undertaken outside the typical working hours to minimise traffic disruption and to meet the requirements of network utility operators, as these works will likely result in temporary traffic lane closures to allow for safe access and manoeuvring of heavy machinery i.e. cranes.

Page 20

| Normanby Road Early Works


Outline Plan of Works

5.

Outline Plan Requirements

Section 176A of the RMA sets out the matters to be included in an Outline Plan. These are addressed in Sections 5.1 to 5.5 below.

5.1 Height, Shape and Bulk of the Works The tree removal and building demolition work to establish the CSA will involve minor earthworks for contouring. Earthworks are also required to re-form the carpark at 32 Normanby Road and initial establishment of the CSA. These earthworks are considered to be minor in nature as they involve minimal cut and fill, and will not appreciably change the existing ground contour. Utility relocations will involve the excavation of a number of trenches and pits to facilitate the relocation works, located within the road reserve and the proposed CSA. Excavations will be open for the extent of the work while relocations are carried out, before being backfilled and surfaces (pavement and footpaths) reinstated to current levels. The temporary utility and pedestrian bridge to be constructed over the existing railway corridor will be approximately 10m high and span 30m. Design drawings of this temporary structure are included in Appendix F. Earthworks will be required to connect the utilities to the temporary utility and pedestrian bridge. As part of the early works, earthworks will be required to construct two retaining walls, as shown in Figure 5.1. The specific details of these retaining walls are as follows: • •

Retaining wall ‘A’ – 3.2m high by 41.5m long. This reinforced concrete retaining wall is required to accommodate relocated services and the future Boston Road level. Retaining wall ‘B’ – 1.8m high by 27m long (made up of 17m and 10m length walls forming an ‘L’ shaped wall). This concrete block retaining wall is required to support the future increased level of Normanby Road for the future road over rail bridge and retain the Office Max building entrance and vehicle crossing grade for safe access by vehicles.

The design drawings from the retaining walls are included in Appendix F. Temporary mesh fences (approximately 1.8m in height) will be erected around active working areas for the network utility relocations. Standard plywood hoardings will be erected around the CSA, which are similar to other active CRL construction areas. Within the CSA a number of buildings and structures, such as offices, toilets will be placed on site. Stormwater treatment areas and covered spoil and stockpile areas will also be established and remain in place for the duration of the early works construction period. The CSA is described in further detail in the CEMP (Appendix D).

Page 21

| Normanby Road Early Works


Outline Plan of Works

Retaining Wall ‘A’

Retaining Wall ‘B’

Figure 5.1: Normanby Road early works retaining wall locations

As described in Section 1.3, earthworks required to complete the following utility diversions also form part of the early works: • •

Diversion of a permanent 150mm diameter (dia.) south wastewater line along Normanby Road. This will require a trench with the following dimensions: 2.5m x 2m x 70m (WxDxL). Diversion of a permanent 150mm dia. north wastewater line from the Normanby Road / Boston Road roundabout to Water Street. This will require a trench with the following dimensions: 2.5m x 3m x 180m (WxDxL). Diversion of a permanent 450mm dia. stormwater line across Normanby Road from the Mt Eden Corrections Facility to 32 Normanby Road; and construction of new private stormwater connections from the premises at 32 Normanby Road to the new stormwater line located on the site. This will require a trench with the following dimensions 2.5m x 4m x 15m (WxDxL) across Normanby Road; 2m x 4m x 80m (public line) and 2m x 2m x 30m (private line) for the connection to 32 Normanby Road.

Refer to Section 4.2 and Table 2-2 in the CEMP for a breakdown of the construction sequencing.

Page 22

| Normanby Road Early Works


Outline Plan of Works

5.2 Location of the Site The early works are located in the vicinity of Normanby Road, Boston Road and Water Street as shown in the staging drawings in Appendix E.

5.3 Likely Finished Contour of the Site The establishment of the CSA includes demolition of the building at 11 Water Street and the construction of a retaining wall along the north-eastern boundary of the CSA (along the Normanby Road / Boston Road boundary). The indicative finished contour of the CSA will be relatively flat and is shown in the staging drawings included in Appendix E. The utility relocations will not alter the current contours of the site.

5.4 Vehicular Access, Circulation and Parking The TAP DWP (Appendix K of the CEMP) describes the vehicle access, circulation and provisions for parking during the early works. The early works will be undertaken in several construction stages over a period of approximately eight months (February – September 2020). During this time, a number of Temporary Traffic Management Plans (TTMPs) will be implemented for the works with evolving traffic management requirements and traffic lane configurations. Traffic management will range from temporary footpath occupation and temporary closures to traffic lane closures on Normanby Road (one lane of traffic in each direction on Normanby Road will be maintained throughout the duration of works). The traffic management approach will temporarily remove the existing kerbside parking on both sides of Normanby Road over a 150m section immediately south of Boston Road for the duration of the works. While work areas occupy one side of Normanby Road, two-way two-lane traffic operations will be maintained over at least 6.0m width of the remaining carriageway. Where a full closure of the Normanby Road level crossing is required, it will be undertaken either for several hours over selected nights or over Easter Weekend in April 2020. This will occur prior to the start of the Mt Eden Road bridge replacement works in accordance with CRL designation Condition 30.2(e), which does not permit the two fully operational traffic lanes of Mt Eden Road and Normanby Road to be restricted at the same time. Throughout the early works vehicle and pedestrian access to businesses and properties along Normanby Road (22-24, 32, 51-63 Normanby Road and 1 Lauder Road – the Mt Eden Corrections Facility) will be maintained through traffic management measures around the work zones, to reduce the disruption to these businesses and sites. Once the alternative parking spaces for 32 Normanby Road businesses have been provided in the CSA (as per CRL designation Condition 30.1(j)(iii)), a pedestrian path between the CSA and this property will be established via the existing pedestrian level crossing over the NAL. This pedestrian access will remain in place until the car park at 32 Normanby Road has been regraded, and the stormwater, retaining wall and land scaping works within the property are completed. Refer to section 4 of the TAP DWP for more details on the construction sequencing. The connection of the permanent north sewer works described in Section 4.4 will require temporary removal of parking spaces in the private car park of 8 and 10 Boston Road. The displaced parking spaces during the works will be provided for within the car park for 11 Water Street (owned by CRLL) and at 14-22 Boston Road. Page 23

| Normanby Road Early Works


Outline Plan of Works Pedestrian, cyclist and mobility/wheelchair access will be maintained through the construction area at all times. A 1.8m wide footpath will be maintained on the northern side of Boston Road. Safe temporary pedestrian/accessible crossing facilities will be provided at either extent of the Boston Road works. Where works will occupy the footpath on one side of the road, then the alternative pedestrian path on the other side of the road will be provided. TMPs will ensure that all pedestrian routes meet accessibility requirements, with appropriate ramps and gradients for all users. Traffic management areas interfacing with pedestrian crossing points will widen to cater for the crossing demand required during the works. Wayfinding signage will be provided at each junction along the key pedestrian routes through the works area. Where appropriate, this will provide information on the location and operation of specific buildings or businesses. Overall, the volume of construction traffic generated by the early works is predicted to be very low, with approximately 5 two-way truck movements per day. Construction traffic will include deliveries of plant and equipment for the works. Alternative options for the removal of spoil using the rail corridor were explored by the Link Alliance in conjunction with CRLL, Auckland Transport and KiwiRail, however were deemed not to be practicable. Parking for construction vehicles during the early works will be provided within each works area and the CSA. Vehicle circulation within the CSA will be two way, however vehicles entering and exiting the site will only be able to turn left in and left out. Normanby Road is an over-dimensional route as identified in the TAP DWP, while Mt Eden Road is an overweight route. Alternate routes will be put in place during the early works, as detailed in Section 5.8 of the TAP DWP, to retain the ability of providing for over-dimensional and over-weight vehicles.

5.5 Landscaping The early works do not comprise any landscaping. Replacement planting is proposed to mitigate the loss of the trees from within the Normanby Road early works area. This planting will be undertaken as part of the public realm (streetscape) reinstatement on completion of the main construction works, as discussed in Section 4.1 of the TV DWP at Appendix J of the CEMP.

Page 24

| Normanby Road Early Works


Outline Plan of Works

6.

Other Matters to Avoid, Remedy or Mitigate Adverse Effects on the Environment

The CEMP and sub-plans that form part of this Outline Plan provide comprehensive detail on the management of environmental effects during construction of the early works, including measures to avoid, remedy or mitigate adverse effects on the environment. A summary of the matters covered in the CEMP and sub-plans is provided below.

6.1 Access and Parking The Transport, Access and Parking Delivery Work Plan (TAP DWP) (Appendix K of the CEMP) outlines the measures that will be implemented during the early works to manage effects on access and parking (which will include footpath and lane closures and the temporary and permanent loss of car parking). Through the early works construction, the properties and roads that will be affected include: • • •

Temporary rail, road and lane closures to facilitate utility relocation and connections in Normanby and Boston Roads. Managing unimpeded access to the Mt Eden Corrections Facility (Lauder Road). The vehicle access and car parking for the businesses along Normanby Road. Specifically: o 32 Normanby Road o 22/24 Normanby Road o 26 Normanby Road o 51-63 Normanby Road o 45 – 47 Normanby Road o 49 Normanby Road (Vet)

Measures outlined in the TAP DWP to mitigate the effects on access and parking that will be implemented during the early works include: •

Page 25

Two fully operational traffic lanes on Normanby Road will be maintained at all times, except during the Easter weekend of 2020. While the lanes will be narrower, and a reduced speed limit will be in place, Normanby Road will retain its current through-traffic function with two fully operational traffic lanes for the majority of the early works. Kerbside parking on both sides of Normanby Road (approximately 180m) will be temporarily removed for the installation of the permanent south sewer line. The majority of this parking demand will be displaced to neighbouring roads. The Mt Eden Road bridge works will require the full closure of Mt Eden Road to all traffic on at least two occasions. To mitigate the impact of this, the closure will take place during evenings only, between 10:00pm and 6:00am. A weekend closure of the Normanby Road rail level crossing will be undertaken to accommodate the installation of the temporary sewer line across Normanby Road, immediately north of the NAL. The closure is to be undertaken between Friday 10 April to Monday 13 April 2020, which is the Easter public holiday. The timing of this closure will not coincide with the CRL works on Mt Eden Road bridge such that CRL designation Condition 30.2(e) will be satisfied. | Normanby Road Early Works


Outline Plan of Works • •

Provision for pedestrian access around the works areas and retaining pedestrian access to businesses and offices. Two-way vehicle access will be maintained for vehicle accessways to 51-63 Normanby Road and to the Mt Eden Corrections Facility during the early works construction. Where any access to private property is temporarily impacted by the early works, the affected parties will be consulted with, prior to the closure in accordance with the designation conditions. The affected community will be given advance notice of the traffic management measures prior to their implementation. The car park for the businesses at 32 Normanby Road will be affected during approximately the first 3 months of the early works construction period, with some car parks retained, as well as access maintained for delivery vehicles and pedestrians at all times, in a safe manner around the work zones, throughout all stages. Refer to Section 5.4 of this Outline Plan for details of the alternative car parking arrangement for the businesses at 32 Normanby Road.

6.2 Construction Noise and Vibration The early works will create changes to the existing noise environment, with noise and vibration generating machinery (including concrete cutting, hydro excavation, and use of mechanical excavators and compactors) operating in relatively close proximity to noise and vibration sensitive receptors. Any road cutting or piling works will be restricted to between the hours of 7am-7pm Monday to Saturday in accordance with CRL designation Condition 36.3(b), with the implementation of mitigation measures as practicable. The management of construction noise and vibration during the early works is addressed by the Construction Noise and Vibration Delivery Work Plan (CNV DWP) (Appendix L of the CEMP). The CNV DWP outlines the construction noise and vibration performance standards that must, as far as practicable, be complied with. The CNV DWP also sets out the management and mitigation measures that will be implemented during the early works in order to avoid or mitigate adverse noise and vibration effects on sensitive receptors located in the surrounding area. The CNV DWP identifies those buildings where construction activities are predicted to exceed the Project Standards for construction noise and vibration and for which a Site-Specific Construction Noise and/or Vibration Management Plan (SSCNVMP) is required in accordance with CRL designation Conditions 37 and 38. Specifically, a SSCNVMP or SSCNMP is required for: • • • • • • • •

The Project (Mediaworks) (SSCNVMP) 12 Boston Road (SSCNMP) 7 Water Street (SSCNMP) – required for construction and building demolition noise 25 Enfield St (SSCNMP) 22 – 24 Normanby Road (SSCNMP) 26 Normanby Road (SSCNVMP) 32 Normanby Road (SSCNVMP) 51 – 63 Normanby Road (SSCNMP)

Refer Section 5 and Appendix C of the CNV DWP (Appendix L of the CEMP). The respective sitespecific management plans outline the Best Practicable Option that will be implemented during the works to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise or vibration on the respective properties. Page 26

| Normanby Road Early Works


Outline Plan of Works

6.3 Network Utilities The early works will require the temporary and permanent relocation of network utilities within the road corridors of Normanby Road and Boston Road. All works relating to network utilities will be undertaken in a manner that takes account of, and includes measures to address the safety, integrity and protection of existing network utilities that traverse, or are in close proximity to the works area. Co-ordination and consultation with the NUOs has been undertaken throughout the development of the works methodology and will continue during the works. Refer to Section 5.1 of the CEMP at Appendix D for a more detailed outline of network utility management during the early works.

6.4 Built Heritage and Archaeology As part of the Normanby Road early works, no work will directly affect any identified historic heritage buildings or structures, or their scheduled extent of place. The heritage sites in the vicinity of the project works area are the Mt Eden Corrections Facility , the bluestone walls that form part of the entrance to the site (located on the corner of Lauder Road and Normanby Road), the former Colonial Ammunition Company (CAC) Bulk Store at 26 Normanby Road, the former CAC Shot Tower at 24 Normanby Road and the former CAC General Office at 49 Normanby Road. In light of this, a built heritage assessment has been undertaken for the early works and include in Appendix M of the CEMP. While works will not directly affect any heritage buildings, the south sewer diversion work is located along the southern driveway of 22 Normanby Road, to the south of the scheduled building at 26 Normanby Road. The CNV DWP identifies that there is a potential to exceed the cosmetic building damage thresholds at the south-eastern end of the building. The Cosmetic building damage effects are deemed minor damage in the DIN Standard, such as cracking in paint or plasterwork, which can generally be easily repaired. A SSCNVMP has been prepared for the site and pre-construction building condition survey will be undertaken prior to the trenching work undertaken to record baseline information and ensure any damage caused by the construction works is identified for remediation. Protection measures, such as 2m high site fencing, will be installed along the southern side of the building to minimise any risk of impact damage. Clough & Associates (the Project Archaeologists) have undertaken a desktop assessment of the Normanby Road early works area. The assessment, which is provided in Appendix N of the CEMP, acknowledges the importance of the proposed CSA area being the site of a former spring known to Maori as Te Ipu-pakore. Over time, through European settlement and development for railway purposes in the 19th century, the area has been subject to significant disturbance and modification. Given this, the assessment concludes that the Normanby Road early works project area therefore has no known archaeological value. However, the possibility that subsurface archaeological remains may be exposed during the early works cannot be excluded. The following mitigation measures are in place: •

Page 27

An Archaeological Authority under Section 44(a) of the Heritage New Zealand Pouhere Taonga Act 2014 (Authority no. 2017/793) has been obtained and the works will be undertaken in accordance with this Authority. The Authority requires that work must be carried out in accordance with an approved archaeological management plan, which forms the basis of the Authority. | Normanby Road Early Works


Outline Plan of Works •

Prior to the start of the Normanby Road Early Works, the Link Alliance Project Manager/contractors will arrange an on-site meeting with the Project Archaeologist and Mana Whenua representatives, who will provide a briefing on archaeological and cultural requirements for the works, including the type of archaeological remains that might be exposed during works. The Project Archaeologist will attend toolbox meetings as required by the Link Alliance Project Manager during the course of the works, the purpose of which will be to remind staff of the Project’s archaeological requirements and to ensure that any new staff joining the Project team are fully briefed prior to the commencement of works.

6.5 Trees and Vegetation A Trees and Vegetation Delivery Work Plan (TV DWP) has been prepared to remedy or mitigate the adverse effects on trees and vegetation affected or removed by the early works (Appendix J of the CEMP). As noted, the early works require the removal of 48 trees within the vicinity of the CSA and 32 Normanby Road. The TV DWP outlines how the trees will be removed and how effects on remaining trees and vegetation will be avoided, remedied or mitigated to an acceptable level. The TV DWP also refers to the replacement planting which will be undertaken through the public realm (streetscape) reinstatement on completion of the main construction works.

6.6 Contamination The Contamination DWP (Appendix O of the CEMP) outlines the procedures to be implemented in relation to the handling and excavation of potentially contaminated soils during construction in order to avoid, remedy or mitigate adverse effects on human health and the environment. The potentially contaminated soil removed from trenches etc. during the earthworks will be backfilled with clean aggregate. Specifically, the DWP includes: • •

• •

Procedures for the management of contaminated fill and groundwater within the early works footprint, Measures to ensure the disposal of contaminated material to an appropriately licensed landfill and appropriate treatment of potentially contaminated water in order to avoid, remedy or mitigate effects; A contamination Health and Safety Plan; and Contingency measures to manage any unexpected discovery of contamination.

6.7 Air Quality The Air Quality Delivery Work Plan (AQ DWP) (Appendix I of the CEMP) outlines how any adverse effects of the discharge of dust and odour from the early works will be avoided, remedied or mitigated to acceptable levels. The overall approach to dust control during the early works involves a focus on pre-emptive mitigation measures such as visual inspections and monitoring to aid in the avoidance of significant discharges of dust, odour and hazardous air pollutants generated by construction activities for the early works. Given the location of the early works, in a built up urban environment, sensitivity to air pollution in general is relatively high. A range of measures will be used to manage and mitigate the effects of discharges of dust, odour and construction vehicle exhaust emissions during the early works. In particular: Page 28

| Normanby Road Early Works


Outline Plan of Works • •

• •

Controlling dust from exposed surfaces and limiting the disturbance of soil or dusty materials or the area of exposed materials, particularly during windy conditions; Temporary stabilisation or dust suppression measures shall be implemented to prevent dust nuisance to adjoining properties, pedestrians and road traffic. Surfaces that could give rise to dust will be swept regularly to remove any deposited material, and where this is impractical or ineffective these surfaces will be maintained in a damp condition using water sprays to increase surface moisture; Controlling emissions from plant and equipment where applicable, in accordance with regulatory requirements (such as emissions standards), and plant utilised for contract works shall be maintained in a good state of repair so as not to produce excessive fumes or leakage of contaminants when parked or in operation; Covering loads in haulage trucks where there is a risk of dust and materials being blown from vehicles; and Dust contingency measures to address complaints or concentrations of dust that are significantly greater than the trigger values.

Visual monitoring will be undertaken for the duration of the early works on a daily or weekly basis, where required. A Total Suspended Particulate monitor will be installed at the Normanby Road CSA as outlined in the AQ DWP.

6.8 Social Impact and Business Disruption The Social Impact and Business Disruption Delivery Work Plan (SIBD DWP) has been prepared to avoid, remedy or mitigate the adverse effects arising from disruption to businesses, residents and community services/facilities so far as reasonably practicable. The SIBD DWP (Appendix F of the CEMP) has been prepared in consultation with representatives from the community, business owners, affected parties and affected in proximity parties. The focus of the engagement has been on the affected community as shown in Section 5.2 of the SIBD DWP. Common issues raised by parties consulted are summarised below: • • • •

Concerns over temporary loss of pedestrian and vehicular access for deliveries to properties, and loss of private and on street carparks during construction; Concerns regarding loss of trade from the temporary lane closures that would be required; Impacts on residents and workers through noise and vibration; and Disruption to utilities as a result of the relocation of utilities.

The SIBD DWP addresses the management and mitigation of these potential impacts during the construction works. Mitigation measures proposed include: • •

Page 29

Temporary alternative parking for businesses located at 32 Normanby Road will be provided within the CSA at 14-22 Boston Road Ongoing and proactive communication from the Link Alliance will be maintained to inform the affected community of traffic management changes and to allow them to plan ahead for works. Affected parties will be provided with advance notice of construction works commencing and an understanding of noise levels. This engagement will be led by the Mt Eden Communication and Engagement team in conjunction with the noise and vibration subject matter experts. | Normanby Road Early Works


Outline Plan of Works •

Where planned utility outages are required, the affected community will be advised at least 10 working days prior to the planned event. This will be undertaken by the Mt Eden Communication and Engagement Team with the agreed arrangement and timing conveyed to the business at least 10 working days before the outage.

6.9 Erosion and Sediment Control The early works will involve small scale earthworks within the road associated with utility relocations, along with earthworks associated with the contouring of the CSA and excavation associated with the construction of retaining walls and car park regrading at 32 Normanby Road. Earthworks have the potential to generate sediment laden discharges to the surrounding receiving environment if not appropriately managed. In this case, the early works area covers seven stormwater sub-catchments. All drainage flows to Motions Creek. Erosion and sediment control measures need to be established correctly and maintained with effective capacity for the duration of the works. The early works Erosion and Sediment Control Plan (ESCP) (Appendix H of the CEMP) identifies the measures that will be implemented to mitigate and manage the potential adverse effects on the receiving environment from any erosion and sediment generation during the early works. The ESCP follows the principles of erosion and sediment control set out in Auckland Council “Erosion and Sediment Control Guide for Land Disturbing Activities in the Auckland Region”, Guideline Document 005 (GD05), which supersedes Auckland Council Technical Publication 90 (TP90). The mitigation measures include: • • • • •

Silt fences around the site, where practical. Catch pit protection (sand sock). Vehicle wheel wash to clean tyres and vehicle under-body prior to exiting the CSA. Diversion bunds and clean water diversions. Run-off storage tank within the CSA to treat sediment contaminated stormwater.

All erosion and sediment control measures will be fully established within each works area before physical works commence in that area.

6.10 Building Condition Surveys Building condition surveys will be undertaken in accordance with CRL designation Condition 46 and A2N resource consent Condition 133. Specifically, a condition survey will be undertaken for all buildings where there is potential for damage to buildings or structures arising from construction works, such as excavation, or vibration effects. For the Normanby Road early works, the only building condition surveys being undertaken are: • •

A pre-construction survey of 32 Normanby Road, which will ensure any damage during the early works is identified for remediation. A building condition survey of 26 Normanby Road, prior to utility trenching works to record baseline information and ensure any damage is identified for remediation.

6.11 Environmental Monitoring Section 6 of the CEMP at Appendix D provides a comprehensive outline of environmental monitoring and review requirements to be undertaken during the early works. Page 30

| Normanby Road Early Works


Outline Plan of Works In summary, monitoring of compliance with the designation and resource consent conditions will be undertaken throughout the early works to ensure that environmental effects are appropriately avoided, remedied or mitigated. This will enable the overall effectiveness of the environmental controls to be determined and allows areas of non-compliance or opportunities for improvement to be identified so appropriate actions can be taken. The specific monitoring required for each environmental element is detailed in the respective subplans appended to the CEMP. The sub-plans outline monitoring requirements, the frequency of the monitoring to be undertaken and the appropriate responsible person. Monitoring will take place on a routine basis, with additional monitoring required as appropriate i.e. in the event of a complaint or incident, or after a specific event, such as a rain event (water quality monitoring). Section 6 of the CEMP also details the collaborative process between the Link alliance, CRLL and Auckland Council compliance officers during construction in accordance with CRL designation Condition 13.

Page 31

| Normanby Road Early Works


Outline Plan of Works

7.

Consultation

Consultation with the Mt Eden Community and Business Liaison Group (CLG), Mt Eden Corrections Facility (Department of Corrections), Auckland Council, Network Utility Operators, Heritage New Zealand Pouhere Taonga, emergency services, Auckland Transport, NZ Transport Agency, businesses and residential properties has been undertaken as part of the initial consultation phase of the early works. Feedback from directly affected and affected-in proximity parties, along with the CLG and key stakeholders, regarding the development of the CEMP and sub-plans is captured in the respective plans, along with the Link Alliance’s response to the feedback. All of the consultation has been used to inform preparation of this Outline Plan and the supporting CEMP and sub-plans. A summary of this consultation is outlined below.

7.1 Community and Business Liaison Group The Mt Eden Community and Business Liaison Group (CLG), consists of members from a crosssection of the community, including residents, property owners, businesses and interest groups. This group focuses on the land surrounding the Western Line from Normanby Road to Haultain Street and up to Nikau Street CLG meetings are held at least every three months and will continue for the duration of the CRL Mt Eden construction works. The CLG is a key forum for providing: • • •

The community with regular information in relation to the CRL project, such as construction details, programme and what can be expected during construction; An opportunity for community concerns and interest to be raised and reported to the Link Alliance; and The community with an opportunity to review and provide feedback on the CEMP and subplans.

The CEMP and sub-plans listed in Table 1-1, and which form part of this Outline Plan, have been made available to the CLG for review and comment. Comments received from the CLG have served to inform the preparation of these plans and are captured in an appendix to the respective documents, along with a clear explanation of where comments or recommendations have been incorporated in the Plans, or where they have not been incorporated, the reasons for this.

7.2 New Zealand Transport Agency As outlined in Section 6 of the CCP, the Link Alliance has undertaken consultation with the New Zealand Transport Agency. This included information on the location, timing and duration of the early works (particularly in relation to traffic lane reductions and/or closures, alternative routes and detours) and consultation in advance of the commencement of construction. The consultation also covered the impact of the early works on over-dimensional routes and the management of works to minimise impacts on the surrounding state highway transport network. Refer to the Transport, Access and Parking DWP (Appendix K of the CEMP) for further details on engagement with the New Zealand Transport Agency. Page 32

| Normanby Road Early Works


Outline Plan of Works

7.3 Auckland Council The Link Alliance has a process for engaging with Auckland Council Parks Department regarding works to be undertaken to any trees on public land located within the early works area. Specifically, the early works will affect 50 trees, as works are required within the root zone of the Flame Tree (a ‘Notable’ tree in the AUP) located at the Normanby Road / Boston Road / Nugent Road roundabout and an English Oak Tree. Of the 50 trees affected, 48 trees within private properties will be removed. Pre-application meetings with Auckland Council Regulatory staff, technical advisors and compliance staff have been undertaken in relation to the Normanby Road early works and the preparation of the CEMP and sub-plans.

7.4 Auckland Transport As outlined in Section 6 of the CCP, the Link Alliance has engaged with Auckland Transport regarding the Normanby Road early works, in particular impacts on the traffic network, and public transport services. Refer to the Transport, Access and Parking DWP (Appendix K of the CEMP) for further details on engagement with Auckland Transport.

7.5 Network Utility Operators The network utilities that will be impacted by the early works are owned by the following Network Utility Operators (NUOs): • • • • • •

Vector Electricity; Vector Gas; Vector Communications; Chorus; Auckland Council’s stormwater unit (Healthy Waters); and Watercare Services Ltd.

Engagement with the NUOs has been undertaken to inform the design of the early works and will be ongoing during construction, with the objective of ensuring appropriate management of utility assets and the ability to meet operational requirements at all times. Refer to Section 7.2.5 of the Communication and Consultation Plan (CCP) for further details. The ‘Mt Eden Station, Karangahape Station and NAL Connections – Utilities Management Plan’ which informs construction processes has also been developed through engagement with the NUOs.

7.6 Mana Whenua A CRL mana whenua forum has been established for the purposes of undertaking kaitiakitanga responsibilities associated with the project. The forum comprises those mana whenua groups who expressed an interest in being involved in the CRL project and its related activities. Refer to Section 1.6 of the CEMP (Appendix D) for detail in this regard. The early works were presented to the mana whenua forum on 3 September 2019.

Page 33

| Normanby Road Early Works


Outline Plan of Works

7.7 Heritage New Zealand Pouhere Taonga Engagement has been undertaken with HNZPT regarding the wider CRL project, and an associated Archaeological Authority has been obtained. Engagement will continue in relation to the Normanby Road early works as required as outlined in the CCP.

7.8 Department of Corrections Engagement has been undertaken with the Mt Eden Corrections Facility regarding the Normanby Road early works. Refer to Appendix C of the CCP for a summary of the engagement undertaken. The Corrections Facility’s main concerns are: • •

Retain full unimpeded vehicle access throughout the early works Concern regarding impacts on utilities interruptions. Any impact on water supply and power would need to be managed, however most concerning would be an interruption in communications. Advanced notice is essential to allow contingency plans to be put in place.

7.9 Other parties Engagement has also been undertaken with representatives from the community, business owners, affected parties and affected in proximity parties in the process of developing the SIBD DWP. That engagement is detailed in the SIBD DWP contained in Appendix F of the CEMP.

Page 34

| Normanby Road Early Works


Outline Plan of Works

Appendix A:

Page 35

Cover Letters

| Normanby Road Early Works


Outline Plan of Works

Appendix B:

Page 36

Planning Maps

| Normanby Road Early Works


Auckland Council

Auckland Unitary Plan - Operative in part

113

119 6

123

DISCLAIMER: This map/plan is illustrative only and all information should be independently verified on site before taking any action. Copyright Auckland Council. Land Parcel Boundary information from LINZ (Crown Copyright Reserved). Whilst due care has been taken, Auckland Council gives no warranty as to the accuracy and plan completeness of any information on this map/plan and accepts no liability for any error, omission or use of the information. Height datum: Auckland 1946.

Mo un

Ed

40

t Bo s to

26

t E nfield S re et

24

27

2-106R

29 En fiel dS tre

60

t

2-106

54 2

Edwin S treet

60

S tr ee

e ig et h

ad

Ro

3

44-52

56

Laud

er Laud d a Ro

4-6 19

oad er R 1A

51-63

30

22

20

et

31-49

Ed w i

nS

tree t

Zones and Rural Urban Boundary Normanby Road - Early works

R oad

Avenue East

ld En field En fie et e tr S S t reet

Mo u e n nt Ro ad

105 107 Sylvan 109

115

7

103

er Laud d a Ro

28

1A

31-35

18

0

27

to n Bos d Roa

´

oad

an by

2

4

nR

No rm

6

6

2

32

Str ee

4

8

n

to Bos

ad Ro

Ma ry

8

10

24

1

Ed

12

A kiraho St reet

14-22

11

Harold Street

10

14

o ston Ro ad

41-43

d oa yR

16

1

5-7

20

53

55

45

39

b an

18

3

101

4 6 8-10 12

57

65

rm No

5

16-18

26

Mo u e n nt Ro ad

97

67

Boston Road

47-49

by Nor m an Road

95

75

tE de n

83

81

2

10 14

73 71 69

B

Ru tr S

21

40

Bosto n Road

67-71

39

Nug e nt

et

57

23

27-29

33

2

4

k oc dd t a Sh tree S

34 rl B u tre S 36

47

M o u nt Ed e n Road

e Str 5

10

43-45

3

5-7

15-17

16-18

ru eet

6

32

rn Aubu t Stree

r we Flo

i rar Ko eet Str 36-38

34

18

20-22 24-26 28-30

30

16

Map

10

20

Meters

Scale @ A4 = 1:2,500

Date Printed: 20/11/2019

30

1


Auckland Council

57

Ed

Mo

6300

un t

95

V U

S tr ee

t 4 6 8-10 12

65

5-7

20

11

o ston Ro ad

14-22

V U 6300

24

32

105 40 107 1616 Sylvan 109

Avenue East 113 115 119

7

6

103

123

DISCLAIMER: This map/plan is illustrative only and all information should be independently verified on site before taking any action. Copyright Auckland Council. Land Parcel Boundary information from LINZ (Crown Copyright Reserved). Whilst due care has been taken, Auckland Council gives no warranty as to the accuracy and plan completeness of any information on this map/plan and accepts no liability for any error, omission or use of the information. Height datum: Auckland 1946.

V U

29 En fiel dS tre

60

t

2-106

54 2

Edwin S treet

60

24

27

2-106R

44-52

56

4-6 19

1A

V U

51-63

30

22

20

et

Ed w i

nS

tree t

Designations Normanby Road - Early works

V U 4702

31-49

R oad

2

4

1

3903

18

an by

6

6

2

Laud

oad er R

No rm

4

8

Str ee

8

10

er Laud d a Ro

er Laud d a o R

26

t En field E nfield S re et Street

2500-6

n sto B o ad Ro

Ma ry

12

A kiraho St reet

3

1A

1

Harold Street

10

14

´

d oa yR

16

1

1616

to n Bos d Roa

b an

18

3

101

n

ad Ro

31-35

27

28

1616

5

55

39

41-43

45

47-49

53

rm No

U V V U V U

Boston Road

57

d 16-18

26

97

67

oa

V U

2500-6

73 71 69

by Nor m an Road

83

81

2

10 14

75

R

21

75

Bosto n Road

67-71

en

ru

27-29

40

B

Ru

23

39

36

Bo s to

2

4

k oc dd t a Sh tree S

34

Nug e nt

10

47

M o u nt Ed e n Road

et 5

5-7

V U

43-45

3

30

32

1592

Map rn Aubu t Stree

e Str

6

15-17

33

et

18

20-22 24-26 28-30

16-18

S tre

16

r we Flo

V U

2500-2

i rar Ko eet Str 36-38

34

Auckland Unitary Plan - Operative in part

0

10

20

Meters

Scale @ A4 = 1:2,500

Date Printed: 20/11/2019

30


Auckland Council

Auckland Unitary Plan - Operative in part

St 34 au k i N 36-38

5 15-17

16-18

Sh

ad

e Str ck o d

4

et

47

2

l Bur

Ru

r

21

83

ad

en

36

75

73 71 69

2

4 6 8-10 12

10 14

75

Wa te

16-18

20

r St

67

65

57

55

Laud

11

26

Mo Sylvan A venu 8

4

6

6

4

2

105 107 109

e E as t 2

113 115 119

7

6

103

123

DISCLAIMER: This map/plan is illustrative only and all information should be independently verified on site before taking any action. Copyright Auckland Council. Land Parcel Boundary information from LINZ (Crown Copyright Reserved). Whilst due care has been taken, Auckland Council gives no warranty as to the accuracy and plan completeness of any information on this map/plan and accepts no liability for any error, omission or use of the information. Height datum: Auckland 1946.

40

2-106R

2-106

44-52 54 56

2 60

24

27

60

t

8

Str ee

10

26

22

30

29 En fiel dS tre

20

et

31-49

Ma ry

12

Akiraho S t reet

3

d oa

10

14

1A

R by an

16

1A

4-6 19

Edwin S

´ 1

oad er R

28

1

27

oad

51-63

101

1

nR

32

treet Harold S

18

3

to Bos

31-35

14-22

ree t

5-7

45

39

41-43

rm No

5

47-49

53

u nt

Ed

39

24

Ro

95

81

34

40

57 67-71

97

h e ig

t

5-7

10

43-45

3

23

27-29

33 uS treet

et

et

e Str

tre t r ee

6

30

32

Nugen t Str ee

18

Str e et

r we Flo

iS rar Ko

20-22 24-26 28-30

16

Map

tr e et

Historic Heritage and Special Character Normanby Road - Early works

18

0

10

20

Meters

Scale @ A4 = 1:2,500

Date Printed: 20/11/2019

30


Auckland Council

V

V

V

V

V

V

V

V ka Ni 36-38 V 16-18

27-29 V V

r

33 u V S treeV t 21

V

V

V

V

5 V

10

15-17 Sh V

V

V 5-7

V

3 V

V

V V

V

V

V

V75

d ad

k oc

V

V

V

V

V

V

V

V

V 83 95

V

V

V

V

V

V

V

V

V

V

V

V 97

V

V

V

V

V

V

V

V

V

V

V

V

V

V 3

V

1V

V

V

V

V

V10

8 V6

4V

2 V

V

V

105 V 107 V

V2

V

V

V

V

V

V

V

V

7

V 10

V

V 6

V

Sylvan A venu

V

V V

12

V

8

V V V V

4

6

e E as t

V V

V V

115

V

119

V 123 V

DISCLAIMER: This map/plan is illustrative only and all information should be independently verified on site before taking any action. Copyright Auckland Council. Land Parcel Boundary information from LINZ (Crown Copyright Reserved). Whilst due care has been taken, Auckland Council gives no warranty as to the accuracy and plan completeness of any information on this map/plan and accepts no liability for any error, omission or use of the information. Height datum: Auckland 1946.

en

V

V

V

V

V

V

V

V 4-6

V 60

V

19 V

V 44-52 54 56

1

V

109

113

Ed

u nt

V 103

V

40

2

V

V

V

V

V

10 V 14

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

39V

V

V

V

V

V

V

31-35 V

V

V

´

V

V

V

V

V

V

V

67 V

V 47-49

75

65V

2

V

73 71 69 V

V

14-22 V V

V

V t 5-7

V

V

V

V

V

V

V

V

V

V

28 V

V

V

V

V

V

V

V V

Wa te

V 16-18V 20

26

36

V40

V

4 6 8-10 12 V V

V 24

Ro V

14 V

101

V

34

V

67-71

81

1A

V

treet Harold S

18 16 V

V

V

V

ad

V

l Bur

hV e ig

V

r St

ree

3

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

d

V

V

V

V

V

V

V

V

V

V

V

V

V

Ver RoaV

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

51-63 V V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

60V

V

29 En V field V

V

V

V

11

V 2-106R

27

V

V

V

V

V

V

V

V

V

tr e et V

V

V

V

V

V

V

V

V

#

Voad

nR

V

V

V

53 V

to Bos

V

V

V

V

V55

41-43

27

V

V

V

Edwin S

57

V 45

39

V

V

V

2-106

Map

V

V

V

24

32

Str e

et

26

Laud

1A

V

V

V

V

V

V

V

V

V

V

V

d oa

V

V

30 V

32

V

V

V

V

V

V

V

V

V

V

20 V

V

V

V

V

V

V

V

R by an

V

57

V

rm No

V

V

V

V

Akiraho S t reet

47

4 V

V

5

43-45

t ee Str V

V

V

2

V

t

6

V

Mo

V

23

V

et

et tr e u SV 34

Ru

V

et

V

tre

V

18 20-22 V V 24-26 28-30

V

Nugen t Str ee

V

V

22

V

V

V

V

V

31-49 V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

V

18 V

V

V

V

V

V

V

t

V

V 16

Str ee

V

V

Str e et

V

V

Ma ry

V

e Str

V

r we Flo

V

iS rar Ko

V

Auckland Unitary Plan - Operative in part

V

30

V

Natural Heritage Normanby Road - Early works

V

V

V

V

V

0

V

10

20

Meters

Scale @ A4 = 1:2,500

Date Printed: 20/11/2019

30

V

V

V

1

@

@

@ V

@

@

@ V

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@ V

@ V


Auckland Council

Auckland Unitary Plan - Operative in part 30

Map

t

et

et

´

Nugen t Str ee

tre

e Str

Str e et

r we Flo

iS rar Ko

( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (16( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (32( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (18( ( ( ( ( ( ( ( ( ( ( (3 ( ( (43-45 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (27( ( ( ( ( ( ( ( 20-22 6 ( ( (( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( (5-7 ( ( ( ( ( ( ( ( ( ( e(i gh( (34( ( ( ( ( ( ( ( ( ( ( ( (39( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (39 ( (31-35 (( ( (( ( (( ( (( ( 24-26 47 rl 36 u 10 B ( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( 2 28-30 41-43 et t ( ( 4( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( tre( ( ( ( ( ( ( ( ( ( ( ( 5 ( ( ( ( (re( e ( ( (( ( ( S 45 34 40 t ad au k S( ( ( ( ( ( ( ( ( nR c( ( ( (N(ik36-38 ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( (o( (o( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 57( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (47-49 to( s do d ( ( (( ( (( ( (( ( (( ( (( ( ( (Sh(a ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (75( (73 ( (71(69 ( ( ( ( ( ( ( ( ( (57 ( ( ( ( ( ( ( ( ( ( B( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 15-17 67 65 ( (16-18 ( ( ( ( ( ( ( ( ( ( (23( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (55( (53( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 67-71 ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 4 6 8-10 12 27-29 33 ( ( ( ( ( (u(S t( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (75( ( ( (10 ( ( (2( ( ( ( ( ( ( (14-22 ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( reet 14 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (W( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( a te r S( ( ( ( ( (21( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (81( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (1( tre( et d 83 16-18 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (5-7 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (u(de(r R(oa( ( ( (( ( (( ( (( ( (( ( (( ( a 20 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( L ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( 11 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (95( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (1A( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (24( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (32 ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (97 ( ( ( (26 ( ( ( ( ( (28( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (51-63 ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 1A( ( ( ( 3 1 ( (( ( ( ( ( (5 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (101 ( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (26 ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( ( ( ( ( ( (3 ( ( ( (1( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 24 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( A(kir(ah(o ( (e( ( ( (( ( (( ( t ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (27 S t re 22( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 18 16 14 ( ( ( ( ( ( (12 ( (10( (8 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 2 6 4 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 103 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (2-106R (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (105 ( ( ( 40 ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( (29 (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( E 20 fie( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (107 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (60( ( ( ( ( ( (n( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ld S tre e ( ( ( ( ( (Sy(lv( (nu (e(E( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( an( t A ve 109 2-106 as t 31-49 30( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (10 ( ( ( 8( ( ( 4 ( ( 2( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 44-52 ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 113 ( ( ( ( ( ( ( ( ( 6( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 54 ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (115 ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( 4-6( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (56 ( ( ( ( (2 ( ( ( Edwin S tr e ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( 119 18( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( et 19( ( ( ( ( 60 ( (7( ( ( ( ( ( ( ( ( ( ( ( ( (123 ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( ( ( ( (6( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( (( ( Ru

rm No

Mo

u nt

Ed

en

Ro

ad

r

R by an

Ma ry

Str ee

t

d oa

treet Harold S

DISCLAIMER: This map/plan is illustrative only and all information should be independently verified on site before taking any action. Copyright Auckland Council. Land Parcel Boundary information from LINZ (Crown Copyright Reserved). Whilst due care has been taken, Auckland Council gives no warranty as to the accuracy and plan completeness of any information on this map/plan and accepts no liability for any error, omission or use of the information. Height datum: Auckland 1946.

Natural Resources Normanby Road - Early works

0

10

20

Meters

Scale @ A4 = 1:2,500

Date Printed: 20/11/2019

30


Auckland Unitary Plan Operative in part 15th November 2016 - LEGEND Date: 15/07/2019

NOTATIONS

Appeals Properties affected by Appeals seeking change to zones or management layers Properties affected by Appeals seeking reinstatement of management layers

[i] [ rp ]

Proposed Plan Modifications Notice of Requirements Plan Changes

!

!

!

!

!

!

!

!

Tagging of Provisions: = Information only = Regional Plan

[ rcp ] = Regional Coastal Plan [ rps ] = Regional Policy Statement [ dp ]

= District Plan (only noted when dual provisions apply)

ZONING Residential

Rural Rural - Rural Production Zone

Residential - Rural and Coastal Settlement Zone

Rural - Mixed Rural Zone

Residential - Single House Zone

Rural - Rural Coastal Zone

Rural

Residential - Large Lot Zone

Residential - Mixed Housing Suburban Zone

Rural - Rural Conservation Zone

Residential - Mixed Housing Urban Zone

Rural - Countryside Living Zone

Residential - Terrace Housing and Apartment Buildings Zone

Rural - Waitakere Foothills Zone

Business Business - City Centre Zone

Rural - Waitakere Ranges Zone

Future Urban

Business - Metropolitan Centre Zone

Future Urban Zone

Business - Town Centre Zone

Green Infrastructure Corridor (Operative in some Special Housing Areas)

Business - Local Centre Zone

Infrastructure Special Purpose Zone - Airports & Airfields Cemetery Quarry Healthcare Facility & Hospital Tertiary Education MÄ ori Purpose Major Recreation Facility School Strategic Transport Corridor Zone

Business - Neighbourhood Centre Zone Business - Mixed Use Zone Business - General Business Zone Business - Business Park Zone Business - Heavy Industry Zone Business - Light Industry Zone

Coastal Coastal - General Coastal Marine Zone [rcp]

Open space Open Space - Conservation Zone

Coastal - Marina Zone [rcp/dp]

Open Space - Informal Recreation Zone

Coastal - Mooring Zone [rcp]

Open Space - Sport and Active Recreation Zone

Coastal - Minor Port Zone [rcp/dp]

Open Space - Civic Spaces Zone

Coastal - Ferry Terminal Zone [rcp/dp]

Open Space - Community Zone

Coastal - Defence Zone [rcp]

Water [i]

Coastal - Coastal Transition Zone

Precincts

Rural Urban Boundary

Indicative Coastline [i]


Overlays

Natural Resources

Natural Heritage

Notable Trees Overlay

Ì Ì Ì ÌÌ Ì Ì Ì Ì ÌÌ Ì Ì Ì Ì ÌÌ Ì Ì Ì Ì ÌÌ Ì

#

Terrestrial [rp/dp]

WWWW WWWW

Water Supply Management Areas Overlay [rp]

Outstanding Natural Character Overlay [rcp/dp]

Natural Stream Management Areas Overlay [rp]

High Natural Character Overlay [rcp/dp]

Significant Ecological Areas Overlay

Marine 1 [rcp] Marine 2 [rcp]

Urban ! ! ! ! !

! ! ! ! !

! ! ! ! !

! ! ! ! !

@

@

@

@

@

@

@

@

@

@

@

@

@

@

@

V V V V▼ V▼V▼ ▼ V▼ V▼V▼ ▼ ▼ ▼ ▼ ▼

High-Use Stream Management Areas Overlay [rp] Natural

@

Lake Management Areas Overlay (Natural Lake and Urban Lake)

High-Use Aquifer Management Areas Overlay [rp]

( ( ( ( ( Quality-Sensitive Aquifer Management Areas Overlay [rp] ((((( ( ( ( ( ( Wetland Management Areas Overlay [rp]

▬ ▬▬ ▬▬ ▬ ▬▬ ▬▬ ▬ ▬▬ ▬▬ ▬ ▬▬ ▬▬ ▬ ▬▬ ▬▬

Airport Approach Surface Overlay AAAAA AAAAA ( Ò (A Ò (A Ò (A Ò ( Ò AA (Ò Ò (Ò (Ò (Ò ( (Ò Ò (Ò (Ò (Ò (

ÉÉÉÉ É É É É Quarry Buffer Area Overlay É É É É National Grid Subdivision Corridor

!

National Grid Corridor Overlay

National Grid Yard Compromised

# # # #

# # # #

Locally Significant Volcanic Viewshafts Overlay Contours [i]

Ridgeline Protection Overlay

Extent of Overlay

Waitakere Ranges Hertage Area Overlay

Subdivision Schedule

Historic Heritage Overlay Place [rcp/dp]

Special Character Areas Overlay Residential and Business Auckland War Memorial Museum Viewshaft Overlay [rcp/dp]

Mana Whenua # # # #

Locally Significant Volcanic Viewshafts Overlay [rcp/dp]

Historic Heritage Overlay Extent of Place [rcp/dp]

National Grid Yard Uncompromised # # # #

Regionally Significant Volcanic Viewshafts Overlay Contours [i]

Historic Heritage & Special Character

National Grid Substation Corridor

# # # #

Height Sensitive Areas

Regionally Significant Volcanic Viewshafts & Height Sensitive Areas Overlay [rcp/dp]

Local Public Views Overlay [rcp/dp]

City Centre Port Noise Overlay [rcp / dp]

# # # #

Viewshafts

Natural

Aircraft Noise Overlay

# # # #

Outstanding Natural Landscapes Overlay [rcp/dp]

Modified

Infrastructure # # # # # # # # # # # #

Outstanding Natural Features Overlay [rcp/dp]

Auckland War Memorial Museum Viewshaft Overlay Contours [i]

Sites & Places of Significance to Mana Whenua Overlay [rcp/dp]

Built Environment

Stockade Hill Viewshaft Overlay – 8m height area Stockade Hill Viewshaft [i]

Identified Growth Corridor Overlay

Controls

General

"

Motorway Interchange Control

"

Vehicle Access Restiction Control

Centre Fringe Office Control Height Variation Control

@ @ @ @ Parking Variation Control @@@@ U U U U U U@U@U @ U @ U Level Crossings With Sightlines Control U U U U U

Emergency Management Area Control

Macroinvertebrate Community Index G G G G

) ) )

Infrastructure

G G G G

X X X Adjacent to Level Crossings

Hazardous Facilities

G G G G

General Commercial Frontage

!

Business Park Zone Office Control

Building Frontage Control

Flow 1 [rp]

EEEE E E E E Flow 2 [rp] E Ç ÇE Ç ÇE Ç ÇE ÇÇ Ç Ç Ç ÇÇ Ç Ç Ç

G G G G

Key Retail Frontage

Ç Ç Ç ÇÇ Ç Ç Ç Ç Ç Ç ÇÇ Ç Ç Ç Ç Ç Ç ÇÇ Ç Ç Ç ******* ******* ******* *******

Stormwater Management Area Control

Subdivision Variation Control Surf Breaks [rcp] Cable Protection Areas Control [rcp] Coastal Inundation 1 per cent AEP Plus 1m Control

Arterial Roads

Designations

V U 123

Designations

U 200

Airspace Restriction Designations


Outline Plan of Works

Appendix C: Designation Conditions & Spatial Map showing the interaction between the KiwiRail and CRL designations

Page 37

| Normanby Road Early Works


CRL Designation Conditions 29 October 2019

Aotea Alteration: BROWN (confirmed 24 January 2017) Condition 27.1(b) (Swanson St diversion): ORANGE (confirmed 23 June 2017) Strata/Sub-Strata Alteration: GREEN (confirmed 22 September 2017) Mt Eden CRL and NAL Alteration: BLUE (Environment Court Decision 15/12/17) Condition 27.1(b) (second Swanson St diversion): PINK (confirmed 27 March 2018) Operational Vibration Conditions 63 & 66: PURPLE (confirmed 24 July 2018) Karangahape Station Alteration: RED (Environment Court Decision 12 April 2019, upheld by High Court Decision 25 October 2019)

City Rail Link Notice of Requirement

Page 1


Explanatory Note: The following explanatory note does not form part of the conditions. It is a non-statutory way finding explanation of how the conditions are structured, what they cover in broad terms and where referenced documents can be found. This note does not alter legal obligations and rights created by the conditions. The conditions attach to six different designations. The designations are: 2500-1

A surface designation extending from Britomart Transport Centre to Albert Street/Mayoral Drive (in the vicinity of the Aotea car park entrance on Mayoral Drive) for the construction, operation and maintenance of the CRL – including two rail tunnels and Aotea Station.

2500-2

A sub-strata designation of land below the ground surface (within road resource and private property) for the construction, operation and maintenance of the CRL – including two rail tunnels and ancillary activities. This designation sits underneath the strata (protection) designation 2500-3 and extends from Mayoral Drive to New North Road.

2500-3

A strata (protection) designation that acts as a buffer between activities on the ground surface and the sub-strata designation (2500-2) that provides for the two rail tunnels. This designation sits above designation 2500-2, starting from 5 metres below the ground surface, and extends from Mayoral Drive to New North Road.

2500-4

A surface and sub-strata designation for the construction, operation and maintenance of Karangahape Station, and encompassing land within road reserve and private property in the vicinity of Pitt Street, Beresford Square, Karangahape Road, and Mercury Lane.

2500-5

A surface and sub-strata designation for the construction, operation and maintenance of Newton Station, and encompassing land within road reserve and private property in the vicinity of Symonds Street, Dundonald Street, and New North Road.

2500-6

A surface designation for the construction, operation and maintenance of the CRL – including the rail tunnels and connections required to join the CRL to the North Auckland Railway Line (NAL). This designation is located generally between New North Road, Mt Eden Road and Boston Road in the north and the NAL in the south. It also includes land located on the southern side and adjacent to the NAL between Normanby Road and Mt Eden Road, and to the immediate east and west of Porters Avenue.

Hereafter for the purpose of this condition set the designations are referred to as 1, 2, 3, 4, 5 and 6. The table of contents for the conditions provides a broad overview of the subject matter. It commences with definitions and abbreviations and progresses to general conditions applicable to all designations followed by the conditions for pre-construction, construction, and operation. Under each of these

City Rail Link Notice of Requirement

Page 2


headings may be found sub-headings dealing with specific aspects of the work. There follow advice notes and appendices for: - buildings for consideration as to building condition surveys; and - heritage buildings for consideration as to building condition surveys The conditions for designation 3 conclude the suite of conditions. Set out below are a series of figures illustrating and explaining the location, extent and nature of designations 1 – 6. For precise details, please refer to the relevant designation overlays within the planning maps. Figure 1: Designations Overview Map The map below is not to scale and is intended as a visual tool only to show the location of each designation. The Land Requirement Plans and associated Schedule of Directly Affected Parties (attached to each designation) should be referred to for the actual area of land required.

City Rail Link Notice of Requirement

Page 3


Figure 2: Visual explanation of the designation types Surface Designations

Sub-strata Designations

Strata Designation with Sub-strata Designation below

City Rail Link Notice of Requirement

Page 4


Figure 3: Indicative long-section of the designations across the length of the CRL

The relationship between the various plans required by designation conditions is illustrated in the diagram below:

The documents referred to in the designation conditions can be found at [insert]

City Rail Link Notice of Requirement

Page 5


Contents Requiring Authority Designation Conditions – for Designations 1, 2, 4, 5 and 6 DEFINITIONS GENERAL CONDITIONS Condition 1 Condition 2 Condition 3 PRE-CONSTRUCTION CONDITIONS Condition 4 – Appointment of Communication and Consultation Manager Condition 5 – Pre-Construction Communication and Consultation Plan Condition 6 – Network Utility Operators Condition 7 – Community Liaison Groups Condition 8 – Mana Whenua Consultation Condition 9 – Network Utility Operator Liaison CONSTRUCTION CONDITIONS Condition 10 – Outline Plan Requirements Condition 11 – Independent Peer Review of CEMP and DWPs Condition 12 – Availability of Outline Plan(s) Condition 13 – Monitoring of Construction Conditions Communication and Consultation Condition 14 – Contact Person Condition 15 – Communication and Consultation Plan Condition 16 – Communications – Notable Noise and Vibration Receivers Condition 17 – Concerns and Complaints Management Condition 18 – “One Network” Consultation Construction Environmental Management Plan (CEMP) and Delivery Work Plans (DWPs) Condition 19 – Preparation, Compliance and Monitoring Condition 20 – CEMP Requirements Condition 21 – CEMP Construction Works Requirements Condition 22 – Review Process for CEMP and DWPs

City Rail Link Notice of Requirement

Page 6


Condition 23 – Update of CEMP and DWPs following review Condition 24 – Network Utilities Transport, Access and Parking Condition 25 – General Transport, Access and Parking Condition 26 – Monitoring of Transport Network Congestion Condition 27 – Transport, Access and Parking: Specific Requirements (Britomart to Mayoral Drive) Condition 28 – Transport, Access and Parking: Specific Requirements (Karangahape Station Area) Condition 29 – Transport, Access and Parking: Specific Requirements (Newton Station Area) Condition 30 – Transport, Access and Parking: Specific Requirements (NAL Area) Noise and Vibration Condition 31 – Project Standards – Construction Noise Condition 32 – Project Standards – Blasting Noise Condition 33 – Project Standards – Construction Vibration Condition 34 – Project Standards – Construction Vibration (Amenity) Condition 35 – Project Standards – MediaWorks Condition 36 – Construction Noise and Vibration DWP Condition 37 – Site Specific Construction Noise Management Plan (SSCNMP) Condition 38 – Site Specific Construction Vibration Management Plan (SSCVMP) Condition 39 – Notable Noise and Vibration Receivers Condition 40 – Construct ion Noise and Vibration Management Plan – MediaWorks Built Heritage/Archaeology Condition 41 – Historic Character – Built Heritage Condition 42– Historic Character – Archaeology Condition 43 – Heritage Advisory Group and Composition Condition 44 – Heritage Advisory Group Function Condition 45 – Bluestone Wall Management Plan Building Condition Surveys Condition 46 – Process for Building Condition Surveys Urban Design Condition 47 – Urban Design Principles

City Rail Link Notice of Requirement

Page 7


Condition 48 – Mitigation Planting Requirements Condition 49 – Engagement with Mana Whenua and the Mana Whenua Principles Condition 50 – Specific Area Requirements: Britomart to Aotea Station Condition 51 – Specific Area Requirements: Karangahape Station area Condition 52 – Specific Area Requirements: Newton Station area Condition 53 – Specific Area Requirements: North Auckland Line area Condition 54 – Station Plan Requirements Trees and Vegetation Condition 55 – Trees and Vegetation DWP Public Art Condition 56 – Public Art DWP Contamination Condition 57 – Contamination DWP Condition 58 – Contamination Validation Report at Completion of Construction Air Quality Condition 59 – Air Quality DWP Social Impact and Business Disruption Condition 60 – Property Management Strategy Condition 61 – Social Impact and Business Disruption DWP Specific Design Requirements Condition 62 – Specific Design Requirements relating to 152 Vincent Street OPERATIONAL CONDITIONS Condition 63 – Operational Rail Vibration Condition 64 – Operational Noise – Mechanical Ventilation Plant Condition 65 – Operational Noise and Vibration Management Plan (ONVMP) Condition 66 – Operational Noise and Vibration Management – Mediaworks ADVICE NOTES APPENDIX ONE – Buildings for Consideration as to Building Condition Surveys APPENDIX TWO – Heritage Buildings for Consideration as to Building Condition Surveys

City Rail Link Notice of Requirement

Page 8


Requiring Authority Designation Conditions – Designation 3 Condition 1 Condition 2 Condition 3 Condition 4 Condition 5 ADVICE NOTES

City Rail Link Notice of Requirement

Page 9


Requiring Authority Designation Conditions – for Designations 1, 2, 4, 5 and 6

Condition Number

NoR Designati on Applies to

Condition

DEFINITIONS 1 2

Consult

4

Consulting

5

Consultation

6 1 4 5

Fully operational traffic lane

May include a traffic lane that is subject to a reduced speed limit, or one which may have a temporary reduction in the lane width, due to construction activity.

Two way access

Access into and out from a site or a road. This access may include restrictions (eg. left in, left out) where these are specified within the relevant conditions.

6 1 4 5 6

Receivers that undertake activities within spaces that rely on a particularly low noise and vibration environment. For these designations these spaces are defined as:

1 2 4 5

The process of providing information about the construction works, and receiving for consideration, information from stakeholders, directly affected and affected in proximity parties, regarding those effects and proposals for the management and mitigation of them.

Notable Noise and Vibration Receivers

6

Public Performance Theatres;

Recording Studios, both sound and television (including Mediaworks, except the specific spaces addressed by Condition 35);

In relation to sensitive equipment - Medical Facilities and Scientific Laboratories;

In relation to the requirement to record witness statements - The Auckland District Court in Albert Street

Receivers that may be disturbed during rest, concentration, communication or prayer. For these designations these include (but are not limited to): 1 2 4 5

Sensitive Noise and Vibration Receivers

6

1

Site Specific Construction

Dwellings

Offices

Schools, including Child Care Centres and tertiary facilities

Libraries

Hospitals

Rest Homes

Marae and other Cultural Centres

Churches

Hotels or other accommodation facilities

These include site specific construction noise management plans (SSCNMP), site specific construction vibration plans (SSCVMP), or a

City Rail Link Notice of Requirement

Page 10


Condition Number

NoR Designati on Applies to

2 4 5 6

Condition

Noise and Vibration Management Plans

1 2 4 5

Best practicable option

Has the meaning under the Resource Management Act 1991 and, for the purpose of these conditions, comprises the best practicable option for minimising the effects of any construction activity (including effects on the transport network or heritage values) on the receiver.

Historic Character

This includes heritage buildings, sites and places identified in the New Zealand Historic Places Trust register or in the Auckland Council District Plan (Isthmus or Central Area Sections) or as specifically identified in conditions.

6 1 2 4

combination of both noise and vibration in one plan (SSCNVMP) to address the effects from the construction activity on notable or sensitive receivers.

5 6

Mana whenua for the purpose of this designation are considered to be the following (in no particular order), who at the time of Notice of Requirement expressed a desire to be involved in the City Rail Link Project: 1 2 4

Mana Whenua

5 6

1 2 4

Material change

5 6

4 5 6

Ngati Maru

Ngati Paoa

Ngai Tai ki Tamaki

Ngati Te Ata

Ngati Whatua o Orakei

Te Akitai

Te Kawerau o maki

Ngati Tamaoho

Material change will include amendment to any base information informing the CEMP or other Plan or any process, procedure or method of the CEMP or other Plan which has the potential to materially increase adverse effects on a particular receiver. For clarity, changes to personnel and contact schedules do not constitute a material change. Delivery Work Plans will contain specific objectives and methods for avoiding, remedying or mitigating effects and address the following topics:

1 2

Delivery Work Plans

(a)

Transport, Access and Parking;

(b)

Construction noise and vibration;

(c)

Historic Character (including Archaeology);

(d)

Urban Design (including landscape and station plans);

(e)

Trees and vegetation;

City Rail Link Notice of Requirement

Page 11


Condition Number

NoR Designati on Applies to

Condition

(f)

Social Impact and Business Disruption;

(g)

Air quality;

(h)

Public Art; and

(i)

Contamination.

1 2 4 5

Peak Particle Velocity

The maximum component peak vibration level (in mm/s) measured in any of three orthogonal axes (vertical, transverse, longitudinal).

MediaWorks

MediaWorks means any television, radio and/or interactive media facilities which broadcast from the MediaWorks site (including any successor which conducts the same activities).

6 6

MediaWorks site means the properties at 2-3 Flower Street and 44-52 New North Road included within the following:

6

MediaWorks site

6

MediaWorks buildings

6

Studio 1

Lot 1 DP 84213

NA40B/1323

Lot 2 DP 49561

NA2063/54

Lot 4 Section 3 Deeds Plan 45(blue)

NA557/190

Part Lot 5 Section 3 Deeds Plan 45 Blue

NA557/144

Lot 1 DP 60771

NA15C/727

MediaWorks buildings means the buildings located at 2 Flower Street (Lot 2 DP 49561, NA2063/54), 3 Flower Street (Lot 1 DP 84213, NA40B/1323), 40 New North Road (Lot 1 DP 80372, NA37A/545), 44 New North Road (Lot 4 Section 3 Deeds Plan 45 (Blue), NA557/190), 4648 New North Road (Pt Lot 5 Section 3 Deeds Plan 45 (Blue), NA557/144), and 52 New North Road (Lot 1 DP 60771, NA15C/727). Studio 1 means the main broadcasting studio at the MediaWorks building at 3 Flower Street as shown on Diagram 1.

ABBREVIATIONS CEMP

Construction Environmental Management Plan

DWP

Delivery Work Plan

NoR

Notice of Requirement

ONVMP

Operational Noise and Vibration Management Plan

PPV

Peak Particle Velocity

SSCNVMP

Site Specific Noise and Vibration Management Plan

City Rail Link Notice of Requirement

Page 12


Condition Number

NoR Designati on Applies to

Condition

GENERAL CONDITIONS 1.1 The City Rail Link Project (City Rail Designations 1, 2, 4, 5 and 6) shall be undertaken in general accordance with the following, subject to final detailed design: (a) the information provided by the Requiring Authority in the Notice of Requirement dated 23 August 2012 and supporting documents (as updated by information provided by the Requiring Authority up until the close of the Hearing and during the course of Environment Court proceedings) being: (i) Assessment of Environmental Effects report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 15 August 2012 Rev B); (ii) Supporting environmental assessment reports (contained in Volume 3 of the Notice of Requirement suite of documents, dated August 2012); (iii) The Concept Design Report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3); (iv) Plan sets:

1 2 1

4 5 6

Land requirement plans (contained in Volume 1 of the Notice of Requirement suite of documents, dated 15 August 2012 and GIS4214293-100-10 Rev 5 as amended for 32 Normanby Road, dated 14 September 2015);

Plans contained in the Concept Design Report Appendices (contained in Volume 3 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3);

Plan CIV-000-DRG-0001 attached at Appendix 1 to these Conditions.

(v) Information provided in response to the Section 92 requests and/or in advance of the Council’s section 42A report, including the following: •

“City Rail Link Notice of Requirement: Social Impact Assessment” prepared by Beca Carter Hollings & Ferner Ltd (Beca), dated 19 April 2011 (approved for release 19 April 2013);

“City Rail Link – Supplementary Report: Traffic Modelling of Alternative Construction Scenarios” prepared by Flow Transportation Specialists Ltd, dated 22 May 2013.

(vi) Evidence (including supplementary evidence) provided prior to and at the Council hearing, including but not limited to: •

Statement of Evidence by Ian Clark (Transport) dated 2 July 2013;

“Drawing 0220, Revision B” dated 20 August 2013, being part of the City Rail Link Project: Mt Eden Worksite set by Aurecon, submitted as part of the Second Supplementary Statement of Evidence of William (Bill) Russell Newns for Auckland Transport;

“City Rail Link Notice of Requirement: Outline Plan Process and Environmental Management Plan System (Indicative)” prepared by Beca Carter Hollings & Ferner Ltd, dated 27 September 2013;

“City Rail Link: Indicative Communication and Consultation Plan” prepared by Auckland Transport, dated September 2013;

“Outline Social Impact and Business Disruption Delivery Work Plan” submitted as Attachment A to the Statement of Evidence of Amelia Joan Linzey (Beca Carter Hollings & Ferner Ltd), dated 26 September

City Rail Link Notice of Requirement

Page 13


Condition Number

NoR Designati on Applies to

Condition

2013. (vii) All material and evidence (including rebuttal evidence) provided by the Requiring Authority in the Environment Court proceedings (ENV-2014-AKL-000057). (b) Except as modified by the following alterations: (i) Assessment of Environmental Effects (Reference CRL-AOT-RME-000-0057), Design and Construction Report (Reference CRL-AOT-RME-000-0059 and Drawings CRL¬ SYW-RME-000- DWG-0025-0030 (‘Aotea Alteration’ - CRL Designation 1); and (ii) Assessment of Environmental Effects (Reference CRL-SYWRME-000-RPT-0065, Design and Construction Memorandum (Reference CRL-SYW- RME-000-MEM0002) and Drawings CRL-SYW- RME-000-DRG-0120 to 0124 and 0128 to 0132 ‘Strata / Sub-Strata Alteration (CRL Designation 2); and (iii) Assessment of Environmental Effects (Reference CRL-MTE-RME- 000-RPT-0060, Revision 7 dated 9/11/16), Design and Construction Memorandum (Reference CRL-MTE-RME-000-MEM-0001, dated 9/11/16) and Drawings CRL-SYW-RME000-DWGDRG-0101 Revision 1 dated 26/7/16, 0102 Revision 1 dated 26/7/16, 0110 Revision 1 dated 26/7/16 and 0133 Revision 1 dated 26/7/16 and CRL-EFCROA-000-DRG-1027 Revision 4 dated 30/6/16, 1028 Revision 4 dated 30/6/16 and 1127 Revision 2 dated 30/6/16 and CRL-EFC-CON-000-DRG- 0060 Revision 1 dated 20/6/16, 0061 Revision 1 dated 20/6/16, 0062 Revision 1 dated 20/6/16, 0063 Revision 1 dated 20/6/16 and 0064 Revision 1 dated 8/7/16)(‘Mt Eden Station Alteration’ - CRL Designation 6), Section 92 responses dated 20/12/16, 17/2/17 and 27/4/17; (iv) Assessment of Environmental Effects (Reference CRL-PAT-ENV-CON-PLN-003285, Revision 2 dated 19/12/17, Section 92 Responses dated 19/2/18. (v) Assessment of Environmental Effects (Reference CRL-KRD-RME-000-RPT-003, Revision 3.0 dated 2/5/17), Design and Construction Memorandum (Reference CRL-KRD-RME-000-MEM-0002 FINAL, Revision 0 dated 2/5/17) and Drawings CRL-SYW-RME-000-DRG-0134 Revision 2.0 dated 21/9/18 and 0135 Revision 2.0 dated 28/9/18 (Karangahape Station Alteration – CRL Designation 4), and Section 92 response dated 4/7/17, as amended to exclude any reference to the ventilation and emergency egress structures on Pitt Street and the temporary removal of canopies at 70-74 and 82-86 Pitt Street. For the avoidance of doubt these Pitt Street structures and canopy works at these locations no longer form part of the Karangahape Station Alteration. Temporary removal of canopies is limited to 55-59 and 61-65 Pitt Street and 9 Mercury Lane. 1.2 Where there is inconsistency between: (a) The documents listed above and these conditions, these conditions shall prevail; (b) The information and plans set out in conditions 1.1(a) and 1.1(b) lodged with the requirements and presented at the Council Hearing and during the course of Environment Court proceedings, the most recent information and plans shall prevail; (c) The indicative management plans and evidence presented at the Council Hearing and the management plans (DWPs, CEMP, etc) required by the conditions of these designations and submitted through an Outline Plan, the requirements of the management plans shall prevail. 2

1 2

2.1 In accordance with section 184(1) of the Resource Management Act 1991 (the RMA), these designations shall lapse if not given effect to within 15 10 years from the date on

City Rail Link Notice of Requirement

Page 14


Condition Number

NoR Designati on Applies to

4

Condition

which they are confirmed.

5 6 3.1 As soon as reasonably practicable, and no later than the point at which any part or parts of the City Rail Link become operational, the Requiring Authority shall: (a) Review the area and volume of land designated for the City Rail Link; (b) Identify any areas of designated land that are either no longer necessary for construction of the City Rail Link (if the City Rail Link has been constructed in part), or no longer necessary for the on-going operation and/or maintenance of the City Rail Link or for on-going mitigation measures; and (c) Give notice in accordance with Section 182 of the RMA for the removal of those parts of the designation identified in (b) above.

1 2 3

4 5 6

(d) Give notice in accordance with s182 of the RMA for the drawback of the CRL designation post construction where the CRL overlaps the North Auckland Line designation (Auckland Unitary Plan reference 6300) as follows: (i) Between 4 Haultain Street and 5 Fenton Street north and south (Identification reference 7 on drawing CRL-SYW-RME-000-DRG-0104 Revision 1 dated 26/7/16); (ii) Between 49-51 Boston Road and Severn Street (Identification references 1, 2 and 3 on drawing CRL-SYW-RME-000-DRG-0101 Revision 1 dated 26/7/16; (iii) At 14-22 Boston Road (Identification references 5 on drawing CRL-SYW-RME000-DRG-0101 Revision 1 dated 26/7/16); (iv) At 11 Water Street (Identification reference 6 on drawing CRL-SYW-RME-000DRG-0101 Revision 1 dated 26/7/16); (v) At 26 and 28 Mt Eden Road (Identification references 5 and 6 on drawing CRLSYW-RME-000-DRG-0103 Revision 1 dated 26/7/16); (vi) Over road reserve at Normanby Road between Lauder Road and Boston Road to reflect the Normanby Road overbridge (Identification reference 2 on drawing CRL-SYW-RME-000-DRG-0103 Revision 1 dated 26/7/16); and (vii) At Porters Ave to reflect the location of signalling infrastructure (Identification reference 8 on drawing CRL-SYW-RME-000-DRG-0104 Revision 1 dated 26/7/16).

PRE-CONSTRUCTION CONDITIONS Appointment of Communication and Consultation Manager

4

1 2 4 5 6

4.1 Within three months of the confirmation of the designation the Requiring Authority shall appoint a Communication and Consultation Manager to implement the Pre-construction Communication and Consultation Plan (Condition 5). The Communication and Consultation Manager shall be the main and readily accessible point of contact for persons affected by or interested in the City Rail Link Project until the commencement of the construction phase of the Project, or the contact person under Condition 14 is appointed. 4.2 The Communication and Consultation Manager’s contact details (or, if appointed under Condition 14, that contact persons details) shall be listed in the Pre-construction Communication and Consultation Plan and listed on the Requiring Authority website, the City Rail Link Website, and the Auckland Council website.

City Rail Link Notice of Requirement

Page 15


Condition Number

NoR Designati on Applies to

Condition

Pre-Construction Communication and Consultation Plan 5.1 The objective of the Pre-construction Communication and Consultation Plan is to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties and affected in proximity parties prior to the commencement of construction of the City Rail Link. 5.2 The Requiring Authority shall prepare a Pre-Construction Communication and Consultation Plan. This Plan shall be submitted to Auckland Councils Major Infrastructure Projects Team Manager, within 2 months of the Designation being confirmed, for confirmation that the Plan has been prepared in accordance with this condition. 5.3 The Plan shall be implemented and complied with within 3 months from the confirmation of the designations until the commencement of the construction of the City Rail Link. 5.4 This Plan shall set out recommendations and requirements (as applicable) that should be adopted by and/or inform the development of the CEMP and DWPs. 5.5 The Pre-construction Communication and Consultation Plan shall set out how the Requiring Authority will: (a) Inform the community of Project progress and likely commencement of construction works and programme; (b) Engage with the community in order to foster good relationships and to provide opportunities for learning about the Project;

5

1 2 4 5 6

(c) Obtain (and specify reasonable timeframes for) feedback and input from Stakeholders, directly affected and affected in proximity parties regarding the development of the CEMP and DWPs; (d) Respond to queries and complaints. Information shall include but not be limited to: (i) Who is responsible for responding; (ii) How responses will be provided; (iii) The timeframes that the responses will be provided within. (e) Where feedback (in accordance with this condition) is provided, the Pre-construction Communication and Consultation Plan shall articulate how that feedback has informed the development of the CEMP and DWPs and where it has not, reasons why it hasn’t; (f) Provide updates on the property acquisition process as well as the management strategy for properties acquired by the Requiring Authority for the construction of the City Rail Link. 5.6 The Pre-Construction Communication and Consultation Plan shall be prepared in consultation with Stakeholders, directly affected parties and affected in proximity parties including, but not limited to: (a) All property owners and occupiers (including, subject to Condition 61.5, sub lessees) identified within the designation footprint; (b) All property owners and occupiers adjacent to construction sites (Britomart and Albert Street (Designation 1), Karangahape Road (Designation 4), Newton Station (Designation 5), and the main construction site including grade separation works at Normanby Road and Porters Ave (Designation 6)); (c) New Zealand Historic Places Trust (NZHPT); (d) Department of Corrections; (e) Ministry of Justice;

City Rail Link Notice of Requirement

Page 16


Condition Number

NoR Designati on Applies to

Condition

(f) MediaWorks; (g) Network Utility Operators; (h) Bear Park Early Childhood Centre; (i) Body Corporate 164980 & Tenham Investments Limited (j) Community Liaison Group(s) (refer Condition 7); 5.7 The Pre-construction Communication and Consultation Plan shall, as a minimum, include: (a) A communications framework that details the Requiring Authority’s communication strategies, the accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc.), and any other relevant communication matters; (b) Details of the Communication and Consultation Manager for the pre-construction period (Condition 4 of this designation) including their contact details (phone, email and postal address); (c) The methods for identifying, communicating and consulting with stakeholders, directly affected parties and affected in proximity parties and other interested parties. Such methods shall include but not be limited to: (i) Newsletters; (ii) Newspaper advertising; (iii) Notification and targeted consultation with stakeholders, affected parties and affected in proximity parties; and (iv) The use of the project website for public information. (d) The methods for identifying, communicating and consulting with the owners of 1 Queen Street (HSBC House) and 21 Queen Street (Zurich House) regarding the development of the City Rail Link design and construction methodology between Britomart Transport Centre and Customs Street (through the Downtown Shopping Centre site). (e) The methods for communicating and consulting with mana whenua for the implementation of mana whenua principles for the project (refer to condition 8 and 48); (f) The methods for communicating and consulting with the Community Liaison Group(s); (g) How communication and consultation activity will be recorded; and (h) Methods for recording reasonably foreseeable future planned network utility works so that these can be considered and incorporated, where appropriate, into the City Rail Link design. 5.8 The Pre-construction Communication and Consultation Plan will be publicly available once finalised and for the duration of construction. 1 2 6

4 5 6

Network Utility Operators 6.1 Under s 176(1)(b) of the Resource Management Act 1991 (RMA) no person may do anything in relation to the designated land that would prevent or hinder the City Rail Link, without the prior written consent of the Requiring Authority. 6.2 In the period before construction begins on the City Rail Link (or a section thereof), the following activities undertaken by Network Utility Operators will not prevent or hinder the City Rail Link, and can be undertaken without seeking the Requiring Authority’s

City Rail Link Notice of Requirement

Page 17


Condition Number

NoR Designati on Applies to

Condition

written approval under section 176(1)(b) of the RMA: (a) Maintenance and urgent repair works of existing Network Utilities; (b) Minor renewal works to existing Network Utilities necessary for the on-going provision or security of supply of Network Utility Operations; (c) Minor works such as new property service connections; (d) Upgrades to existing Network Utilities within the same or similar location with the same or similar effects on the City Rail Link designation. 6.3 For the avoidance of doubt, in this condition an “existing Network Utility” includes infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with this condition or the section 176(1)(b) RMA process. Community Liaison Groups 7.1 Within three months of the confirmation of the designations the Requiring Authority shall, in consultation with the Auckland Council, establish at least one Community Liaison Group in each of the following key construction areas: (a) Britomart and Albert Street (Designation 1) (b) Karangahape Road (Designation 4) (c) Newton Station (Designation 5) (d) Main Construction site (Designation 6) 7.2 The number of Groups shall be confirmed with the Auckland Council. 7.3 The membership of the Community Liaison Group(s) shall include representative(s) of the Requiring Authority and be open to all directly affected and affected in proximity parties to the Project including, but not limited to the following:

7

1 2 4 5 6

(a) Representative(s) for and/or directly affected and affected in proximity property owners and occupiers; (b) CBD Residents Advisory Group; (c) The Karangahape Road Business Association; (d) Eden Terrace Business Association; (e) Heart of the City; (f) Roman Catholic Diocese of Auckland; (g) St Patrick’s Cathedral; and (h) St Benedict’s Parish. 7.4 In addition to the requirements in Condition 5, the purpose of the Groups shall be to: (a) Provide a means for receiving regular updates on Project progress; (b) Monitor the effects of constructing the Project on the community by providing a regular forum through which information about the Project can be provided to the community. (c) Enable opportunities for concerns and issues to be reported to and responded by the Requiring Authority. (d) Provide feedback on the development of the CEMP and DWPS. (e) Proposed potential joint initiatives to the Requiring Authority for the Property Management Strategy regarding the interim use of properties including vacant land

City Rail Link Notice of Requirement

Page 18


Condition Number

NoR Designati on Applies to

Condition

acquired for the construction of the City Rail Link. 7.5 The Requiring Authority will consult with the Groups in respect of the development of the CEMP and DWPs. 7.6 The Requiring Authority will appoint one or more persons appropriately qualified in community consultation as the Community Consultation Advisor(s) to: (a) Provide administrative assistance to the Groups; (b) Ensure the Groups are working effectively (including the development of a Code of Conduct) and appropriate procedures for each Group; and (c) Act as a community consultation advisor to the Group. 7.7 The Requiring Authority will use its best endeavours to ensure that the Groups meet at least annually until the commencement of construction and then at least once every three months or as otherwise required once construction commences. 7.8 Once construction has commenced the Requiring Authority will provide an update at least every three months (or as otherwise agreed) to the Groups on compliance with the designation conditions and the CEMP and DWP and any material changes to these plans. 7.9 The Requiring Authority shall provide reasonable administrative support for the Groups including organising meetings at a local venue, inviting all members of the Groups, as well as the taking and dissemination of meeting minutes. 7.10 The Groups shall continue for the duration of the construction phase of the Project and for six months following completion of the Project. Mana Whenua Consultation 8.1 Within three months of the confirmation of the designations the Requiring Authority shall establish a kaitiaki or mana whenua forum to provide for an on-going role in the design and construction of the CRL Project. 8.2 The frequency at which the forum meets shall be agreed between the Requiring Authority and mana whenua. 8.3 The role of the mana whenua forum may include the following: (a) Developing practical measures to give effect to the principles in the Urban Design DWP (refer to Condition 49);

8

1

(b) Input into, where practicable, the design of the stations (refer to Condition 54);

2

(c) Input into the preparation of the CEMP and DWPs;

4

(d) Working collaboratively with the Requiring Authority around built heritage and archaeological matters;

5 6

(e) Undertaking kaitiakitanga responsibilities associated with the City Rail Link Project, including monitoring, assisting with discovery procedures, and providing mÄ tauranga MÄ ori input in the relevant stages of the Project; and (f) Providing a forum for consultation with mana whenua regarding the names for the City Rail Link stations, noting that there may be formal statutory processes outside the project (such as the New Zealand Geographic Board) which may be involved in any decision making on station names. 8.4 The mana whenua forum may provide written advice to the Requiring Authority in relation to any of the above matters. The Requiring Authority must consider this advice and the means by which any suggestions may be incorporated in the City Rail Link project.

9

1

Network Utility Operator Liaison

City Rail Link Notice of Requirement

Page 19


Condition Number

NoR Designati on Applies to

2 4 5 6

Condition

9.1 The Requiring Authority and its contractor shall: (a) Work collaboratively with Network Utility Operators during the development of the further design for the City Rail Link to provide for the ongoing operation and access to network Utility operations; (b) Undertake communication and consultation with Network Utility Operators as soon as reasonably practicable, and at least once prior to construction timing being confirmed and construction methodology, and duration being known; and (c) Work collaboratively with Network Utility Operators during the preparation and implementation of the CEMP (Condition 24) and DWPs in relation to management of adverse effects on Network Utility Operations. 9.2 A summary of the communication and consultation undertaken between the Requiring Authority and Network Utility Operators prior to construction commencing shall be provided as part of the Outline Plan. 9.3 The Requiring Authority shall undertake on-going communication and consultation with Network Utility operators throughout the duration of construction, including in relation to changes envisaged by Conditions 22 and 23 affecting Network Utility Operations to ascertain whether or not any changes or updates to the CEMP Network Utilities section are required to address unforeseen effects.

CONSTRUCTION CONDITIONS Outline Plan Requirements 10.1 The Requiring Authority shall submit an Outline Plan to the Auckland Council for the construction of the City Rail Link in accordance with section 176A of the RMA. The Outline Plan shall include: (a) The Communication and Consultation Plan (Condition 15); (b) The Construction Environmental Management Plan (CEMP); (c) Delivery Work Plans (DWPs); (d) Site Specific Construction Noise/Vibration Management Plans (SSCNVMPs) and Notable Receiver Management Plans; and 1 2 10

4 5 6

(e) Any other information required by the conditions of this designation associated with the construction of the City Rail Link. 10.2 The plans listed in Condition 10.1 above must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, and any recommendations received as part of the Independent Peer Review Panel process (where applicable), along with a clear explanation of where any affected party comments or peer review recommendations have not been incorporated, and the reasons why not. 10.3 The Requiring Authority may choose to give effect to the designation conditions associated with the construction of the City Rail Link: (a) Either at the same time or in parts; (b) By submitting one or more: (i) Communication and Consultation Plans; (ii) CEMP; (iii) DWPs; and (iv) SSCNVMPs, SSCNMPs and SSCVMPs

City Rail Link Notice of Requirement

Page 20


Condition Number

NoR Designati on Applies to

Condition

10.4 These plans should clearly show how the part integrates with adjacent City Rail Link construction works and interrelated activities. This particularly applies where the Urban Design DWP is submitted as a number of plans. 10.5 Early engagement will be undertaken with Auckland Council in relation to preparation and submission of the Outline Plan to establish a programme for the Outline Plan process to ensure achievable timeframes for both parties. 10.6 All works shall be carried out in accordance with the Outline Plan(s) required by this condition. Independent Peer Review of CEMP and DWPs 11.1 Prior to submitting the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) to Auckland Council for the construction of the City Rail Link, the Requiring Authority shall engage suitably qualified independent specialists agreed to by Auckland Council to form an Independent Peer Review Panel. The purpose of the Independent Peer Review Panel is to undertake a peer review of the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39), and provide recommendations on whether changes are required to those plans in order to meet the objective and other requirements of these conditions. 1 2 11

4 5 6

11.2 The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) must clearly document the comments and inputs received by the Requiring Authority during its consultation with stakeholders, affected parties and affected in proximity parties, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) provided to both the independent peer reviewer and Auckland Council as part of this condition. 11.3 The CEMP, DWPs, SSCNMPs and SSCVMPs (other than those prepared in accordance with Condition 39) submitted to Auckland Council shall demonstrate how the recommendations from the independent peer reviewers have been incorporated, and, where they have not, the reasons why not. 11.4 In reviewing an Outline Plan submitted in accordance with these designation conditions, Auckland Council shall take into consideration the independent specialist peer review undertaken in accordance with this condition and any additional information provided to Auckland Council by affected parties. Availability of Outline Plan(s)

1 2 12

4 5 6

13

12.1 For the duration of construction the following plans and any material changes to these plans shall be made available for public viewing on the Project web site: (a) CEMP; (b) DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs); and (c) Communication and Consultation Plan. 12.2 A copy of these Plans will also be held and made available for viewing at each construction site.

1

Monitoring of Construction Conditions

2

13.1 The Requiring Authority, its contractor team, and the Auckland Council Consent Monitoring officer(s) shall establish and implement a collaborative working process for dealing with day to day construction processes, including monitoring compliance with the designation conditions and with the CEMP and DWPs (including SSCNVMPs, SSCNMPs and

4 5

City Rail Link Notice of Requirement

Page 21


Condition Number

NoR Designati on Applies to

6

Condition

SSCVMPs) and any material changes to these plans associated with construction of the City Rail Link. 13.2 This collaborative working process shall: (a) Operate for the duration of the construction works and for 6 months following completion of construction works where monitoring of designation conditions is still required, unless a different timeframe is mutually agreed between the Requiring Authority and the Auckland Council; (b) Have a “key contact” person representing the Requiring Authority and a “key contact” person representing the contractor team to work with the Auckland Council Consent Monitoring officer(s); (c) The “key contacts” shall be identified in the CEMP and shall meet at least monthly unless a different timeframe is agreed with the Auckland Council Consent Monitoring officer(s). The purpose of the meeting is to report on compliance with the designation conditions and with the CEMP, DWPs and material changes to these plans and on any matters of non-compliance and how they have been addressed; (d) Once construction has commenced, the Requiring Authority and / or the contractor shall provide an update to the Community Liaison Groups (Condition 7 of this designation) at least once every 3 months, or if in accordance with Condition 7 these groups meet more regularly, at least once every two months. 13.3 The purpose and function of the collaborative working process is to: (a) Assist as necessary the Auckland Council Consent Monitoring officer(s) to confirm that: (i) The works authorised under these designations are being carried out in compliance with the designation conditions, the CEMP, DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and any material changes to these plans; (ii) The Requiring Authority and its contractor are undertaking all monitoring and the recording of monitoring results in compliance with the requirements of the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and any material changes to these plans; (b) Subsequent to a confirmed Outline Plan, provide a mechanism through which any changes to the design, CEMP or DWPs, which are not material changes requiring approval under Condition 10 triggering the requirement for a new Outline Plan, can be required, reviewed and confirmed; (c) Advise where changes to construction works following a confirmed Outline Plan require a new CEMP or DWP (including SSCNVMPs, SSCNMPs and SSCVMPs); (d) Review and identify any concerns or complaints received from, or related to, the construction works monthly (unless a different timeframe is mutually agreed with the Auckland Council Consent Monitoring officer) and adequacy of the measures adopted to respond to these.

Communication and Consultation Contact Person

14

1 2 4 5 6

15

1

Communication and Consultation Plan

14.1 The Requiring Authority shall make a contact person available 24 hours seven days a week for the duration of construction for public enquiries on the construction works.

City Rail Link Notice of Requirement

Page 22


Condition Number

NoR Designati on Applies to

2 4 5 6

Condition

15.1 The objective of the Communication and Consultation Plan is to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties and affected in proximity parties during the construction of the City Rail Link. 15.2 The Requiring Authority shall prepare a Communication and Consultation Plan which shall be implemented and complied with for the duration of the construction of the City Rail Link. 15.3 The Communication and Consultation Plan shall set out how the Requiring Authority will: (a) Inform the community of construction progress and future construction activities and constraints that could affect them; (b) Provide early information on key Project milestones; (c) Obtain and specify a reasonable timeframe (being not less than 10 working days), for feedback and inputs from directly affected and affected in proximity parties regarding the development (as part of the review process provided by Condition 22) and implementation of the CEMP or DWPs (including SSCNVMPs, SSNMPs and SSCVMPs); and (d) Respond to queries and complaints including but not limited to: (i) Who is responsible for responding; (ii) How responses will be provided; (iii) The timeframes that responses will be provided within. 15.4 The Communication and Consultation Plan shall as a minimum include: (a) A communications framework that details the Requiring Authority’s communication strategies, the accountabilities, frequency of communications and consultation, the range of communication and consultation tools to be used (including any modern and relevant communication methods, newsletters or similar, advertising etc), and any other relevant communication matters; (b) The Communication and Consultation Manager for the Project including their contact details (phone, email and postal address); (c) The methods for identifying, communicating and consulting with persons affected by the project including but not limited to: (i) All property owners and occupiers within the designation footprint (ii) All property owners and occupiers adjacent to construction sites (Britomart and Albert Street (Designation 1), Karangahape Road (Designation 4), Newton Station (Designation 5), Main Construction site and the works at Normanby Road and Porters Ave (Designation 6)) (iii) New Zealand Historic Places Trust (NZHPT) (iv) Department of Corrections (including the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road) (v) Ministry of Justice (including but not limited to) confirming the details of the contact person required under Condition 14 of this designation, and to provide appropriate details (including but not restricted to timing, duration, scale, noise effects, vibration effects, access restrictions, and disruption to utilities) in respect to any works impacting the operation of the Auckland District Court at 65-71 Albert Street, Auckland. Communication and consultation of such details should be provided to the Ministry of Justice Auckland Property Programme

City Rail Link Notice of Requirement

Page 23


Condition Number

NoR Designati on Applies to

Condition

Manager at least 9 months prior to the commencement of such works. (vi) Media Works (vii) Community Liaison Group(s) (refer Condition 7); (viii) Bear Park Early Childhood Centre; (ix) Body Corporate 164980 and Tenham Investments Ltd; (x) Network Utility Operators, including the process: •

To be implemented to capture and trigger where communication and consultation is required in relation to any material changes affecting the Network Utilities;

For the Requiring Authority to give approval (where appropriate) to Network Utility Operators as required by section 176(1)(b) of the RMA during the construction period;

For obtaining any supplementary authorisations (including but not limited to resource consents (including those required under a National Environmental Standard) and easements);

For inspection and final approval of works by Network Utility Operators; and

For implementing conditions 9, 22, 23, and 24 of this designation in so far as they affect Network Utility Operations.

(xi) The owner of 4 Kingston Street (xii) The owner of 6-12 Kingston Street (xiii) The owner of 83 Albert Street (xiv) The owner(s) of 5 Porters Avenue (ALLOT 236 SEC 10 Suburbs AUCKLAND) (d) How stakeholders and persons affected by the project will be notified of the commencement of construction activities and works, the expected duration of the activities and works, and who to contact for any queries, concerns and complaints; (e) How stakeholders and persons affected by the project will be consulted in the development and review of the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs), including specifying reasonable timeframes for feedback; (f) Methods for communicating in advance temporary traffic management measures and permanent changes to road networks and layouts to directly affected and in proximity parties, bus (public and private) operators, taxi operators, bus users, and the general public; (g) Methods for communicating in advance to surrounding communities (including sensitive noise and vibration receivers) which must be notified at least 24 hours in advance where construction activities are predicted to: (i) Exceed the noise limits (refer Condition 31); or (ii) Exceed a vibration limit (refer Conditions 33 and 34); or (iii) Be within 200m of a blast site (refer Condition 32). Further provisions for Notable Noise and Vibration Receivers are contained in Condition 16. (h) Methods for communicating in advance proposed hours of construction activities outside of normal working hours and on weekends and public holidays, to surrounding communities, and methods to record and deal with concerns raised about such hours; (i) Methods for communicating and consulting with mana whenua for the duration of

City Rail Link Notice of Requirement

Page 24


Condition Number

NoR Designati on Applies to

Condition

construction and implementation of mana whenua principles for the project (refer to Conditions 8 and 49); (j) Methods for communicating and consulting with the Auckland Council Parks Department regarding works to be undertaken to any trees on public land (streets, squares, etc.) located within the City Rail Link surface designation footprint, including how trees not being removed, or in close proximity to the surface designation footprint where works are occurring, will be protected; (k) Methods for communicating and consulting in advance of construction works with emergency services (Police, Fire, Ambulance) on the location, timing and duration of construction works, and particularly in relation to temporary road lane reductions and/or closures and the alternative routes or detours to be used, with specific detail around the management of the Fire and Ambulance from their central stations on Pitt Street; (l) A list of Stakeholders, directly affected and affected in proximity parties to the construction works who will be communicated with; (m) How communication and consultation activity relating to construction activities and monitoring requirements will be recorded; and (n) Methods for communicating and consulting with the Department of Corrections (including the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road), to confirm the details of the contact person required under Condition 14 of this designation, and in respect of any works impacting on access or works in proximity to the Mt Eden Corrections Facility and the Boston Road Community Corrections site; including temporary traffic management measures and permanent changes to road networks and layouts which may impact on access to and from the Facility and the motorway network. 15.5 The Communication and Consultation Plan shall also include (as relevant) linkages and cross-references to the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs). 15.6 The Communication and Consultation Plan shall include a summary of the communication and consultation undertaken between the Requiring Authority and parties as required by the Pre-construction Communication and Consultation Plan. The summary shall include any outstanding issues or disputes raised by parties. The Communication and Consultation Plan shall be reviewed six monthly for the duration of construction and updated if required. Any updated Communication and Consultation Plan shall be provided to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for review and agreement on any further action to be undertaken. Any further action recommended as a result of this review shall be undertaken by the Communication and Consultation Manager for the City Rail Link and confirmation of completion provided back to the Auckland Council Consent Monitoring officer. 15.7 If, in the course of amendments undertaken as part of the review process, a material change to the Communication and Consultation Plan is made, those parties affected by the change shall be notified within 1 month of the material change occurring. Communications – Notable Noise and Vibration Receivers 1 16

4 5 6

16.1 A SSCNVMP shall be prepared for all Notable Noise and Vibration Receivers (refer Condition 39). As part of the SSCNVMP (and further to Condition 15 of this designation), the Requiring Authority shall undertake communication and consultation, as soon as reasonably practicable (and at least once following confirmation of construction timing and methodology), with any Notable Noise and Vibration Receivers located within 200 metres of blasting, or within 100 metres (either horizontally or vertically) of the

City Rail Link Notice of Requirement

Page 25


Condition Number

NoR Designati on Applies to

Condition

designation footprint for other construction activities. Communication and consultation with these parties should focus on a collaborative approach to manage the adverse effects from construction noise and vibration while works are undertaken in the vicinity. 16.2 The Requiring Authority shall undertake on-going communication and consultation with notable noise and vibration receivers throughout the duration of construction occurring in the vicinity. This communication shall be reported back to the “key contacts” (see Condition 13) and the Auckland Council Consent Monitoring officer for their review and confirmation of any further action to be undertaken. The Auckland Council Consent Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving this information from the Requiring Authority. Concerns and Complaints Management 17.1 Upon receiving a concern or complaint during construction, the Requiring Authority shall instigate a process to address concerns or complaints received about adverse effects. This shall: (a) Identify of the nature of the concern or complaint, and the location, date and time of the alleged event(s); (b) Acknowledge receipt of the concern or complaint within 24 hours of receipt; (c) Respond to the concern or complaint in accordance with the relevant management plan , which may include monitoring of the activity by a suitably qualified expert, implementation of mitigation measures, and, in the case of noise and / or vibration, preparation of a site specific noise and / or vibration management plan (in accordance with Conditions 37 and 38); 17.2 A record of all concerns and / or complaints received shall be kept by the Requiring Authority. This record shall include: 1 2 17

4 5 6

(a) The name and address of the person(s) who raised the concern or complaint (unless they elect not to provide this) and details of the concern or complaint; (b) Where practicable, weather conditions at the time of the concern or complaint, including wind direction and cloud cover if the complaint relates to noise or air quality; (c) Known City Rail Link construction activities at the time and in the vicinity of the concern or complaint; (d) Any other activities in the area unrelated to the City Rail Link construction that may have contributed to the concern or complaint such as non-City Rail Link construction, fires, traffic accidents or unusually dusty conditions generally; (e) Remedial actions undertaken (if any) and the outcome of these, including monitoring of the activity. 17.3 This record shall be maintained on site, be available for inspection upon request, and shall be provided every two months (or as otherwise agreed) to the Auckland Council Consent Monitoring officer, and to the “key contacts” (see Condition 13). 17.4 Where a complaint remains unresolved or a dispute arises, the Auckland Council Compliance Monitoring Officer will be provided with all records of the complaint and how it has been dealt with and addressed and whether the Requiring Authority considers that any other steps to resolve the complaint are required. Upon receiving records of the complaint the Auckland Council Compliance Monitoring Officer must determine whether a review of the CEMP and/or DWPs is required under Condition 22 to address this complaint. The Auckland Council Compliance Monitoring Officer shall advise the Requiring Authority of its recommendation within 10 working days of receiving the

City Rail Link Notice of Requirement

Page 26


Condition Number

NoR Designati on Applies to

Condition

records of complaint. “One Network� Consultation 1 18

4 5 6

18.1 The Requiring Authority and its contractor shall work collaboratively with the New Zealand Transport Agency (NZTA) during the preparation of the Traffic, Access and Parking DWP (Conditions 25, 27, 28, 29, and 30) in relation to confirming the management of adverse transport effects on the road network. A record of this consultation and outcomes shall be included in the Traffic, Access and Parking DWP. The Requiring Authority shall consult with the NZTA throughout the duration of construction on any changes or updates to the Traffic, Access and Parking DWP which relate to the management of the road network.

Construction Environmental Management Plan (CEMP) and Delivery Work Plans (DWPs) Preparation, Compliance and Monitoring 19.1 The objective of the CEMP and DWPs is to so far as is reasonably practicable, avoid, remedy or mitigate any adverse effects (including cumulative effects) associated with the City Rail Link construction.

19

1 2 4 5 6

19.2 All works must be carried out in accordance with the CEMP, the DWPs required by these conditions and in accordance with any changes to plans made under Condition 23. 19.3 The CEMP and DWPs shall be prepared, complied with and monitored by the Requiring Authority throughout the duration of construction of the City Rail Link. 19.4 The DWPs shall give effect to the specific requirements and objectives set out in these designation conditions. 19.5 The CEMP shall include measures to give effect to any specific requirements and objectives set out in these designation conditions that are not addressed by the DWPs. 19.6 Where mitigation measures are required to be implemented by the Requiring Authority in relation to the construction of City Rail Link, it shall meet reasonable and direct costs of implementing such mitigation measures. CEMP Requirements 20.1 In order to give effect to the objective in Condition 19.1, the CEMP must provide for the following: (a) In relation to Designation 2, the use of one Tunnel Boring Machine (unless the effects of using more than one Tunnel Boring Machine are not materially different from those associated with the use of one Tunnel Boring Machine);

20

1 2 4 5 6

(b) Notice boards that clearly identify the Requiring Authority and the Project name, together with the name, telephone number and email address of the Site or Project Manager and the Communication and Consultation Manager; (c) Training requirements for employees, sub-contractors and visitors on construction procedures, environment management and monitoring; (d) A Travel Management Plan for each construction site outlining onsite car parking management and methods for encouraging travel to the site using forms of transport other than private vehicle to assist in mitigating localised traffic effects; and (e) Where a complaint is received, the complaint must be recorded and responded to as provided for in Conditions 13, 15 and 17. 20.2 The CEMP shall include details of: (a) The site or Project Manager and the Communication and Consultation Manager (who will implement and monitor the Communication and Consultation Plan), including

City Rail Link Notice of Requirement

Page 27


Condition Number

NoR Designati on Applies to

Condition

their contact details (phone, email and physical address); (b) The Document management system for administering the CEMP, including review and Requiring Authority / Constructor / Auckland Council requirements; (c) Environmental incident and emergency management procedures; (d) Environmental complaint's management procedures (see also Condition 17); (e) An outline of the construction programme of the work, including construction hours of operation, indicating linkages to the DWPs which address the management of adverse effects during construction; (f) Specific details on demolition to be undertaken during the construction period; (g) Means of ensuring the safety of the general public; and (h) Methods to assess and monitor potential cumulative adverse effects. 20.3 Subject to any alternative agreement with the landowner(s) of HSBC House and Zurich House, the Requiring Authority shall prepare specific construction methodologies for the works adjacent to 1 Queen Street and 21 Queen Street detailing how they will be undertaken to avoid compromising the structural integrity of the existing structures on the site including their foundation systems. The specific construction methodologies shall be prepared in consultation with the owner(s) of these properties. A record of this liaison and outcomes shall be included in the CEMP as part of the Outline Plan. This summary must provide a clear explanation of where any comments have not been incorporated into the CEMP, and the reasons why not. This summary must be provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process. CEMP Construction Works Requirements 21.1 In order to give effect to the objective in Condition 19.1, the CEMP shall include the following details and requirements in relation to all areas within the surface designation footprint where construction works are to occur, and / or where materials and construction machinery are to be used or stored: (a) Where access points are to be located and procedures for managing construction vehicle ingress and egress to construction support and storage areas; (b) Methods for managing the control of silt and sediment within the construction area;

21

1 4 5 6

(c) Methods for earthworks management (including depth and extent of earthworks and temporary, permanent stabilisation measures and monitoring of ground movement) for earthworks adjacent to buildings and structures; (d) Measures to adopt to keep the construction area in a tidy condition in terms of disposal / storage of rubbish and storage unloading of construction materials (including equipment). All storage of materials and equipment associated with the construction works shall take place within the boundaries of the designation; (e) Measures to ensure all temporary boundary / security fences associated with the construction of the City Rail Link are maintained in good order with any graffiti removed as soon as possible; (f) For the duration of construction affecting Lower Queen Street or Queen Elizabeth II Square, construction fences and / or hoardings shall be placed no closer than 3 metres from the north frontage (building frontage onto Queen Elizabeth II Square) of 21 Queen Street in the vicinity of the entrance to the ground level retail space and the main pedestrian entrance to the building. (g) The location and specification of any temporary acoustic fences and visual barriers, and where practicable, opportunities for mana whenua (see Condition 8) and

City Rail Link Notice of Requirement

Page 28


Condition Number

NoR Designati on Applies to

Condition

community art or other decorative measures along with viewing screens to be incorporated into these without compromising the purpose for which these are erected; (h) How the construction areas are to be fenced and kept secure from the public and, where practicable and without compromising their purpose how opportunities for public viewing, including provision of viewing screens and display of information about the project and opportunities for mana whenua and community art or other decorative measures can be incorporated to enhance public amenity and connection to the project; (i) The location of any temporary buildings (including workers offices and portaloos) and vehicle parking (which should be located within the construction area and not on adjacent streets); (j) Methods to control the intensity, location and direction of artificial construction lighting to avoid light spill and glare onto sites adjacent construction areas; (k) Methods to ensure the prevention and mitigation of adverse effects associated with the storage, use, disposal, or transportation of hazardous substances; (l) That onsite stockpiling of spoil or fill at Downtown and Lower Albert Street construction yards be minimised where practicable; (m) That site offices and less noisy construction activities be located at the edge of the construction yards where practicable; and (n) Methods for management of vacant areas once construction is completed in accordance with the Urban Design DWP. 21.2 Unless expressly agreed in writing with the landowner of the Downtown Shopping Centre (at 7 Queen Street): (a) the Downtown construction yard (including QEII Square, Downtown Shopping Centre and Lower Albert Street), shall be progressively released from occupation for construction purposes where the area or any part of the area is no longer required for construction of the section of CRL between Britomart and Wyndham Street; and (b) following completion of the section of the CRL between the Downtown Shopping Centre and Wyndham Street and reinstatement of Albert Street, Lower Albert Street shall not be occupied for construction purposes for any section of CRL south of Wyndham Street. Review Process for CEMP and DWPs 22.1 The CEMP and DWPs shall be reviewed at least annually or as a result of a material change to the City Rail Link project or to address unforeseen adverse effects arising from construction or unresolved complaints. Such a review may be initiated by either Auckland Council or the Requiring Authority. The review shall take into consideration: 22

1 2 4 5 6

(a) Compliance with designation conditions, the CEMP, DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs) and material changes to these plans; (b) Any changes to construction methods; (c) Key changes to roles and responsibilities within the City Rail Link project; (d) Changes in industry best practice standards; (e) Changes in legal or other requirements; (f) Results of monitoring and reporting procedures associated with the management of adverse effects during construction; (g) Any comments or recommendations received from Auckland Council regarding the

City Rail Link Notice of Requirement

Page 29


Condition Number

NoR Designati on Applies to

Condition

CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs); and (h) Any unresolved complaints and any response to the complaints and remedial action taken to address the complaint as required under Condition 17. 22.2 A summary of the review process shall be kept by the Requiring Authority, provided annually to the Auckland Council, and made available to the Auckland Council upon request. Update of CEMP and DWPs following Review 23.1 Following the CEMP and DWPs review process described in Condition 22, the CEMP may require updating. 23.2 Any material change to the CEMP and DWP must be consistent with the purpose and objective of the relevant condition.

23

1 2 4 5 6

23.3 Affected parties will be notified of the review and any material change proposed to the CEMP and DWPs (including SSCNVMPs, SSCNMPs and SSCVMPs). 23.4 The CEMP and DWPs must clearly document the comments and inputs received by the Requiring Authority from affected parties about the material change, along with a clear explanation of where any comments have not been incorporated, and the reasons why not. 23.5 Any material change proposed to the CEMP and DWPs shall be subject to an independent peer review as required by Condition 11. 23.6 Following that review any material change proposed to the CEMP and DWPs relating to an adverse effect shall be submitted for approval to Auckland Council Compliance and Monitoring Officer, at least 10 working days prior to the proposed changes taking effect. If any changes are not agreed, the relevant provisions of the RMA relating to approval of outline plans shall apply. Network Utilities 24.1 To manage the adverse effects on Network Utilities Operations during the construction of the City Rail Link, the following shall be included in the CEMP. 24.2 The purpose of this section of the CEMP shall be to ensure that the enabling works and construction of the City Rail Link adequately take account of, and include measures to address the safety, integrity, protection or, where necessary, relocation of existing network utilities that traverse, or are in close proximity to, the designation during the construction of the City Rail Link.

1 24

4 5 6

24.3 For the avoidance of doubt and for the purposes of this condition an “existing Network Utility� includes infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with condition 6 of this designation or the section 176(1)(b) RMA process. 24.4 The CEMP shall be prepared in consultation with Network Utility Operators who have existing Network Utilities that traverse, or are in close proximity to, the designation and shall be adhered to and implemented during the construction of the City Rail Link. The CEMP shall include as a minimum: (a) Cross references to the Communication and Consultation Plan for the methods that will be used to liaise with all Network Utility Operators who have existing network utilities that traverse, or are in close proximity to, the designation; (b) Measures to be used to accurately identify the location of existing Network Utilities,

City Rail Link Notice of Requirement

Page 30


Condition Number

NoR Designati on Applies to

Condition

and the measures for the protection, support, relocation and/or reinstatement of existing Network Utilities; (c) Methods to be used to ensure that all construction personnel, including contractors, are aware of the presence and location of the various existing Network Utilities (and their priority designations) which traverse, or are in close proximity to, the designation, and the restrictions in place in relation to those existing Network Utilities. This shall include: (i) Measures to provide for the safe operation of plant and equipment, and the safety of workers, in proximity to existing Network Utilities; (ii) Plans identifying the locations of the existing Network Utilities (and their designations) and appropriate physical indicators on the ground showing specific surveyed locations; (d) Measures to be used to ensure the continued operation of Network Utility Operations and the security of supply of the services by Network Utility Operators at all times; (e) Measures to be used to enable Network Utility Operators to access existing Network Utilities for maintenance at all reasonable times on an ongoing basis during construction, and to access existing Network Utilities for emergency and urgent repair works at all times during the construction of the City Rail Link; (f) Contingency management plans for reasonably foreseeable circumstances in respect of the relocation and rebuild of existing Network Utilities during the construction of the City Rail Link; (g) A risk analysis for the relocation and rebuild of existing Network Utilities during the construction of the City Rail Link; (h) Earthworks management (including depth and extent of earthworks and temporary and permanent stabilisation measures), for earthworks in close proximity to existing Network Utilities; (i) Vibration management and monitoring for works in close proximity to existing Network Utilities; (j) Emergency management procedures in the event of any emergency involving existing Network Utilities; (k) The process for providing as-built drawings showing the relationship of the relocated Network Utilities to the City Rail Link to Network Utility Operators and the timing for providing these drawings; (l) Measures to ensure that network utility services are not interrupted to the Mt Eden Corrections Facility as a result of City Rail Link works. The requiring authority shall advise the Department of Corrections and the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road, of any works on network utilities in the vicinity of the Mt Eden Corrections Facility which may impact on utility service provision to the Mt Eden Corrections Facility at least 14 days prior to those works occurring to allow the Department of Corrections (and the entity contracted to administer and run the facility at 1 Lauder Road) to arrange suitable contingencies. Communication and consultation with the Department of Corrections, and the entity contracted to administer and run the facility at 1 Lauder Road, shall be recorded in accordance with condition 15) of this designation. The Requiring Authority shall be responsible for ensuring that construction works do not interrupt network utility services to the Mt Eden Corrections Facility, unless by prior arrangement with Department of Corrections and

City Rail Link Notice of Requirement

Page 31


Condition Number

NoR Designati on Applies to

Condition

the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road. (m) A summary of the consultation (including any methods or measures in dispute and the Requiring Authorities response to them) undertaken between the Requiring Authority and any Network Utility Operators during the preparation of the CEMP. 24.5 If the Requiring Authority and a Network Utility Operator cannot agree on the methods proposed under the CEMP to manage the construction effects on the Operator’s network utility operation, unless otherwise agreed, each party will appoint a suitably qualified and independent expert, who shall jointly appoint a third such expert to advise the parties and make a recommendation. That recommendation will be provided by the Requiring Authority as part of the CEMP along with reasons if the recommendation is not accepted. Transport, Access and Parking General Transport, Access and Parking 25.1 A Transport, Access and Parking DWP shall be prepared to manage the adverse effects of construction of the City Rail Link, or any part of it, on the transport network. 25.2 The objective of the Transport, Access and Parking DWP is to so far as is reasonably practicable, avoid, remedy or mitigate the adverse effects of construction on transport, parking and property access. This is to be achieved by: (a) Managing the road transport network for the duration of construction by adopting the best practicable option to manage congestion; (b) Maintaining pedestrian access to private property at all times; and (c) Providing on-going vehicle access to private property to the greatest extent possible. 25.3 To achieve the above objective, the following shall be included in the Transport, Access and Parking DWP:

25

1 4 5 6

(a) The road routes which are to be used by construction related vehicles, particularly trucks to transport construction related materials, equipment, spoil, including how the use of these routes by these vehicles will be managed to mitigate congestion, and to the greatest extent possible, avoid adverse effects on residential zoned land and education facilities; (b) Transport route options for the movement of construction vehicles carrying spoil, bulk construction materials or machinery shall be identified and details provided as to why these routes are considered appropriate routes. In determining appropriate routes, construction vehicles carrying spoil, bulk construction materials or machinery shall as far as practicably possible only use roads that: (i) Form part of the regional arterial network; (ii) Are overweight / over dimensioned routes; (iii) Or other routes (specified below) where no other practical option is available. (c) For the purposes of this condition the following routes (that at the time this designation was confirmed were not part of the regional arterial network and / or overweight / over dimensioned) shall be used where practicable for the movement of construction vehicles carrying spoil, bulk construction materials or machinery: (i) Ngahura Road, for trucks heading to/from Eden Terrace construction site; (ii) Dundonald Street and Basque Road, for trucks heading to/from the Newton Station construction sites; (iii) Pitt Street (between Hobson Street and Hopetoun Street), Beresford Square, Mercury Lane, Canada Street and Upper Queen Street (between Canada Street

City Rail Link Notice of Requirement

Page 32


Condition Number

NoR Designati on Applies to

Condition

and Karangahape Road), for trucks heading to/from Karangahape Station construction sites; (iv) Wellesley Street (between Nelson Street and east of Albert Street), Cook Street (between Mayoral Drive and Hobson Street) and Mayoral Drive (between Wellesley Street and Cook Street) for trucks heading to/from Aotea Station construction sites; (v) Nelson Street (north of Wellesley Street), Hobson Street (north of Cook Street) and Lower Albert Street, for trucks heading to/from the Albert Street and Downtown construction sites. (d) Where other routes are necessary (other than those routes identified above), the Transport, Access and Parking DWP shall identify any residential zoned land and education facilities and shall provide details on how adverse effects from these vehicle movements are to be mitigated through such measures as: (i) Communication and consultation (in accordance with Condition 15 of this designation) with these properties in advance of the vehicle movements occurring; (ii) Restricting vehicle movements on Monday to Friday to between 9.30am and 4pm, and on Saturday to between 9am and 2pm. (e) Proposed temporary road lane reductions and / or closures, alternative routes and temporary detours, including how these have been selected and will be managed to mitigate congestion as far as practicably possible and how advance notice will be provided; (f) How disruption to the use of private property will be mitigated through: (i) Ensuring pedestrian and cycle access to private property is retained at all times; (ii) Providing vehicle access to private property as far as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; and (iii) How the loss of any private car parking will be mitigated through alternative car parking arrangements. (g) Where an affected party unexpectedly finds their vehicle blocked in as a result of a temporary closure, the Requiring Authority shall (within reasonable limits) offer alternative transport such as a taxi, rental car, or other alternative. Note: For the purposes of designation Conditions 25, 27, 28, 29 and 30 “temporary closure� is defined as the following: (i) In place for less than six hours, the Requiring Authority shall communicate and consult on the closure at least 24 hours in advance, but is not required to offer or provide alternative parking arrangements, though it may choose to offer this on a case by case basis in consultation with the affected party; and (ii) In place for between six and 72 hours, the Requiring Authority shall communicate and consult on the closure at least 72 hours in advance, and will offer and provide where agreed with the affected party alternative parking arrangements. The alternative parking arrangement should be as close to the site affected as is reasonably practicable. (h) How disruption to use of the road network will be mitigated for emergency services, public transport, bus users, taxi operators, freight and other related vehicles, pedestrians and cyclists through:

City Rail Link Notice of Requirement

Page 33


Condition Number

NoR Designati on Applies to

Condition

(i) Prioritising, as far as practicably possible, pedestrian and public transport at intersections where construction works are occurring; (ii) Relocating bus stops and taxi stands to locations which, as far as practicably possible, minimise disruption; and (iii) Identifying alternate heavy haul routes where these are affected by construction works. (i) Cross references to the specific sections in the Communication and Consultation Plan that detail how emergency services, landowners, occupiers, public transport users, bus and taxi operators, and the general public are to be consulted with in relation to the management of the adverse effects on the transport network. (j) The alternative (to road) transport options that are available (including the option of rail use at the main construction site adjacent the North Auckland Rail Line) and that have been considered and assessed for the transportation of spoil. This will include as applicable: (i) Benefits that could be provided by alternative options; (ii) Potential adverse effects associated with alternative options; (iii) Where an alternative option is proposed, methods for managing potential adverse effects; and (iv) Reasons for either adopting or not adopting alternative transport options. Monitoring of Transport Network Congestion 26.1 To achieve the objective of Condition 25.2(a), the Requiring Authority will undertake monitoring of the transport network and implement additional mitigation measures as required to manage congestion to achieve the best practicable option. 26.2 The purpose of the monitoring is to monitor congestion on the transport network by measuring average delays for traffic travelling along specified routes. The evaluation times will be: (a) The average travel times over the weekday two hour morning peak period; and (b) The average travel times over the weekday two hour evening peak period; and (c) The average weekday inter-peak travel times between 9am to noon, noon to 2pm and 2 to 4pm. 1 26

4 5 6

26.3 The Requiring Authority shall carry out continuous monitoring for the duration that construction of the City Rail Link is occurring. The intention is that this monitoring is to be continuous, although it is acknowledged that there may be occasional malfunctions. 26.4 If a congestion incident occurs (such as an accident), the monitoring during the affected period will be considered unrepresentative. 26.5 Monitoring shall commence six months prior to construction of the City Rail Link to establish a baseline of existing transport congestion. 26.6 The monitoring will establish whether the City Rail Link construction works have increased traffic delays as follows: (a) Either by more than 10 minutes (from the monitoring previously undertaken in accordance with this condition) (b) Or if the travel times are more than three minutes or 30% greater than the forecast modelled increases along that route (according to the most recent traffic model test of that scenario, undertaken prior to the start of construction. The modelled time is to be based on the Auckland City Centre SATURN traffic model or a different traffic model approved by the Requiring Authority).

City Rail Link Notice of Requirement

Page 34


Condition Number

NoR Designati on Applies to

Condition

(c) The 30% above shall only apply for an increase predicted to be over four minutes. 26.7 If the travel times exceed the above criteria on any one of the specified routes, then additional mitigation shall be implemented by the Requiring Authority in its role as the Road Controlling Authority (under its statutory obligation). The additional mitigation could include but is not limited to advertising alternative routes, removing on street car parking or implementing operational measures, such as lane reconfigurations or signal phasing, to increase capacity on the surrounding network where reasonably possible at that time. 26.8 The purpose of additional mitigation measures is to mitigate the increases in traffic delays, reducing these to below the levels identified in Condition 26.6 as far as is reasonably achievable. 26.9 For the purposes of this condition, the following are the specified routes: (a) Wellesley Street (between Victoria Street and Princes Street) (b) Victoria Street (between Wellesley Street and Princes Street) (c) Customs Street/Fanshawe Street (between Nelson Street and Tangihua Street) (d) Quay Street/Lower Hobson Street (between Fanshawe Street/Hobson Street and Tangihua Street) (e) Nelson Street/Hobson Street (between Pitt Street and Fanshawe Street) (f) Queen Street (between Mayoral Drive and Customs Street) (g) New North Road/Symonds Street (between Dominion Road and Newton Road) (h) Mount Eden Road (between Normanby Road and Symonds Street) (i) Khyber Pass Road between the southern motorway ramps and Symonds Street if this route is to be used by construction related trucks (j) Newton Road between the northwestern motorway ramps and Symonds Street 26.10 The specified routes shall exclude whichever east-west route has its intersection with Albert Street closed at the time of the surveys. Transport, Access and Parking: Specific Requirements (Britomart to Mayoral Drive) 27.1 To achieve the objective in Condition 25, the following measures shall be implemented: (a) A vehicle access lane at least 3m wide shall be provided along the eastern side of Albert Street between Customs Street and Victoria Street to provide access to properties (except that while the Albert Street/Victoria Street intersection is closed, this access lane is only to be provided between Customs Street and Durham Street);

27

1

(b) A vehicle access lane at least 3m wide shall be provided along the western side of Albert Street between Customs Street and Victoria Street to provide access to properties, except that: (i) While the Albert Street/Customs Street intersection is closed, this access lane is only to be provided between Victoria Street and Wolfe Street; and (ii) While the Albert Street/Victoria Street intersection is closed, this access lane is only to be provided between Kingston Street and Customs Street. If Kingston Street is also to be closed to Albert Street during this construction stage, this access lane shall be provided between Wyndham Street and Customs Street; and (iii) For a single period of up to 3 months while the cut and cover trench structure establishment works are carried out along Albert Street between Swanson Street and Customs Street, this access land is only required to be provided between Victoria Street and Swanson Street if northbound traffic is otherwise diverted via

City Rail Link Notice of Requirement

Page 35


Condition Number

NoR Designati on Applies to

Condition

Swanson Street West and Federal Street; and (iv) For a single period of up to 10 months while the public realm reinstatement works are carried out along Albert Street between Wyndham Street and Wolfe Street, this access lane is only required to be provided between Victoria Street and Swanson Street if northbound traffic is otherwise diverted via Swanson Street West and Federal Street. (c) The east-west / west-east connection (two fully operational traffic lanes in each direction) is to be maintained in each direction at two of the Customs Street, Victoria Street and Wellesley Street intersections with Albert Street during the period when the third of those intersections is otherwise fully closed; (d) The left turn movement from Customs Street (from the east) into Albert Street, and the left turn from Customs Street (from the west) into Albert Street, shall be retained while the Albert Street / Customs Street intersection is fully closed; (e) The left turn from Durham Street into Queen Street shall be reopened while the Albert Street/Victoria Street intersection is fully closed; (f) Two way access shall be provided on the single service lane along the western side of Albert Street between 87 Albert Street and Kingston Street while the Albert Street/Victoria Street intersection is fully closed. If Kingston Street is also to be closed to Albert Street during this construction stage, this access shall be provided to Wyndham Street; (g) Vehicular access into and egress from: (i)

Mills Lane to and from either Albert Street or Swanson Street; and

(ii) The Stamford Plaza Auckland main entrance and forecourt area is to be provided at all times and for the avoidance of doubt cannot be temporarily closed during construction. (h) Providing pedestrian and cycle access to private property at all times; (i) Providing footpaths of at least 1.5m in width along either side of Albert Street; (j) At a minimum two safe crossing passageways (which are “fully accessible” with a minimum width of 1.5m wide and well lit ), need to be provided in the vicinity of Swanson Street and Wyndham Street, in addition to pedestrian crossings at the intersections of Victoria Street and Customs Street; (k) Ensuring that construction traffic does not use Swanson Street, Wolf Street or Federal Street north of Swanson Street; (l) During the Kingston Street closure, pedestrian access to and from the Auckland District Court’s fire escape on the north side of Kingston Street shall be maintained at all times; and (m) 18 metres of on street parking within Kingston Street shall be reserved for police at the nearest practicable location. 27.2 The Transport, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following: (a) How construction works will be undertaken to mitigate congestion on Albert Street, Wellesley Street, Victoria Street, Customs Street, and Quay Street including retaining east-west traffic movements across Albert Street on Customs Street, Victoria Street and Wellesley Street; (b) The timing and sequencing of temporary road lane reductions and / or closures, and the alternative routes and temporary detours to be used, including: (i) How these have been selected and will be managed to, where practicable,

City Rail Link Notice of Requirement

Page 36


Condition Number

NoR Designati on Applies to

Condition

mitigate congestion on the surrounding road network; (ii) How the Albert Street/Wyndham Street intersection will be reopened as soon as practically possible; (c) How disruption to the use of private property located immediately adjacent the designation with access onto Galway Street, Tyler Street, Queen Elizabeth Square, Customs Street, Albert Street, Kingston Street, will be mitigated through: (i) Providing vehicle access to private property as practicably possible at all times; (ii) Retaining local vehicle access to properties located along Albert Street (which may include only left in, left out access); (iii) Retaining access for loading and unloading of goods located along the service lane on the eastern side of Albert Street, between Victoria Street and Wellesley Street; and; (iv) Providing an on street loading bay on Customs Street, Lower Albert Street or Lower Queen Street to provide servicing to 21 Queen Street if access during construction cannot be provided to the existing loading bay area for 21 Queen Street, accessed from Lower Albert Street; and; (v) Providing access for loading and unloading of goods between Wyndham Street and Victoria Street West. (d) How disruption to the use of the local road network will be mitigated for private bus users, pedestrians and cyclists through: (i) Providing, where practicable, for the continued operation of private bus operators from hotels and other pick up / drop off locations in the city centre area (cross references to the Communication and Consultation Plan for consulting with private bus operators shall be included in the CEMP and Traffic, Access and Parking DWP); and (ii) Retaining pedestrian and cycle access through Lower Queen Street and / or Queen Elizabeth Square to provide access to and from the Ferry terminal and Customs Street; and (e) How disruption to pedestrians and cyclists requiring the ability to cross from east to west (and vice versa) across Albert Street between Victoria Street and Customs Street can be mitigated through providing, where practicable, safe pedestrian and cyclist passageways across the construction works on Albert Street. Transport Access and Parking: Specific Requirements (Karangahape Station Area) 28.1 To achieve the objective in Condition 25, the following measure shall be implemented: (a) Retaining one lane of traffic in each direction on Pitt Street (unless otherwise agreed with the Auckland Council Consent Monitoring officer); and (b) Spoil trucks shall not use East Street where practicable and on-street parking at the Southern end of East Street will be retained. 28

4

28.2 The Transport, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following: (a) How construction of the shafts providing access to the Station can be undertaken to mitigate congestion on Pitt Street, Karangahape Road, and Mercury Lane; (b) The timing and sequencing of temporary road lane reductions and / or closures on Pitt Street, Mercury Lane, and the western end of Beresford Street, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the

City Rail Link Notice of Requirement

Page 37


Condition Number

NoR Designati on Applies to

Condition

surrounding road network; (c) How disruption to the use of private property located immediately adjacent the surface designation with access onto Beresford Street, Pitt Street, Mercury Lane, and East Street will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times, particularly those businesses located at the eastern end of Beresford Street and the northern end of Mercury Lane; (ii) Providing vehicle access to private property, which may include only a turn in and a turn out in the same direction), as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; (iii) Providing local vehicle access to properties located along Beresford Street and Samoa House Lane (which may include only a turn in and a turn out in the same direction); (iv) Alternative parking arrangements or other offers for resolving the temporary loss of car parking during construction for the Hopetoun Alpha Building. Transport, Access and Parking: Specific Requirements (Newton Station Area) 29.1 To achieve the objective in Condition 25, the Transport, Access and Parking DWP shall include the following: (a) How construction of the shafts providing access to the Newton Station, although constructed wholly on private land, can be undertaken to mitigate construction related congestion on Symonds St, the Symonds Street / Mt Eden Road / New North Road intersection, Dundonald Street, and the western end of Basque Road; (b) The timing and sequencing of temporary road lane reductions and / or closures on Symonds St in the vicinity of the intersection of Symonds Street / Mt Eden Road and New North Road , Dundonald Street, and the western end of Basque Road, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the surrounding road network; 29

5

(c) How disruption to the use of private property located immediately adjacent the surface designation with access onto Symonds Street, Dundonald Street, and the western end of Basque Road will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times, particularly for those businesses and residences located along Symonds Street and Dundonald Street; (ii) Providing vehicle access to private property, which may include only a turn in and a turn out in the same direction), as practicably possible at all times, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure. How the loss of public pay and display parking located at the Auckland Transport Symonds Street Public Car Park will be mitigated through alternative parking arrangements. The Requiring Authority may be able to arrange such alternative car parking at the Burleigh Street car park. (d) The effects of the temporary use of the Symonds Street car park as a construction site are to be mitigated by the Requiring Authority by active parking management and enforcement, within 400m of the car park, to maximise short term parking within this area

City Rail Link Notice of Requirement

Page 38


Condition Number

NoR Designati on Applies to

Condition

Transport and Property Access: Additional Requirements (NAL Area) 30.1 To achieve the objective in Condition 25, the following measures shall be implemented: (a) The retention of at least two traffic lanes (one in either direction) on Mt Eden Road during the construction of the replacement Mt Eden Road Bridge; (b) During the closure of the Normanby Road level crossing to construct the grade separated crossing, the Mt Eden Road and Normanby Road intersection shall be signalised and a second traffic lane shall be provided on the Boston Road approach to its intersection with Mt Eden Road intersection. Additionally, the no parking restrictions on Boston Road shall be extended along the length of Boston Road and considered for any adjacent local roads to facilitate through traffic; (c) A temporary pedestrian crossing (over the rail line) at Normanby Road is to be provided for the period of the temporary closure of the Normanby Road connection; (d) Access will be maintained to Nikau Street at all times by at least one lane (minimum 3m), and two lanes on Nikau St between Flower and Korari Streets. Access to sites within Flower Street and Korari Street is to be retained, from Nikau Street or New North Road, at all times; (e) Construction works will be undertaken to ensure two-way access is maintained at all times for vehicles to all accessways to the MediaWorks site including staff and visitors cars, trucks and service vehicles; (f) Providing for traffic to turn right out of Ruru Street to reduce any congestion (particularly at peak times) resulting from not being able to travel via Nikau Street to the traffic lights at Flower Street and New North Road; 30

6

(g) Providing accessibility along Mt Eden and Normanby Roads as a priority for, where practicable: public transport (buses), emergency services, access to properties for pedestrians, and cyclists; (h) Construction works will be undertaken to ensure two-way access is maintained at all times for all vehicles accessing the Mt Eden Corrections Facility at Lauder Road (including staff and visitors’ cars, service vehicles, prison vans, emergency vehicles and buses), communication and consultation with the Department of Corrections, and the entity contracted by Department of Corrections to administer and run the Mt Eden Corrections facility at 1 Lauder Road, on this matter shall be recorded in accordance with Condition 15) of this designation. The Requiring Authority shall be responsible for ensuring that the construction works do not restrict 24-hour two-way access for all vehicles accessing the Mt Eden Corrections Facility at Lauder Road; (i) Construction works will be undertaken to ensure two-way access is maintained at all times for vehicles accessing the premises at 51-63 Normanby Road, including staff and visitors cars, trucks and service vehicles. The measures shall: (i) Ensure safe and reasonable access to and from the site, to Austroads standards; (ii) Not result in the loss of any on site parking; (iii) Incorporate a crossing width sufficient not to reduce the range of vehicles required to access the site, relative to the existing situation; (iv) It is noted that the site is used occasionally by large trucks of up to 18m. These vehicles are to be provided for in the design of the access (i.e. the vehicle crossing and the access onto the site); (v) Following completion of the grade separation of Normanby Road safe and reasonable access will be provided to and from the property at 51-63 Normanby Road to meet the relevant Austroads and NZS2890.1 standards or the applicable

City Rail Link Notice of Requirement

Page 39


Condition Number

NoR Designati on Applies to

Condition

standard required by the road controlling authority. (j) Construction works will be undertaken to ensure pedestrian and two-way vehicle access is maintained at all times to access the premises at 32 Normanby Road, including staff and visitors cars, trucks and service vehicles. The measures shall: (i) Ensure safe and reasonable access to and from the site, to Austroads standards; (ii) Incorporate a crossing width sufficient not to reduce the range of vehicles required to access the site, relative to the existing situation; (iii) Should the Requiring Authority require part of the site at 32 Normanby Road that is currently used for 40 car parking spaces for the construction of the City Rail Link 34 alternative car parking spaces will be provided at 14-22 Boston Road (in accordance with Plans DRG 0052 Rev 2.0 CRL-EFC-CON-000-DRG-0064 Revision 1 dated 8/7/16 and DRW 0058 Rev 5.0 CRL-EFC-ROA-000-DRG-1027 Revision 4 dated 30/6/16, 1028 Revision 4 dated 30/6/16 and 1127 Revision 2 dated 30/6/16). The Requiring Authority shall provide safe pedestrian access across the North Auckland Line and into the site for customers and staff, visiting or employed at the site in accordance with Condition 30.1(c) until the grade separation works are completed and permanent access is reinstated to the site. (k) At completion of the grade separation of Normanby Road safe and reasonable pedestrian and vehicle access to and from the site and 34 on site car parking spaces will be provided for the property at 32 Normanby Road. In the case of pedestrian and vehicle access and parking arrangements, this will be in accordance with Plans DRG 0058 Rev 5.0 CRL-EFC-ROA-000-DRG-1027 Revision 4 dated 30/6/16, 1028 Revision 4 dated 30/6/16 and 1127 Revision 2 dated 30/6/16, and meet the following requirements: (i) The ramp access will meet relevant Austroads, NZS2890.2 and the Auckland Council District Plan: Isthmus Section design standards; (ii) The 34 car parking spaces will be provided across the site and the adjoining KiwiRail property. The spaces will be compliant with the appropriate Auckland Council District Plan: Isthmus Section parking standards for dimension and manoeuvring; (iii) The design, structures and barriers associated with the ramp and pedestrian access to the site will be subject to the urban design process of Condition 47; and (iv) Provision for landscape planting both on the site and on the KiwiRail land in the area shown on DRG 0058 Rev 5.0 CRL-EFC-ROA-000-DRG-1127 Revision 2 dated 30/6/16 and if appropriate beyond the site (in accordance with Condition 47.2). Indicative widths of landscaping on DRG 0058 Rev 5.0 are 1m for the section shown alongside the railway and 0.5m for the section on the southern side of the ramp. (l) The KiwiRail land required by condition (k) above for car parking spaces, landscaping and the ramp access will be provided by the Requiring Authority until such time as the vehicle access ramp is no longer required by the landowner. If the vehicle access ramp is no longer required to provide access to the property it shall be removed by the Requiring Authority at its cost within 3 months unless otherwise agreed with the landowner. (m) Construction of the grade separation works at Normanby Road on the parcels of land identified on the CRL NOR6 Sheet 2 as parcels 242, 243, 244, 245, 246, 393, 394, 399, 400 and 401 shall not commence until the KiwiRail land is available and written

City Rail Link Notice of Requirement

Page 40


Condition Number

NoR Designati on Applies to

Condition

confirmation of this has been provided by the Requiring Authority to Auckland Council. (n) Access to Water Street to and from Mt Eden Road for CRL construction related heavy commercial vehicles shall be limited to left-in and left-out movements only. (o) Access to 14-22 Boston Road from Normanby Road shall be restricted to left-in and left-out movements only; the exception to this will be when Normanby Road is closed; and (p) During the temporary works along Boston Road, a 1.8m wide footpath on the north side of the street, in addition to two 3.0m wide traffic lances shall be provided on Boston Road between Normanby Road and Khyber Pass. A safe temporary pedestrian crossing facility shall be provided at the western extent of Active Construction Zone M1. 30.2 The Traffic, Access and Parking DWP shall demonstrate how these measures will be implemented and shall also include the following: (a) How construction works can be undertaken to mitigate congestion on New North Road, Ruru Street, Korari Street, Flower Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road, Normanby Road, Boston Road, Nugent Street, and the road network in general in this area including: (b) Which routes are to be used by construction trucks to remove spoil from the construction yard including how the use of these routes by these vehicles will be managed to mitigate congestion; (c) Which routes are to be used by construction related traffic (especially trucks) to deliver construction materials and other related goods and services to the construction yard including how the use of these routes by these vehicles will be managed to mitigate congestion; The grade separation of Porters Ave so that it is undertaken at a time when vehicles, pedestrians, and cyclists can be managed and accommodated on Dominion Road, Mt Eden Road and Normanby Road to an extent which mitigates where practicable, delays to travel journeys from congestion on these roads resulting from City Rail Link construction works; (d) The grade separation of Normanby Road so that it is undertaken at a time when vehicles, pedestrians, and cyclists can be managed and accommodated on Dominion Road, Mt Eden Road and Porters Avenue, to an extent which mitigates where practicable, delays to travel journeys from congestion on these roads resulting from City Rail Link construction works; (e) Any reduction in the number of fully operational traffic lanes associated with the closure of Porters Avenue and Normanby Road, and the reduction in the number of vehicle lanes on the Mount Eden Road bridge, is to be undertaken on only one of these three two routes at a time; (f) The timing and sequencing of temporary road lane reductions and / or closures at the Symonds Street / New North Road / Mt Eden Road intersection , Ruru Street, Korari Street, Flower Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road in the vicinity of the bridge over the rail line, Normanby Road, Boston Road, Nugent Street in the vicinity of the rail crossing, and the alternative routes and temporary detours to be used, including how these have been selected and will be managed to, where practicable, mitigate congestion on the surrounding road network; (g) How disruption to the use of property located immediately adjacent to the surface

City Rail Link Notice of Requirement

Page 41


Condition Number

NoR Designati on Applies to

Condition

designation with access onto New North Road, Ruru Street, Korari Street, Flower Street, Nikau Street, Ngahura Street, Porters Avenue, Mt Eden Road, Normanby Road, Boston Road, Nugent Street will be mitigated through: (i) Providing pedestrian and cycle access to private property at all times; (ii) Providing local vehicle access and pedestrian access at all times to properties located along Flower Street (between Nikau Street and Shaddock Street) and Shaddock Street (between Flower Street and its dead end to the east), which are not located within the designation footprint, except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; (iii) Retaining local vehicle and pedestrian access to properties located outside the designation footprint along Haultain Street, Fenton Street, Porters Avenue, Ngahura Street, Ruru Street, Korari Street, Flower Street, Nikau Street, Mt Eden Road, Boston Road, Nugent Street, and Normanby Road at all times except for temporary closures where landowners and occupiers have been communicated and consulted with in reasonable advance of the closure; and (iv) Full accessibility to those parts of Porters Avenue not affected by, but in the vicinity of, the construction works; and (h) How disruption to the use of Mt Eden Rail Station will be mitigated through providing, where practicable, access during construction works associated with the replacement of Mt Eden Road Bridge. Noise and Vibration Project Standards - Construction Noise 31.1 Construction noise shall comply with the following Project Standards (unless otherwise provided for in a SSCNMP which is approved under Condition 37, 39 or 40): Monday to Saturday 0700 – 2200

Sundays and Public Holidays

Occupied commercial and industrial buildings (including offices)

75 dB LAeq

75 dB LAeq

Sensitive Noise and Vibration Receivers (excluding offices)

75 dB LAeq 90 dB LAFmax

65 dB LAeq 1

Receiver Type

1 31

4 5 6

Early Childhood Education Centres (whilst occupied during normal opening hours)

At all other times

0700 – 2200

80 dB LAFmax

2200 – 0700

75 dB LAeq

2

60 dB LAeq 75 dB LAFmax

35 dB LAeq in sleeping areas

City Rail Link Notice of Requirement

Page 42


Condition Number

NoR Designati on Applies to

Condition

Bear Park Early Childhood Education Centre at 32 Akiraho Street (whilst occupied during normal opening hours)

35 dB LAeq in sleeping areas 65 dB LAeq in outdoor playing areas

Notes: 1. 60dB LAeq for Designation 5 and Designation 6; and 2. 75dB LAFmax for Designation 5 and Designation 6. 31.2 Construction noise shall be measured and assessed in accordance with the provisions of NZS 6803:1999 Project Standards - Blasting Overpressure and Vibration For the avoidance of doubt this condition only applies to NoR 6 where blasting is required. 32.1 Prior to commencement of production blasts (ie. blasting that is undertaken as part of the construction process), trial blasts (ie. preliminary blasts that occur prior to production blasts for the purpose of data acquisition), shall be undertaken to demonstrate how adverse effects will be managed and how compliance with Conditions 32.2, 32.3 and 32.4 will be achieved in production blasting. Trial blasts will determine site-specific attenuation characteristics, air overpressure levels and maximum instantaneous charge weight (MIC) thresholds. Outcomes shall be documented in a Trial Blasting Report. This Trial Blasting Report shall be used for subsequent design of production blasting. 32.2Air overpressure from the blast events shall not exceed 120 dB LZpeak at the facade of any occupied building measures and assessed in accordance with the provisions of the Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives.

32

6

32.3Air overpressure from blast events shall not exceed 133dB LZpeak at the facade of any unoccupied building measured and assessed in accordance with the provisions of Australian Standard AS 2187.2-2006 Explosives – Storage and use – Use of explosives. 32.4 Unless a SSCNVMP is approved under Conditions 38, 39 or 40 which includes an alternative blasting vibration standard: (a) Vibration from blast events shall not exceed 10mm/s PPV for 95% of blast events and 15mm/s for 100% blast events when measured at the foundation of any building that will be occupied during the blast event when measured and assessed in accordance with the provisions of DIN 4150-3:1999. (b) Vibration from blast events shall not in any case exceed the limits specified in Condition 33 when measured at the foundation of any building when measured and assessed in accordance with the provisions of Condition 33. 32.5 For the purposes of 32.2 and 32.3, a building is deemed to be occupied if there are persons inside only during the blast event (ie. if the occupants of a dwelling are out (eg. at work) during the blast event then the dwelling is deemed to be unoccupied). 32.6 Blasts must be performed at set times during the daytime only, between 9am and 5pm, Monday to Saturday only. 32.7 Comprehensive vibration and air overpressure level predictions must be performed prior to every blast event. 32.8 Blasting shall not be carried out where overpressure levels are predicted to be above the Project Standards in 32.1 and 32.2 at any building. Blasting shall not be carried out where

City Rail Link Notice of Requirement

Page 43


Condition Number

NoR Designati on Applies to

Condition

vibration levels are predicted to be above the project standards in Condition 32.4 at any building. 32.9 These criteria may be varied only by a Site Specific Construction Noise Management Plan (SSCNMP) that has been approved under Condition 37. Project Standards - Construction Vibration 33.1 Construction vibration (including blasting) shall comply with the following Project Standards for building damage (unless otherwise provided for in a SSCVMP which is approved under Condition 38, 39 or 40) Type of Structure

Short-term (transient) vibration1

PPV at the foundation at a frequency of

1 2 4 33

5 6

Long-term (continuous) vibration

PPV at horizontal plane of highest floor (mm/s)

PPV at horizontal plane of highest floor (mm/s)

1-10Hz (mm/s)

10-50 Hz (mm/s)

50-100 Hz (mm/s)

Commercial/ Industrial

20

20 – 40

40 – 50

40

10

Residential/ School

5

5 – 15

15 – 20

15

5

Historic or sensitive structures

3

3–8

8 – 10

8

2.5

Note: 1. Standard DIN 4150-3:1999 defines short-term (transient) vibration as “vibration which does not occur often enough to cause structural fatigue and which does not produce resonance in the structure being evaluated”. Long-term (continuous) vibration is defined as all other vibration types not covered by the short-term vibration definition. 33.2 Construction vibration (including blasting) shall be measured in accordance with German Standard DIN 4150-3:1999. Project Standards - Construction Vibration (Amenity) 34.1 Between the hours of 10pm and 7am vibration generated by construction activities (excluding blasting) shall not exceed: 1 2 34

4 5 6

(a) a Peak Particle Velocity (PPV) of 0.3mm/s when measured at any part of the floor of any bedroom; (b) a noise level of 35 dB LAeq(15min) when measured in any bedroom. 34.2 Between the hours of 7am and 10pm vibration generated by construction activities (excluding blasting) shall not exceed: (a) A Peak Particle Velocity (PPV) of 1mm/s as measured on the floor of the receiving room for residentially occupied habitable rooms, bedrooms in temporary accommodation and medical facilities; and (b) A Peak Particle Velocity (PPV) of 2mm/s as measured on the floor of the receiving room for retail and office spaces (including work areas and meeting rooms); 34.3 The limits in 34.1 and 34.2 shall only be investigated and applied upon the receipt of

City Rail Link Notice of Requirement

Page 44


Condition Number

NoR Designati on Applies to

Condition

a complaint from any building occupant. They shall not be applied where there is no concern from the occupant of the building. 34.4 Where the limits in 34.1 and 34.2 are found (through measurement) to be exceeded then a SSCVMP shall be prepared for that receiver (Condition 38). Project Standards – MediaWorks

6

35

35.1 The noise and vibration limits set out in Conditions 35.2 and 35.3 shall apply only during Sensitive Times. For the purposes of MediaWorks, Sensitive Times are defined as follows: (a) During scheduled live broadcasting (b) During emergency/breaking news live broadcasting (c) During scheduled recording sessions If the limits are complied with in Studio 1, the noise and vibration levels in all other Studios will be acceptable. For the avoidance of doubt, (a)-(c) above include sound checks as well as actual broadcast/recording time. 35.2 Noise Limits – Studios The noise level (whether air borne or reradiated from ground vibration) from all construction sources as received inside Studio 1 shall not exceed 30dB LAeq (5 min) and 33 dB LAeq (1 sec). These limits apply to the construction component of the total noise. However for up to two periods of tunnelling, each no more than 15 consecutive days, the noise limits may be up to 5 decibels higher (ie. 35dB LAeq (5 min) and 38 dB LAeq (1 sec)) during Sensitive Times, other than during the Live Broadcasting Periods as follows: (a) Weekdays: 0600-0900 hours 1200-1230 hours 1730-1930 hours 2230-2330 hours (b) Christmas holiday season (Saturday prior to Christmas Day to Sunday following New Years Day inclusive) and weekends: 1730-1900 hours The Requiring Authority must give MediaWorks at least 12 days notice of the commencement of each such period. 35.2A Rockbreaking shall not be used for tunnel excavation within 100m of the MediaWorks site during Sensitive Times unless compliance with the noise limits in Condition 35.2 can be demonstrated in accordance with the methodology set out in the SSCNVMP. 35.3 Vibration Limits – Studios For the protection of studio camera image quality, the construction vibration level (including blasting) as received inside Studio 1 shall not exceed 0.1mm/s PPV. This limit may be elevated by agreement of both the Requiring Authority and MediaWorks where image quality is found to be unaffected. 35.4 Noise level measurements inside Studio 1 shall be undertaken at a position that is representative to the level received within 2m from, and at a similar height to, the microphone of the main presenter(s). 35.5 Noise level measurements inside Studio 1 shall be undertaken with all doors to the studio closed.

City Rail Link Notice of Requirement

Page 45


Condition Number

NoR Designati on Applies to

Condition

35.6 For the protection of amenity, the construction vibration level as received in inside office areas, meeting rooms and technical suits shall not exceed 1mm/s PPV (as received on the floor of the receiving room) when those spaces are in use. 35.7 For the prevention of building damage, the construction vibration level shall not exceed the limits in Condition 33 at all times. 35.8 For the protection of sensitive equipment, the construction vibration (including blasting) level shall not exceed 200mg (2m/s2) between 5-500Hz. Levels are to be measured on the floor supporting the Sensitive Equipment. 35.9 All attended noise and vibration measurements shall be undertaken by a suitably qualified and experienced expert. 35.10 For the avoidance of doubt, the MediaWorks conditions (Conditions 35, 40 and 66) only apply for so long as television, radio and/or interactive media facilities broadcast from the MediaWorks site. 35.11 Blasting shall not occur during MediaWorks Sensitive Times (as defined in Condition 35.1). Blasting shall occur at times to be agreed with MediaWorks and as documented in the SSCNVMP. Construction Noise and Vibration DWP For the avoidance of doubt, this condition is applicable to the management of construction noise and vibration on all receivers, including sensitive and notable receivers. 36.1 A Construction Noise and Vibration DWP shall be prepared and implemented. The objective of the Construction Noise and Vibration DWP is to provide for the development and implementation of identified best practicable option to avoid, remedy or mitigate the adverse effects on receivers of noise and vibration resulting from construction. 36.2 The Construction Noise and Vibration DWP shall: (a) Adopt the noise and vibration standards for construction set out in Conditions 31, 32, 33 and 34 of these designations; 1 2 36

4 5 6

(b) Be generally consistent with the draft Construction Noise and Vibration management plan submitted as part of the Notice of Requirement documentation (dated 23 August 2013); and (c) Identify methods to achieve best practicable option for mitigating adverse effects. 36.3 To achieve this objective, the Construction Noise and Vibration DWP shall include: (a) The roles and responsibilities of the noise and vibration personnel in the contractor team with regard to managing and monitoring adverse noise and vibration effects; (b) That piling and road cutting will be restricted to between the hours of 7am to 7pm, Monday to Saturday; (c) Construction machinery and equipment to be used and their operating noise and vibration levels; (d) Identification of construction activities that are likely to create adverse noise and vibration effects, the location of these in the construction site areas, and the distance to comply with the Project Criteria in Conditions 31, 32, 33 and 34; (e) The timing of construction activities that are likely to create an adverse noise and vibration effect; (f) The location of sensitive noise and vibration receivers; (g) A record of communication and consultation with sensitive noise and vibration receivers. The record must include a clear explanation of where any comments from

City Rail Link Notice of Requirement

Page 46


Condition Number

NoR Designati on Applies to

Condition

sensitive receivers have not been incorporated in the Construction Noise and Vibration DWP, and the reasons why not. This information must be included in the Construction Noise and Vibration DWP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (h) Specific measures to address the concerns raised by those sensitive receivers; (i) Specific training procedures for construction personnel including: (i) The project noise and vibration performance standards for construction (conditions 31, 32, 33 and 34); (ii) Information about noise and vibration sources within the construction area and the locations of sensitive noise and vibration receivers; and (iii) Construction machinery operation instructions relating to mitigating noise and vibration; (j) Methods and measures to mitigate adverse noise and vibration effects including, but not limited to, structural mitigation such as barriers and enclosures, the scheduling of high noise and vibration construction, use of low noise and vibration machinery, temporary relocation of affected receivers or any other measures or offer agreed to by the Requiring Authority and the affected receiver; (k) The proposed methods for monitoring construction noise and vibration to be undertaken by a suitably qualified person for the duration of construction works including: (i) Updating the predicted noise and vibration contours based on the final design and construction activities; (ii) Confirm which buildings are to be subject to a pre and post building condition survey in accordance with Condition 46. This includes consideration of those buildings in Appendix One and Two to these conditions; (iii) The timing and location for monitoring of buildings during construction is required (Note that the flow charts contained in Appendices B and C of Appendix J of the technical noise and vibration report provided as part of the Notice of Requirement should be used as a guide); (iv) Identifying appropriate monitoring locations for receivers of construction noise and vibration; (v) Procedures for working with the Communication and Consultation Manager to respond to complaints received on construction noise and vibration, including methods to monitor and identify noise and vibration sources; (vi) Procedures for monitoring construction noise and vibration and reporting to the Auckland Council Consent Monitoring officer; and (vii) Procedures for how works will be undertaken should they be required as a result of the building condition surveys; (l) Cross references to the specific sections in the Communication and Consultation Plan which detail how landowners and occupiers are to be communicated with around noise and vibration effects.

37

1

Site Specific Construction Noise Management Plan (SSCNMP)

2

For the avoidance of doubt, this condition does not apply to MediaWorks.

4

37.1 The objective of a SSCNMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not

5

City Rail Link Notice of Requirement

Page 47


Condition Number

NoR Designati on Applies to

6

Condition

comply with the Project Noise Standards. 37.2 Further to the Construction Noise and Vibration DWP in Condition 36, a SSCNMP shall be prepared for any receiver or activity for which air overpressure is either predicted or measured to exceed the limits in Condition 32, or where construction noise is either predicted or measured to exceed the Project Noise Standards in Condition 31, except where the exceedance of the standards in Condition 31 is less than 5 decibels and does not exceed : (a) 0700-2200: 1 period of up to 2 consecutive weeks in any 2 months (b) 2200-0700: 1 period of up to 2 consecutive nights in any 10 days 37.3 For predicted exceedances of less than 5 decibels (refer 37.2) monitoring shall be undertaken to confirm the actual noise levels. If exceedance is shown to be more than 5 decibels, or the period exceeds those detailed, then a SSCNMP will be prepared. 37.4 In addition to the SSCNMPs prepared in accordance with Condition 37.2, and notwithstanding Condition 37.1, the Requiring Authority shall prepare SSCNMPs specifying the best practicable option for management, methods and measures to mitigate all noise effects for the properties located at: (a) 1 Queen Street (Lot 1 DP 165403); (b) 21 Queen Street (Lot 1 DP 67723); (c) 29 Customs Street West (Lot 7 DP 77037) (d) 188 Quay Street (Lot 5 DP 63972 and Lot 1 DP 78340); and (e) 23-29 Albert Street (Lot 1 DP 116724). 37.5 SSCNMPs will identify: (a) The extent to which noise may exceed the Project Noise Standards in Condition 31 or the overpressure limits in Condition 32; (b) The timing and duration of any exceedance; (c) Details of the type of activity causing any exceedance; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCNMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate noise effects, including but not limited to, potential to offer temporary relocation of affected receivers, alternative ventilation, faรงade sound insulation improvements, building condition surveys in the case of overpressure generated by blast events, or other offers made by the Requiring Authority and whether these have been agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 37.6 The SSCNMP shall be submitted for the review of Auckland Council as part of the Outline Plan. The works shall then be undertaken in accordance with the SSCNMP confirmed by the Requiring Authority as part of the Outline Plan.

38

1

Site Specific Construction Vibration Management Plan (SSCVMP)

2

For the avoidance of doubt, this condition does not apply to MediaWorks.

4

38.1 The objective of a SSCVMP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from vibration that does not comply with

5

City Rail Link Notice of Requirement

Page 48


Condition Number

NoR Designati on Applies to

6

Condition

the Project Vibration Standards. 38.2 Further to the Construction Noise and Vibration DWP in Condition 36, a SSCVMP shall be prepared: (a) For any unoccupied building, structure or infrastructure for which construction vibration is either predicted or measured to exceed the Project Vibration Standards in Condition 33; (b) Where a complaint or concern is raised and the vibration level exceeds the amenity levels of Condition 34.2(a) and 34.2(b); (c) In response to other concerns or complaints where required (refer Condition 17).; (d) For the properties listed in Condition 37.4. 38.3 Where the amenity limits in Conditions 34.2(a) and 34.2(b) are exceeded: (a) Best practicable management of vibration must be applied; and (b) The vibration activity shall be scheduled to avoid disturbance. If this is not practicable then reasonable respite periods shall be provided to reduce vibration exposure. 38.4 The limits in condition 33 may be relaxed by a SSCVMP but only for a building, structure or infrastructure that has been assessed by a suitably qualified and experienced structural engineer and where it has been deemed to be capable of withstanding higher vibration levels without sustaining building or structural damage, and where appropriate vibration and building condition monitoring regimes are in place. 38.5 SSCVMPs will identify: (a) The timing and duration of any exceedance; (b) Details of the type of activity giving rise to any exceedance; (c) Site Specific vibration criteria that addresses the issue(s) of concern (i.e. building damage, amenity and sensitive equipment). Site Specific criteria shall be determined by a suitably qualified independent vibration expert; (d) The summary of the communication and consultation undertaken with the receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not. This information must be included in the SSCVMP provided to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan process specified in Condition 11; (e) The methods and measures to mitigate vibration effects, including but not limited to, investigating alternative low-vibration construction methods, undertaking highvibration works outside sensitive times, vibration barriers, building condition surveys, potential to offer temporary relocation of affected receivers, or other offers made by the Requiring Authority and agreed to by the affected receiver; (f) The reasons why the management and mitigation measures and methods reflect best practicable option. 38.6 The SSCVMP shall be submitted for the review of Auckland Council. The works shall then be undertaken in accordance with the SSCVMP confirmed by the Requiring Authority as part of the Outline Plan.

Notable Receivers 39

1

Notable Noise and Vibration Receivers

2 4

For the avoidance of doubt, Conditions 39.5 and 39.6 do not apply to MediaWorks. 39.1 Further to Condition 36, the Requiring Authority and its contractor, in conjunction with a

City Rail Link Notice of Requirement

Page 49


Condition Number

NoR Designati on Applies to

5 6

Condition

suitably qualified expert, shall work collaboratively with each notable receiver during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on each Notable Receiver. 39.2 In addition to the Construction Noise and Vibration DWP, a SSCNVMP shall be prepared for each identified Notable Receiver. The objective of the SSCNVMP is to detail the best practicable option to avoid, remedy or mitigate adverse noise and vibration effects on each Notable Receiver. 39.3 The Requiring Authority shall consult with the notable receiver throughout the duration of construction and update the SSCNVMP as required to achieve the objective in 39.2. 39.4 The SSCNVMP shall include: (a) The level at which noise and vibration effects on the notable receiver will unreasonably interfere with its operation. This will enable development of the site specific criteria. In the case of MediaWorks this is set out in Condition 40; (b) Construction activities and equipment which are likely to create adverse noise and vibration effects and the location and timing of these in relation to the notable receiver; (c) The methods and measures associated with the worksite including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (d) The methods and measures associated with the notable receiver building or operation including, but not limited to, potential for isolation of sensitive areas and equipment, dampening of reradiating surfaces and temporary relocation of affected receivers that are proposed to minimise adverse noise and vibration effects on the notable receiver; (e) Details about the methods to be adopted by the Requiring Authority to minimise construction noise and vibration effects on the notable receiver and the anticipated effectiveness of those methods; (f) A summary of the communication and consultation undertaken with the notable receiver. The summary must include a clear explanation of where any comments have not been incorporated, and the reasons why not; (g) Offers made by the Requiring Authority to the notable receiver to mitigate effects and the response by the operators, such as relocation, and whether those offers were accepted or not by the notable receiver; 39.5 If the parties cannot agree on any of the matters above they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the following matters to be included in the SSCNVMP: (a) The level at which noise and vibration effects on the notable receiver unreasonably interfere with its operation (the certified noise and vibration limit); (b) The mitigation methods and measures within the worksite (at source) including, but not limited to, structural mitigation such as barriers and enclosures, use of low noise and vibration machinery and the scheduling of high noise and vibration construction; (c) The mitigation methods and measures at the notable receiver including but not limited to: isolation of sensitive areas and equipment; dampening of reradiating surfaces; any response to such offers; and temporary relocation of affected receivers; (d) Whether or not the mitigation methods and measures reflect best practicable

City Rail Link Notice of Requirement

Page 50


Condition Number

NoR Designati on Applies to

Condition

management; and (e) Whether or not the residual effects are likely to cause significant disruption to the activities of the notable receiver. 39.6 Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with the notable receiver and/or through the above certification process without the consent of the notable receiver. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

40

6

Construction Noise and Vibration Management Plan – Mediaworks Further to Condition 36, a SSCNVMP shall be prepared for MediaWorks implementing the project standards in Condition 35. 40.1 The MediaWorks SSCNVMP shall identify high noise or vibration plant and machinery, and list the relevant items that require testing in accordance with Condition 40.4 and 40.8. 40.2 Prior to any demolition or construction commencing, the Requiring Authority shall undertake a noise survey to determine the Transmission Loss (TL) performance of the MediaWorks building envelope. This testing shall only be undertaken outside of Sensitive Times. 40.3 Prior to any demolition or construction commencing, the Requiring Authority shall undertake a vibration survey to determine the transfer function of the MediaWorks building structure from ground vibration outside the building to reradiated noise in Studio 1. This testing shall only be undertaken outside of Sensitive Times. 40.4 All high noise plant and machinery to be used at a location where it is predicted to generate noise levels in excess of 3 dB below the limits specified in Condition 35.2 shall be tested prior to use, to determine its Sound Power Level (Lw) at a sufficient distance from the MediaWorks building to ensure compliance. These measured Lws shall be used to predict the noise level at the MediaWorks building façade(s) from proposed construction scenarios. The façade TL (refer Condition 40.2) shall then be applied to predict the noise levels in the relevant rooms. 40.5 All high noise plant and machinery may not be used until Condition 40.4 is satisfied, taking into account the cumulative noise levels from active sources on the site. 40.6 The Requiring Authority and its contractor, in conjunction with a suitably qualified expert, shall work collaboratively with MediaWorks during the preparation of a SSCNVMP to confirm the extent and management of adverse effects on MediaWorks. 40.7 The SSCNVMP shall set out the requirements for monitoring, the number of monitors, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks. 40.8 Prior to the use of any high vibration equipment to be used at a location where it is predicted to generate vibration levels greater than 75% of the PPV vibration limits in Condition 35.3, 35.6, 35.7 and 35.8, or reradiated noise within 3 decibels of the limits in Condition 35.2, the Requiring Authority shall undertake vibration measurements at a sufficient distance from the MediaWorks building to ensure compliance, applying the transfer function required by Condition 40.3 to assess reradiated noise. These measurements shall be used to determine minimum set-back distances from the building to avoid potential exceedances of the vibration limits in Conditions 35.2, 35.3, 35.6, 35.7 and 35.8. The results of the testing and the outcomes affecting construction operations

City Rail Link Notice of Requirement

Page 51


Condition Number

NoR Designati on Applies to

Condition

shall be set out in the SSCNVMP. 40.9 The noise and vibration levels from construction shall be monitored to determine compliance with conditions 35.2, 35.3, 35.6, 35.7 and 35.8 continuously by automated noise and vibration monitors located at positions that will represent the noise and vibration level in the relevant spaces and for the relevant noise and vibration limits. The SSCNVMP shall set out the requirements for monitoring, the instrument location, any adjustments necessary if a proxy position is required and any other procedures or requirements that are necessary including methods to exclude extraneous sources. The data shall be available in real time to the Requiring Authority, Auckland Council and MediaWorks. 40.10 Monitoring to determine compliance or otherwise with Condition 35.67 relating to office amenity shall only be undertaken in response to complaints from MediaWorks. The measurements must be attended by a suitably qualified person. 40.11 The SSCNVMP shall set out corrective action measures that must be adopted in situations where any of the noise and vibration limits in Conditions 35.2, 35.3, 35.6, 35.7, and 35.8 are exceeded and where the noise and/or vibration levels are unacceptable to MediaWorks. The corrective action measures must include the following: (a) Immediate cessation of the work(s) that is giving rise to the exceedance; (b) A procedure to require the implementation of whatever measures are necessary to reduce the noise or vibration levels; (c) A monitoring procedure to determine compliance (once the remediation works are complete); (d) A requirement to ensure that the work(s) responsible for the exceedance are not recommenced during Sensitive Times; (e) A complaints procedure that is capable of effecting the immediate cessation of works including making a point of contact directly available 24 hours, seven days a week. 40.12

40.13

If there is a disagreement between the Requiring Authority and MediaWorks as to the content of the SSCNVMP, they shall each appoint a suitably qualified and independent expert, who shall jointly appoint an independent and suitably qualified third expert who shall certify the matters set out in Condition 40.11 and any other matters in dispute in the SSCNVMP. Following the above process the SSCNVMP shall be submitted for the review of Auckland Council as part of the Outline Plan. For the avoidance of doubt, the Requiring Authority shall not be entitled to make any changes to the SSCNVMP through the Outline Plan process following any agreement reached with MediaWorks and/or through the above certification process without the consent of MediaWorks. The works shall then be undertaken in accordance with the SSCNVMP confirmed by the Requiring Authority as part of the Outline Plan process.

Built Heritage/Archaeology Historic Character – Built Heritage 1 2 41

4 5 6

41.1 The Historic Character DWP shall be prepared to manage the adverse effects on built heritage and archaeology that may result from associated works prior to, during, and after the construction of the City Rail Link or any part of it. 41.2 The objective of the Built Heritage section is to avoid, remedy or mitigate adverse effects on built heritage as far as reasonably practicable. To achieve the above objective, the following shall, as a minimum, be included in the built heritage section of the Historic Character DWP:

City Rail Link Notice of Requirement

Page 52


Condition Number

NoR Designati on Applies to

Condition

(a) Preparation of a Building Record and Salvage Strategy that outlines a suitable set of procedures for the removal, storage and for later refitting and reuse of elements of heritage buildings and/or structures identified for demolition including the Griffiths Building, Beresford Toilets, Bluestone Toilets, and the rear annex to the building at 223-227 Symonds Street. (b) The proposed methods for monitoring building damage that is to be undertaken by a suitably qualified person for the duration of construction works. This includes confirming which Built Heritage buildings and structures are to be subject to a pre and post building condition survey through: (i) Using the updated predicted vibration contours undertaken in Condition 36; (ii) Reviewing those buildings in Appendix 2 to these conditions in accordance with Condition 46.1; (iii) Reviewing buildings within the designation footprint (including above sub-strata designation) or located in close proximity to identify buildings which have been recognised as having heritage value as a result of scheduling under the Historic Places Act 1993 or in the Auckland Unitary Plan. (c) Identification and methodology for recording of Built Heritage directly affected by the construction, or associated pre- and post-construction works (i.e. within the surface designation footprint), which cannot be retained and / or adaptively re-used / partially retained. For the avoidance of doubt, the following buildings and structures may be demolished: (i) Bluestone Toilets (SCDP Category B); (ii) Beresford Toilets; (iii) Rear annex to building at 229-231 Symonds Street; and (iv) Griffiths Building. (d) Identification and methodology for recording Built Heritage directly affected by the construction, or associated pre- and post-construction, which are to be: (i) Adaptively reused; (ii) Partially retained in design and construction; or (iii) Built heritage elements have been integrated into other elements of the City Rail. (iv) In particular, the Requiring Authority shall explore the adaptive re-use of the buildings at 51-53 Victoria Street West (known as Martha’s Corner building) with complete demolition only considered as a last resort. As guidance, an appropriate level of adaptive re-use could include retention of the façade on all street frontages or the utilisation and incorporation of elements of the building into the design: (e) How Built Heritage Buildings and Structures will be protected during construction through the use of screening or other protective measures to mitigate adverse construction effects; (f) How mitigation or rectification of damage to Built Heritage Buildings and Structures will be addressed; and (g) Cross references to the specific sections in the Communication and Consultation Plan which detail how the Auckland Council Heritage Department, the New Zealand Historic Places Trust, and mana whenua (see condition 15) are consulted, and the communication with the general public on the management of the adverse effects relating to Built Heritage.

City Rail Link Notice of Requirement

Page 53


Condition Number

NoR Designati on Applies to

Condition

(h) That the detailed design of the reinstated and/or replacement canopies on heritage buildings shall be based on an engineered architectural design which replicates the present installations, and/or recovers original (historical) construction and architectural detail. Historic Character - Archaeology 42.1 A Historic Character DWP shall be prepared to manage the adverse effects on built heritage and archaeology that may result during construction of the City Rail Link or any part of it. 42.2 The objective of the Archaeology section of the Historic Character DWP is to avoid, remedy or mitigate adverse effects on archaeological remains during construction, as far as reasonably practicable. 42.3 To achieve the above objective the following matters shall be included in the Archaeology section of the Historic Character DWP: (a) Constructor roles and responsibilities, stand-down periods and reporting requirements are to be clearly identified; (b) How procedures for archaeological investigations and monitoring of preliminary earthworks are to be implemented in areas where there is potential for archaeological remains to be discovered; (c) Procedures for the discovery of, including accidental discovery of archaeological remains including: (i) The ceasing of all physical construction works in the immediate vicinity of the discovery; 1 42

4 5 6

(ii) Practices for dealing with the uncovering of cultural or archaeological remains and the parties to be notified (including, but not limited to, appropriate iwi authorities, the Auckland Council Consents Monitoring officer, the New Zealand Historic Places Trust, and the New Zealand Police (if koiwi (human skeletal remains) are discovered); (iii) Procedures to be undertaken before physical works in the area of discovery can start again, including any iwi protocols, recording of sites and material, recovery of any artefacts, and consultation to be undertaken with iwi, Auckland Council Consent Monitoring officer and Heritage Unit, and with the New Zealand Historic Places Trust; and (iv) Procedures for recording any archaeological remains or evidence before it is modified or destroyed, including opportunities for the conservation and preservation of artefacts and ecofacts (biological material) that are discovered. Consideration shall be given to the incorporation of in-situ material or artefacts into the design of stations and / or public places associated with the City Rail Link project. Consideration shall also be given to the provision for ‘post-excavation’ assessment analysis and publication of material within 24 months of completion of construction. (v) Provision for ‘post-excavation’ archiving, assessment and analysis of the archaeological records and materials; publication of results of that work within 24 months of completion of construction assessment analysis and publication of material within 24 months of completion of construction. (d) Training procedures for all contractors are to be undertaken in advance of construction, regarding the possible presence of cultural or archaeological sites or material, what these sites or material may look like, and the relevant provisions of

City Rail Link Notice of Requirement

Page 54


Condition Number

NoR Designati on Applies to

Condition

the Historic Places Act 1993 if any sites or material are discovered; (e) Cross references to the specific sections in the Communication and Consultation Plan which details how the Auckland Council Heritage Department, the New Zealand Historic Places Trust, mana whenua (see condition 8) are consulted, and the communication with the general public on the management of the adverse effects relating to archaeology. Heritage Advisory Group and Composition 43.1 The Requiring Authority must engage, at its expense, a panel of suitably qualified and experienced heritage experts to discharge the functions required by conditions 44 and 45. The Heritage Advisory Group will consist of three independent experts, whose members will not be directors or employees of the Requiring Authority, the New Zealand Historic Places Trust or the consent authority. The Heritage Advisory Group will comprise one nominee from the Requiring Authority, one nominee from the consent authority, and a third nominee appointed jointly by the Requiring Authority's and consent authority's nominees. 43

1

43.2 Before establishing the Heritage Advisory Group the Requiring Authority shall seek the opinion of NZHPT on the appointment of the Heritage Advisory Group. 43.3 The Heritage Advisory Group may determine its own processes and procedures for conducting its meetings and performing its functions as it sees fit, including methods for ensuring any disagreements between panel members are resolved, and must meet as necessary to fulfil its functions. All costs associated with the role and function of the Heritage Advisory Group and appropriate administrative support must be paid by the Requiring Authority. If any member of the Heritage Advisory Group is unable to continue in the role for whatever reason, then a replacement member must be appointed using the process set out in this condition. Heritage Advisory Group Function 44.1 The functions of the Heritage Advisory Group are to review the assessment of the alternatives and option selected by the Requiring Authority to manage the adverse effects on the heritage values of the Bluestone wall and the Martha’s Corner building. 44.2 In relation to Bluestone Wall, the Heritage Advisory Group will: (a) Certify that the method selected by the Requiring Authority under Condition 45 will have the least impact on the heritage value of the Bluestone wall compared to other reasonably practicable methods; or

44

1

(b) Prepare a report as to why the method selected by the Requiring Authority under Condition 45 will not have the least impact on the heritage value of the Bluestone wall and set out details as to an alternative recommended reasonably practicable method. 44.3 In relation to Martha’s Corner, the Heritage Advisory Group will: (a) Certify that the heritage outcomes for Martha’s Corner adhere to the intent of Condition 41; or (b) Prepare a report as to why the method selected by the Requiring Authority will not adhere to the intent of Condition 41 and set out details as to the recommended reasonably practicable method. 44.4 The Requiring Authority must provide Auckland Council with the Heritage Advisory Group’s certification or report, and if applicable the reasons the Requiring Authority has not selected the method recommended by the Heritage Advisory Group.

City Rail Link Notice of Requirement

Page 55


Condition Number

NoR Designati on Applies to

Condition

Bluestone Wall Management Plan 45.1 A Bluestone Wall Management Plan shall be prepared to manage the adverse effects on the heritage values of the Bluestone wall during the construction of the City Rail Link. 45.2 The objective of this Plan is to minimise adverse effects on the heritage values of the Bluestone wall during the construction of the City Rail Link by adopting the best practicable option. 45

1

45.3 To achieve the above objective, the following shall be included in the Bluestone Wall Management Plan: (a) Identification of the key heritage values of the wall; (b) Assessment of the alternative construction methods to ensure that construction of the City Rail Link has the least impact on the heritage value of the Bluestone wall, within the practical constraints of constructing the project; and (c) The option selected by the Requiring Authority. 45.4 The Bluestone Management Plan shall be prepared in consultation with the NZHPT and the Heritage Advisory Group (set out in Condition 43).

Building Condition Surveys Process for Building Condition Surveys 46.1 Prior to construction, as a minimum those buildings listed in Appendix One and Appendix Two or identified pursuant to Condition 41.2(b) will be considered for a building condition survey. A building condition survey will be undertaken where it is assessed that there is potential for damage to buildings or structures arising from construction as determined by an independent suitably qualified person appointed by the Requiring Authority based on the criteria below unless the relevant industry criteria applied at the time or heightened building sensitivity or other inherent building vulnerability requires it. Building damage criteria will initially be assessed in accordance with Burland, J.B. (1997) “Assessment of Risk of Damage to Buildings due to Tunnelling and Excavation�. Additional factors which may be considered in determining whether a building condition survey will be undertaken include:

46

1

(a) Age of the building;

2

(b) Construction types;

4

(c) Foundation types;

5

(d) General building condition;

6

(e) Proximity to any excavation; (f) Whether the building is earthquake prone; and (g) Whether any basements are present in the building. 46.2 Where prior to construction it is determined that a Building Condition Survey is required in accordance with Condition 46.1, or if measurements exceed the criteria in Condition 33: (a) The Requiring Authority shall employ a suitably qualified person to undertake the building condition surveys and that person shall be identified in the CEMP; (b) The Requiring Authority shall provide the building condition survey report to the relevant property owner within 15 working days of the survey being undertaken, and additionally it shall notify and provide the Auckland Council Consent Monitoring officer a copy of the completed survey report;

City Rail Link Notice of Requirement

Page 56


Condition Number

NoR Designati on Applies to

Condition

(c) The Requiring Authority shall contact owners of those buildings and structures where a Building Condition Survey is to be undertaken to confirm the timing and methodology for undertaking a pre-construction condition assessment; (d) The Requiring Authority shall record all contact, correspondence and communication with owners and this shall be available on request for the Auckland Council Consent Monitoring Officer; (e) Should agreement from owners to enter property and undertake a condition assessment not be obtained within 3 months from first contact, then the Requiring Authority shall not be required under these designation conditions to undertake these assessments; (f) The Requiring Authority shall undertake a visual inspection during "active construction" if requested by the building owner where a pre-construction condition assessment has been undertaken. (g) The Requiring Authority shall develop a system of monitoring the condition of existing buildings which is commensurate with the type of the existing building and the proximity of the CRL works. The purpose of monitoring is to assess whether or not active construction is compromising the structural integrity of the building. (h) The Requiring Authority shall, during the Building Condition Survey, determine whether the building is classified as Commercial / Industrial / School or a Historic or sensitive structure in terms of Condition 33. 46.3 During construction: (a) The Requiring Authority shall implement procedures that will appropriately respond to the information received from the monitoring system. Where necessary this may include the temporary cessation of works in close proximity to the relevant building until such time as measures are implemented to avoid further damage or compromise of the structural integrity of the building. (b) Any damage to buildings or structures shall be recorded and repaired by the Requiring Authority and costs associated with the repair will met by the Requiring Authority. 46.4 Following construction: (a) The Requiring Authority shall, within 12 months of the commencement of operation of the City Rail Link, contact owners of those buildings and structures where a Building Condition Survey was undertaken to confirm the need for undertaking a post-construction condition assessment; (b) Where a post-construction building condition survey confirms that the building has deteriorated as the result of construction or operation works relating to the City Rail Link, the Requiring Authority shall, at its own cost, rectify the damage; and 46.5 Where the Requiring Authority is required to undertake building repairs in accordance with Conditions 46.3(b) or 46.4(b), such repairs shall be undertaken as soon as reasonably practicable and in consultation with the owner of the building. Urban Design 1 47

4 5 6

Urban Design Principles 47.1 The objective of the Urban Design DWP is to enable the integration of the CRL’s permanent works into the surrounding landscape and urban design context. 47.2 An Urban Design DWP shall be developed to ensure that the areas within the designation footprint used during the construction of the City Rail Link are to be restored and the

City Rail Link Notice of Requirement

Page 57


Condition Number

NoR Designati on Applies to

Condition

permanent works associated with the CRL are developed in accordance with urban design principles. The following Principles from the Urban Design Framework submitted as part of the Notice of Requirement documents will be used to inform the Urban Design and Landscape Plan: (a) Mana Whenua Principles – see Condition 49; (b) Movement and Connections – (i) Existing Networks - Structures of the CRL should not interrupt or adversely change the function of existing public open space, street networks and infrastructure. (ii) Entrance Location - Station entrances should be clearly identifiable and conveniently located in relation to existing and anticipated main pedestrian routes and destinations. (iii) Intuitive Orientation - The location and nature of structures resulting from the CRL (station entrances in particular) should facilitate intuitive orientation and support a legible street network. (iv) Way Finding - Coherent signage should be utilised to aid intuitive orientation and way finding. (v) Mode Integration - Spatial integration with bus stops as well as kiss and ride should be facilitated where possible without imposing on the quality of public realm. (vi) Bicycle Parking – Appropriate numbers of safe bicycle storage or parking should be provided in each station environment. (vii) Street Crossings - Safe pedestrian street crossings shall be provided in the immediate vicinity of station entrances to the extent practicable. The provision of level street crossings is preferable over any grade separated solutions. (viii) Footpaths – Footpaths surrounding stations need to be adequate to provide for pedestrians entering and exiting the stations. (ix) Grade separated rail crossings – Structures associated with grade separated rail crossings need to be carefully and sensitively designed and in accordance with crime prevention through environmental design principles to ensure appropriate amenity and safety are retained or achieved. Measures to achieve this may include: a.

Utilising permeable balustrades on overbridges;

b.

Maximising the width of the footpath at grade in street reserves;

c.

Orientating any steps parallel to overbridges;

d.

Providing appropriate levels of lighting (in accordance with the Auckland Transport Street Lighting Policy (Appendix 1) for “Pathways in high risk, high brightness areas”); and

e.

Treatment of the sides of ramps and footpaths to enhance visual amenity.

(x) Grade separated rail crossings – Permeable balustrades on overbridges should be required not only for crime prevention purposes but to enable views into the neighbouring sites. For clarity all balustrades comprised within Normanby Road grade separation works (as defined in condition 30.1(l) shall be permeable including without limitation the ramp to be constructed into the site at 32 Normanby Road. (xi) The Porters Avenue Bridge (lift and bridge structure above finished ground level)

City Rail Link Notice of Requirement

Page 58


Condition Number

NoR Designati on Applies to

Condition

shall be located no closer than 3.5m from the property boundary of 5 Porters Avenue (ALLOT 236 SEC 10 Suburbs AUCKLAND). Foundation support (i.e. below finished ground level) for the bridge may extend closer but shall not cross the property boundary. (xii) The design of the Porters Avenue and Fenton Street pedestrian/cycle bridges shall: a.

Minimise loss of privacy on adjacent residential sites, including by locating the pedestrian/cycle bridge in the western half of the Avenue;

b.

Ensure the lifts are through lifts to carry bicycles; and

c.

Incorporate bicycle push ramps into the side of the pedestrian stairways.

(xiii) The extensions to Ruru Street and Nikau Street shall generally be undertaken in accordance with the indicative road layout shown on drawing CRL-SYW-RME000-DRG-0110 Revision 1 dated 26/7/16. (c) Public Realm and Landscape – (i) Existing Streetscape – Structures of the CRL should be designed to respect and contribute positively to the form and function of existing public open space. (ii) Universal Access – Station environments should promote universal access (e.g. footpath ramps and smooth ground surfaces). (iii) Safe Environments – Structures resulting from the CRL should promote safe environments. The station entrances should release patrons into safe public spaces that are well lit at night, overlooked by other users (e.g. residents or workers) and have sufficiently wide and unobstructed footpaths. (iv) Reinstated Surfaces - The design and construction of reinstated streetscapes should be coherent with the wider area and/or recent public realm upgrades in the area. (v) Station Plazas - The design and construction of station plazas should be coherent with the wider area and/or recent public realm upgrades in the area. (vi) Public Art - Integration of art and design should foster local identity and character and reflect and/or interpret local characteristics including natural heritage and Mana Whenua cultural narratives, history, art and particular traits of the local community. (vii) Landscape Planting – Plant species used in station environments and/or as part of landscape plantings should consider the opportunity to acknowledge the area’s pre-human ecology as and where appropriate. This may include species which connect strongly with Mana Whenua cultural narratives. (viii) Entrances within the Road Reserve - Designs for station entrances within the road reserve should be designed to consider the impacts upon other modes of traffic, including the expected pedestrian patronage. (ix) Utility Structures - Above ground utility structures (e.g. vents, access services) should be designed to minimise any negative effect on public realm. Where possible these structures should be integrated with other buildings. (x) Where landscape planting is affected by construction works on private properties, replanting and/or mitigation of any such landscaping shall be undertaken in consultation with those landowners, and in recognition of wider mitigation works required for those properties (e.g. vehicle parking and access

City Rail Link Notice of Requirement

Page 59


Condition Number

NoR Designati on Applies to

Condition

requirements). 47.3 The Urban Design DWP shall show how these principles have been used to guide and influence the design of permanent works associated with the CRL, and how the design has responded or otherwise to these principles and initiatives. 47.4 The work to restore those areas within the designation footprint used during construction of the City Rail Link will occur as part of construction or within six months of the City Rail Link being operational. Auckland Council Urban Design Panel 47.5 The Requiring Authority shall request the Auckland Council to refer the Urban Design DWP to the Auckland Urban Design Panel (or other equivalent entity (if any) at that time) and invite the Auckland Urban Design Panel to comment on: (a) The degree to which the Urban Design DWP has appropriately responded to the principles listed in 47.2 and 49.1; (b) The degree to which station plans have appropriately responded to the principles listed in Condition 54.1. 47.6 As part of the Urban Design DWP submitted, the Requiring Authority shall: (a) Provide a record of feedback received from the Auckland Urban Design Panel (or equivalent entity at that time); (b) Provide detail of how the Urban Design DWP has responded to any feedback received from the Auckland Urban Design Panel (or equivalent entity at that time) and, where they have not, the reasons why; (c) Provide detail regarding the degree to which the community stakeholder, affected party and affected in proximity party feedback has been considered and where applicable incorporated into design. Where feedback has not been incorporated, the Requiring Authority shall provide comment as to reasons why the feedback has not been incorporated; (d) The information set out in (a), (b) and (c) above must be included in the Urban Design DWP submitted to both the independent peer reviewer and Auckland Council as part of the Outline Plan. Mitigation Planting Requirements

1 48

4 5 6

48.1 The Urban Design DWP shall include any replacement planting proposed to mitigate the adverse effects of tree and vegetation removal from within the designation footprint. It is acknowledged that the mitigation of effects of tree and vegetation removal will be considered in response to the urban design principles of Condition 47. 48.2 Any landscaping included under the Urban Design DWP shall be implemented in accordance with this plan within the first planting season following the City Rail Link being operational. If the weather in that planting season is unsuitable for planting, as determined by the Auckland Council Consent Monitoring officer (in consultation with the Auckland Council Parks Department), the landscaping shall instead be implemented at the first practicable opportunity thereafter. The next practicable opportunity shall be agreed by the Auckland Council Consent Monitoring officer. 48.3 The landscaping will be maintained by the Requiring Authority for a period of 5 years for specimen trees and 3 years for all other landscape planting.

49

1

Engagement with Mana Whenua and the Mana Whenua Principles

4

49.1 The Urban Design DWP shall include:

City Rail Link Notice of Requirement

Page 60


Condition Number

NoR Designati on Applies to

5 6

Condition

(a) How mana whenua (see Condition 8) have been engaged with during its development in relation to the implementation and interpretation of the Principles set out under Condition 47, and particularly in relation to the mana whenua principles set out below: (i) Mana / Rangatiratanga – As the original local authorities of Tamaki Makaurau, Iwi require high level Treaty based relationships with all key stakeholders including the Requiring Authority and Auckland Council which recognise their Tangata Whenua status in order to fulfil their roles as kaitiaki. Such partnership relationships can then inform engagement with AT / Council at all levels including direct involvement with design consortia. Relationships are required at governance and senior management levels. Such relationships are a precursor to actualising the other 6 principles. (ii) Whakapapa – Names and genealogical connections– reviving names revives mana through Iwi connections to specific ancestors and events / narratives associated with them. An Iwi inventory of names associated with a given site can be developed so that the most appropriate names are identified to develop design, interpretation and artistic responses. (iii) Tohu – Acknowledging the wider significant Iwi cultural land marks associated with the CRL route and their ability to inform the design of the station precincts, entrances and exits. In particular exploring opportunities to maximise view shafts to such tohu / landmarks as a way of both enhancing cultural landscape connections and as way finding / location devices. (iv) Taiao – Exploring opportunities to bring natural landscape elements back into urban /modified areas e.g. specific native trees, water / puna wai (springs) – promoting bird, insect and aquatic life to create meaningful urban eco systems which connect with former habitats, mahinga kai (food gathering areas) and living sites. (v) Mauri tu – Ensuring emphasis on maintaining or enhancing environmental health / life essence of the wider site – in particular focusing on the quality of wai / water (puna / springs), whenua / soil and air. In particular any puna or underground waterways encountered should be carefully treated with Mana Whenua assistance to ensure their mauri is respected and enhanced where possible. It is also important to minimise the disturbance to Papatuanuku through carefully planned ground works. (vi) Mahi toi – Harnessing the Creative dimension through drawing on names and local tohu to develop strategies to creatively re-inscribe iwi narratives into architecture, interior design, landscape, urban design and public art. (vii) Ahi kaa – need to explore opportunities to facilitate living presences for iwi / hapu to resume ahi-kaa and kaitiaki roles in and around the CRL route and new station precincts; and (b) A summary of the engagement with mana whenua (see Condition 15) and identification of where design has incorporated the mana whenua principles and other mana whenua aspirations. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. The summary must be included in the Urban Design DWP submitted to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan.

50

1

Specific Area Requirements: Britomart to Aotea Station 50.1 For this designation the Urban Design DWP shall include how the following are to be

City Rail Link Notice of Requirement

Page 61


Condition Number

NoR Designati on Applies to

Condition

restored following completion of the City Rail Link construction works: (a) Queen Elizabeth Square and lower Queen Street between Quay Street and Customs Street; (b) Albert Street between Quay Street and Victoria Street; and (c) Albert Street between Victoria Street and Mayoral Drive including those part of Victoria and Wellesley Streets, the Council owned land on the southeast corner of Albert and Wellesley Streets which is to be used as a construction area, affected by surface construction works; and (d) Kingston Street. 50.2 The restoration plan for this designation shall demonstrate how street upgrades and public realm improvements have been considered when Albert Street and Mayoral Drive are reinstated. This should include as a minimum how the design and construction utilises material palettes, planting schedules and street furniture that are coherent with the surrounding streetscape character. Specific Area Requirements: Karangahape Station area 51.1 For this designation the Urban Design DWP shall include restoration plans (showing how the following are to be restored following completion of the City Rail Link construction works): (a) Beresford Square and Street including where surface works have occurred within Pitt Street; and (b) Mercury Lane. 51.2 The restoration plan for this designation shall demonstrate how street upgrades and public realm improvements have been considered when Beresford Street, Pitt Street and Mercury Lane are reinstated. This should include as a minimum: (a) How the design and construction utilises material palettes, planting schedules and street furniture that are coherent with the surrounding streetscape character. (b) Methods for street upgrades and public realm improvements. 51

4

(c) With reference to condition 47.2(c)(ii), in Mercury Lane how either a maximum gradient of 1 in 12 for the footpath and approaches to the Station will be achieved, or the compensatory measures to be introduced to address a steeper grade. The number and location of any pause points to improve accessibility should be identified, taking into account other users of the footpath. 51.3 Final public realm design for Mercury Lane shall include the following features: (a) The widening of footpaths of both sides of Mercury Lane between Karangahape Road and the station entrance including the provision of level pause points at intervals within the paved areas with seats and soft landscaping; (b) The forming of a new public laneway between Mercury Lane and East Street, beside the southern edge of the station entrance building; (c) The forming of a raised street surface pedestrian crossing between Cross Street and the station entrance; (d) New street lighting to Mercury Lane; and (e) Resurfacing of all roadway surfaces affected by the works.

52

5

Specific Area Requirements: Newton Station area 52.1 For this designation the Urban Design DWP shall include restoration plans (showing how the following are to be restored following completion of the City Rail Link construction

City Rail Link Notice of Requirement

Page 62


Condition Number

NoR Designati on Applies to

Condition

works) for those areas used for surface construction works within the designation footprint, including the construction yard located on the northeast corner of Mt Eden Road and Symonds Street. Specific Area Requirements: North Auckland Line area 53.1 For this designation the Urban Design DWP shall include the following: (a) Restoration Plans showing how the worksite area will be maintained during the construction period. (b) Restoration Plans showing how the following are to be restored after construction completion: 53

6

(i) The replacement of Mt Eden Road Bridge; (ii) The area used for the grade separation of Porters Avenue; (iii) The area used for the grade separation of Normanby Road; and (iv) The replacement of the pedestrian connection, to be provided over the railway, between Ngahura Street and Fenton Street, including a connection to the Mount Eden Station. (c) How the bulk, scale and massing of structures resulting from the City Rail Link at Mt Eden Station are integrated with the components of the Mt Eden Station located in the adjacent North Auckland Line designation. Station Plan Requirements 54.1 The Urban Design DWP shall include a Station Plan/s (report and design plan/s as required) and include the following: (a) The design details showing both the above ground and below ground elements of the station/s; (b) How the above ground and below ground design of the stations has taken into account the following principles: (i) Overarching - stations should achieve a successful and memorable transport experience. (ii) Function - stations will provide safe, functional and clear transport solutions.

1 54

4 5

(iii) Performance - stations will provide a credible, sustainable design outcome that responds to climate, site and social economics. (iv) Personality - stations will provide an expression that contributes to their context and local identity and will respond to an appropriate network wide identity. (v) Existing and New Building Structures. (vi) Built Heritage: •

Where built heritage is required for City Rail Link station requirements, adaptive reuse strategies should be considered to preserve the building’s role in establishing the streetscape and urban character. The development of new buildings and structures should minimise impact on, and disturbance of, Built heritage listed by the New Zealand Historic Places Trust or the Auckland Council District Plan that play a significant role in establishing the streetscape and urban character of the local area.

(vii) Bulk, Scale and Massing: •

Bulk, scale and massing of structures resulting from the City Rail Link (station buildings in particular) should be sympathetic with the surrounding built urban form.

City Rail Link Notice of Requirement

Page 63


Condition Number

NoR Designati on Applies to

Condition

• •

Aotea Station building frontages should correspond with the road reserve boundary unless a specific station plaza area is intended. Karangahape Road station building(s) should be sensitively designed so as to contribute positively and to complement the good public realm and urban form qualities that currently exist in this area of Karangahape Road, Pitt Street and the upper end of Beresford Street. The redevelopment of land acquired for the Newton Mt Eden Station provides the opportunity for a continuous active building frontage to correspond with the road reserve boundary, providing:  This does not conflict with the operation requirements of the station; or  Unless a specific station plaza area is intended.

(viii) Active Frontage – Structures resulting from the City Rail Link should present an active frontage towards public spaces like streets, squares, pedestrian walkways or station plaza areas provided that this doesn’t conflict with the operation requirements of the station. Where no active frontage is proposed, an explanation of the reasons shall be outlined in the Urban Design DWP. (ix) Weather Protection – Where practicable, station entrances should provide some weather protection along their frontage (e.g. verandahs, awnings, canopies etc.) and these should be considered as part of the design. (x) Adaptability – The design of structures resulting from the City Rail Link should be able to adapt to change over time (e.g. change of uses, innovations in technology etc.) where reasonably practicable and anticipate opportunities (e.g. additional entrances) that may become possible in the future. The station design should not inhibit wider development opportunities (e.g. above or around station entrances). (xi) Identity – The design of the station entrances should provide an expression that reflects their respective context and local cultural identity. They could reflect, respond and/or interpret local characteristics like natural or Mana Whenua heritage, history, art, particular traits of the local community and unique architectural and urban forms of the area. (xii) Construction Quality – The design and construction of structures resulting from the City Rail Link (station buildings in particular) should be of a quality that lasts over time. Materials should be selected that are highly durable, elegant and vandal resistant where they come into contact with patrons. (xiii) Mana Whenua Principles – see Condition 49. (c) How these principles have been used to guide and influence the design, and how the design has responded, or otherwise, to these principles and initiatives; and (d) A summary of the engagement with mana whenua (see Condition 15) and identification of where design has incorporated the mana whenua principles and other mana whenua aspirations into station design. The summary must include a clear explanation of where any comments have not been incorporated and the reasons why not. The summary must be included in the Urban Design DWP submitted to both the Independent Peer Review Panel and Auckland Council as part of the Outline Plan. Trees and Vegetation

City Rail Link Notice of Requirement

Page 64


Condition Number

NoR Designati on Applies to

Condition

Trees and Vegetation DWP 55.1 A Trees and Vegetation DWP shall be prepared to manage the adverse effects from the removal of trees and vegetation during the construction of the City Rail Link or any part of it. 55.2 The objective of the Trees and Vegetation DWP is to avoid the removal of scheduled trees as far as practicable. Where trees are identified for removal in surface works the Requiring Authority will remedy or mitigate the adverse effects of construction on trees and vegetation. 55.3 To achieve the above objective the following shall be included in the Trees and Vegetation DWP and implemented as required:

1 55

4 5 6

(a) Confirmation of the trees to be removed due to surface construction works and whether it is appropriate and feasible to relocate or store these trees for replanting. The removal of schedule trees which form a significant group should only be undertaken as a last resort; (b) A list of trees, which due to being located in proximity to construction works, have root systems and / or foliage within and / or overhanging the surface designation footprint, and the methods to be used, where practicable, to protect these trees from construction works; (c) Cross references to the Urban Design DWP and the proposed mitigation of any tree / vegetation removal through replanting trees at a 1:1 ratio, re-instatement of the area, and other methods. In preparing the Trees and Vegetation DWP, the Requiring Authority shall seek input from the Auckland Council Parks Department with regard to tree species / vegetation selection, tree pit construction where deemed necessary, and the positioning of replacement trees and from directly affected land owners with regards to preferences for any replacement planting for vegetation / trees removed from private property or for any replacement planting on private property; (d) Other methods to be used to monitor and report on the management of the adverse effects from tree / vegetation removal; and (e) Cross references to the specific sections in the Communication and Consultation Plan which detail how the Auckland Council Parks Department, mana whenua (see condition 8) are consulted, and communication with the general public on the management of the adverse effects relating to the removal of trees and vegetation.

Public Art Public Art DWP 56.1 A Public Art DWP shall be prepared to manage the adverse effects on public art located within or in close proximity to the designation footprint. 56.2 The objective of the Public Art DWP is to enable: 56

1

(a) The appropriate removal and / or relocation of one piece of public art directly affected by the construction of the City Rail Link; (b) The protection of two pieces of public art that are located on public land in close proximity to the City Rail Link construction works. 56.3 To achieve the above objective the following shall be included in the Public Art DWP and implemented as required: (a) The process that will be undertaken to remove the public art work known as "Enduring Fires" (at the time of the Notice of Requirement process located within Queen Elizabeth Square), including the consultation undertaken with the Auckland

City Rail Link Notice of Requirement

Page 65


Condition Number

NoR Designati on Applies to

Condition

Council and Ngati Whatua ki Tamaki or Ngati Whatua o Orakei as to its removal, storage, re-establishment or relocation and / or replacement (as part of the restoration works associated with the City Rail Link construction); (b) The process that will be undertaken to protect or remove the public art work known as "Maori Warrior" (at the time of the Notice of Requirement process located on the pavement of Quay Street adjacent to 1 Queen Street), including the consultation undertaken with the Auckland Council as to its protection during construction or whether it should be removed, stored, relocated and / or replaced (as part of the restoration works associated with the City Rail Link construction); (c) The process to protect the public art known as "Matahorua Anchor and Tainui Anchor" (at the time of the Notice of Requirement process located at the northern end of the Bledisloe Building on Wellesley Street) from construction works to the west, including the consultation undertaken with the Auckland Council as to its protection. 56.4 If one does not already exist, an asset management plan shall be prepared by the Requiring Authority in collaboration with Auckland Council for any of the above listed public art works as part of any protection or removal process. 56.5 Should the above public art works be removed from these sites prior and separate to the City Rail Link project, this condition will not need to be complied with. Contaminated Land Contamination DWP 57.1 A Contamination DWP shall be prepared to manage the adverse effects relating to contaminated land during the construction of the City Rail Link or any part of it. 57.2 The objective of the Contamination DWP is to avoid, remedy or mitigate the adverse effects of construction on human health which may result from the disturbance of contaminated materials during construction. 57.3 To achieve the above objective the following shall be included in the Contamination DWP and implemented as required: (a) A health and safety plan that addresses: (i) Worker safety in relation to hazardous substances; and 1 57

4 5 6

(ii) Worker training with regard to handling hazardous substances, identifying potentially contaminated soil / material, and notification procedures for discovery of contamination; (b) Procedures for how erosion and sediment control, storm water, dust, and odour control measures will manage the removal of contaminated soil / material; (c) Procedures for contaminated soil classification, management and disposal of contaminated soil / material; (d) Where any trenches/excavations during civil works are to be sealed as a result of contamination and how this is to be recorded; (e) How and which work areas are to be restricted to authorised personnel only and procedures to limit the presence of ignition sources in these areas (e.g. no smoking within or adjacent to construction area, no welding or open flames near areas with high concentrations of hydrocarbon contamination); (f) Procedures for the monitoring and management of the removal of contaminated soil / material by a suitably qualified environmental specialist; (g) How the placement of re-used contaminated soil / material will be recorded and

City Rail Link Notice of Requirement

Page 66


Condition Number

NoR Designati on Applies to

Condition

tracked; (h) Where areas for stockpiling and storing contaminated soil / material will be established on the construction site and the procedures for managing the containment of the contaminated soil / material in these areas; (i) Cross references to the specific sections in the Communication and Consultation Plan which detail how the general public are to be communicated with on the management of the adverse effects relating to the removal of contaminated soil / material. Contamination Validation Report at Completion of Construction 1 58

4 5 6

58.1 At the completion of construction works a validation report will be prepared in accordance with any Ministry for the Environment guidelines and submitted to the Auckland Council Consent Monitoring officer documenting the management of soil and evidence of appropriate disposal. The validation report shall include a record of all analytical results, volumes, tip dockets, and any incidents or complaints and how these were addressed. The validation report shall also identify any areas which need on-going monitoring and management by the Requiring Authority.

Air Quality Air Quality DWP 59.1 An Air Quality DWP shall be prepared to avoid, remedy or mitigate the adverse effects on air quality during the construction of the City Rail Link or any part of it. 59.2 The objective of the Air Quality DWP is to detail the best practicable option to avoid dust and odour nuisance being caused by construction works and to remedy any such effects should they occur. 59.3 To achieve the above objective the following shall be included in the Air Quality DWP and implemented as required: (a) The procedures to be implemented for the continuous monitoring of Total Suspended Particulate (TSP) concentrations and meteorology including, but not limited to, the establishment of two monitoring sites (to the north and south of the site); 1 59

4 5 6

(b) Identification of the sensitive locations, and the specific methods for monitoring, including trigger limits to determine whether further action (such as implementation of the mitigation measures discussed below or other mitigation measures) is required; (c) Procedures for responding to malfunctions with construction machinery or works causing accidental dust discharges including, but not limited to, the requirement to remedy any malfunction within 24 hours; (d) Procedures for monitoring weather conditions and the requirement that water spray is used on soil stockpiles, any non-paved construction areas, and the wheels of trucks where dust may disperse beyond the site; (e) Procedures for establishing when the covering of trucks will be required; (f) Procedures for determining when hard surfaced areas in construction yards and active construction areas should be cleaned including, but not limited to, the requirement that such areas be cleaned whenever dust generation occurs due to traffic on these surfaces; (g) Procedures for responding to discharges of odour (including in the event of excavation of contaminated sites) including, but not limited to, the requirement to

City Rail Link Notice of Requirement

Page 67


Condition Number

NoR Designati on Applies to

Condition

address discharge of objectionable odour by immediately ceasing the activity causing the discharge; (h) Procedures for equipment inspection (including timeframes for regular inspections), maintenance, monitoring and recording, including baghouses, pressure relief valves and high level alarms to mitigate dust emissions; (i) Procedures for, where practicable, limiting dust and odour nuisance and the methods for monitoring these procedures including Identification of contingency measures to address identified and verified adverse effects on sensitive receptors. Contingency measures may include options such as: (i) Cleaning of air filtration intakes; or (ii) Cleaning of other buildings and infrastructure; and (j) Procedures for responding to any complaints received and the timeframes for response to complaints and reporting; (k) Cross references to the specific sections in the Communication and Consultation Plan which detail how the communities in the vicinity of construction works are to be communicated with on the management of the adverse effects relating to air quality. Social Impact and Business Disruptions Property Management Strategy 60.1 The Requiring Authority will prepare a Property Management Strategy and shall submit the Strategy to Auckland Council within 3 months of the Designation being confirmed for confirmation that the Strategy has been prepared in accordance with this condition.

1 60

4 5 6

60.2 The purpose of the Strategy is to set out how the Requiring Authority will ensure the properties acquired for the City Rail Link are appropriately managed so they do not deteriorate and adversely affect adjoining properties and the surrounding area. The Strategy shall identify measures and methods to ensure the properties are managed in a manner that: (a) Does not significantly change the character, intensity and scale of the effects of the existing use of the land; (b) Maintains the condition of the property at that which existed at the time of purchase by the Requiring Authority; (c) Contributes to the functioning of the area within which the property is located; (d) Maintains occupancy as far as reasonably practicable; and (e) Provides confidence to occupants, adjoining property owners, and the community that the properties are managed responsibly pending construction. Social Impact and Business Disruption DWP

1 61

4 5 6

61.1 The Requiring Authority shall prepare a Social Impact and Business Disruption DWP. The objective of the Social Impact and Business Disruption DWP is to avoid, remedy or mitigate the adverse effects arising from disruption to businesses, residents and community services/facilities so far as reasonably practicable. 61.2 To achieve this objective the Requiring Authority shall engage a suitably qualified specialist(s) to prepare a Social Impact and Business Disruption DWP to address the following specific issues: (a) How disruption to access (including pedestrian, cycle, passenger transport and service/private vehicles) for residents, community services and businesses as a result of construction activities will, so far as is reasonably practicable, be avoided,

City Rail Link Notice of Requirement

Page 68


Condition Number

NoR Designati on Applies to

Condition

remedied or mitigated; (b) How the disruption effects that result or are likely to result in the loss of customers to businesses as a result of construction activities will, so far as is reasonably practicable, be avoided, remedied or mitigated; (c) How the loss and/or relocation of community facilities and the loss or change to catchments associated with these facilities as a result of the property acquisition process particularly to the Chinese Community Centre and Life Centre Church and the temporary loss of car parking at Hopetoun Alpha will be mitigated; and (d) How loss of amenity for residents, community services and businesses as a result of construction activities will be or has been mitigated through the CEMP and other DWPs. 61.3 The Social Impact and Business Disruption DWP shall be prepared in consultation with the community, community facility operators, business owners, affected parties and affected in proximity parties to: (a) Understand client and visitor behaviour and requirements and operational requirements of community facilities and businesses; (b) Identify the scale of disruption and adverse effects likely to result to businesses, residents and community services/facilities as a result of construction of the City Rail Link; (c) Assess access and servicing requirements and in particular any special needs of residents, community facilities and businesses; and (d) To develop methods to address matters outlined in (b) and (c) above, including: (i) The measures to maximise opportunities for pedestrian and service access to businesses, residents and social services/facilities that will be maintained during construction, within the practical requirements of the Transport, Access and Parking conditions (Conditions 25 to 30) and the Transport, Access and Parking DWP; (ii) The measures to mitigate potential severance and loss of business visibility issues by way-finding and supporting signage for pedestrian detours required during construction; (iii) The measures to promote a safe environment, taking a crime prevention through environmental design approach; (iv) Other measures to assist businesses and social services/facilities to maintain client/customer accessibility, including but not limited to client/customer information on temporary parking or parking options for access; (v) Other measures to assist residents, businesses and social services/facilities to provide for service delivery requirements; (vi) The process (if any) for re-establishment and promotion of normal business operation following construction; (vii) If appropriate and reasonable, requirements for temporary relocation during construction and/or assistance for relocation (including information to communities using these services and facilities to advise of relocations); and (viii) The measures to remedy and mitigate the disruption impacts to the community as a result of any closure and/or relocation of community services and facilities required by the Project. 61.4 The Social Impact and Business Disruption DWP shall include: (a) A summary of the findings and recommendations of the Social Impact Assessment

City Rail Link Notice of Requirement

Page 69


Condition Number

NoR Designati on Applies to

Condition

report (2013); (b) A record of the consultation undertaken with the community including specific access and operational requirements of individual businesses and residents including, if relevant, consultation on the necessity for, and the feasibility of, options and requirements for temporary relocation during construction and/or assistance for relocation); (c) An implementation plan of the methods to mitigate the disruption effects (as developed in 61.3 above); (d) Reference to any site/business specific mitigation plans that exist (though these may not be included in the DWP); (e) Cross reference to detail on how the CEMP and DWPs have responded to the issues of resident, business and social service/facility accessibility and amenity; (f) Details of on-going consultation with the local community through the Community Liaison Groups to provide updates and information relating to the timing for project works and acquisition; (g) Details of best endeavours steps undertaken with regard to acquisition and/or relocation of the Chinese Community Centre and Life Centre Church under the Public Works Act 1981; and (h) The process for resolution of any disputes or complaints in relation to the management / mitigation of social impacts (including business disruption impacts). 61.5 In relation to the site at 32 Normanby Road, the Requiring Authority shall consult with sub-lessees in the presence of the landowner and head lessee when developing site/business specific mitigation plans, unless the sub-lessee(s) request otherwise. 61.6 The Social Impact and Business Disruption DWP shall be implemented and complied with for the duration of the construction of the City Rail Link and for up to 12 months following the completion of the Project if required. 61.7 Suitably qualified independent specialists for the social impact and business disruption mitigation (whose appointment shall be agreed by the Council) shall peer review the Social Impact and Business Disruption DWP pursuant to Condition 11. 61.8 The Requiring Authority shall prepare an annual report on the identification, monitoring, evaluation and management of the effects outlined in the Social Impact and Business Disruption DWP together with a summary of matters raised by the community, and how these have been responded to. The report shall be presented to the Community Liaison Groups. Specific Design Requirements 62

2

62.1 The operational tunnel will avoid running under the building footprint of the property at 152 Vincent Street.

OPERATIONAL CONDITIONS Operational Rail Vibration 63.1 The Requiring Authority shall confirm that operational rail vibration and reradiated noise levels comply with the following Project Criteria at any noise or vibration sensitive receiver existing at the time of lodgement of the CRL NoR:

63

Building Type 1

Vibration Criteria

Reradiated Noise Criteria (dB LASmax re: 20 ÂľPa)

PPV (mm/s)

City Rail Link Notice of Requirement

Page 70


Condition Number

NoR Designati on Applies to

Condition

Commercial uses with primarily daytime use1

0.2

40

Residences and buildings where people normally sleep

0.15

35

Auditoria/Theatres1

0.1

30

TV/Recording Studios

0.06

25

Note: 1. 2.

Such as offices, businesses, churches, schools, universities and libraries. This includes Albert Street District Court.

63.2 For any noise or vibration sensitive building types that are not provided for in the table above, the upper limit for vibration and reradiated noise shall not exceed 0.3 mm/s PPV and 50 dB LASmax respectively. 63.3 For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations. 63.4 When assessing operational rail vibration and reradiated noise, compliance with Conditions 63.1 and 63.2 shall be achieved for at least 95% of any 20 consecutive train pass-by ‘events’. Operational Rail Vibration 63A.1 The Requiring Authority shall confirm that operational rail vibration and reradiated noise levels comply with the following Project Criteria at any noise or vibration sensitive receiver existing at the time of lodgement of the CRL NoR: Building Type

Vibration Criteria

Reradiated Noise Criteria (dB LASmax re: 20 µPa)

Velocityᵌ (mm/s)

2 4 63A

5 6

Commercial uses with primarily daytime use1

0.14

40

Residences and buildings where people normally sleep

0.1

35

Auditoria/Theatres1

0.1

30

0.045

25

TV/Recording Studios Note:

1. Such as offices, businesses, churches, schools, universities and libraries. 2. This includes Albert Street District Court. 3. Maximum one-second root-mean-square (RMS) value with an upper frequency limit of 80 Hz. 63A.2 For any noise or vibration sensitive building types that are not provided for in the table above, the upper limit for vibration and reradiated noise shall not exceed a RMS level (1s, maximum) of 0.21 mm/s and 50 dB LASmax respectively. 63A.3 For the avoidance of doubt the Project Criteria in Conditions 63A.1 and 63A.2 do not apply to the North Auckland Line and Britomart Designations. 63A.4 When assessing operational rail vibration and reradiated noise, compliance with

City Rail Link Notice of Requirement

Page 71


Condition Number

NoR Designati on Applies to

Condition

Conditions 63A.1 and 63A.2 shall be achieved for at least 95% of any 20 consecutive train pass-by ‘events’. The events shall be representative of the rolling stock fleet operating on the line and shall include maintenance activities, unless such maintenance activities are undertaken after 11.30pm or before 6.00am. 63A.5 Subject to Condition 66.4 in the case of MediaWorks, when assessing operational rail vibration measurement shall be made in accordance with Section 5.2.3 of BS6472-1:2008 Guide to evaluation of human exposure to vibration in buildings. Operational Noise – Mechanical Ventilation Plant 64.1 Operational noise from mechanical ventilation plant servicing the underground rail sections of the City Rail Link shall be measured and assessed in accordance with the following Project Criteria:

1

Location

Period

Auckland Central Area

7.00am to 11:00pm

65

11:00pm to 7:00am

60

7.00am to 10:00pm

60

10:00pm to 7:00am

55

2 64

dB LAeq

dB LAFmax 75

4 5 6

Auckland Isthmus Area

75

64.2 Measurements shall be undertaken in accordance with New Zealand Standard NZS 6801:2008 “Acoustics – Measurement of environmental sound” and assessed in accordance with New Zealand Standard NZS 6802:2008 “Acoustics - Environmental Noise”. 64.3 For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations. Operational Noise and Vibration Management Plan (ONVMP)

1 2 65

4 5 6

65.1 To manage the adverse effects from the maintenance and operation of the City Rail Link, the Requiring Authority shall, prior to the operation of the CRL, prepare an Operational Noise and Vibration Management Plan, (ONVMP) to the satisfaction of Auckland Council’s Compliance Monitoring Manager. The objective of the ONVMP shall be to ensure that the tracks, rolling stock and associated infrastructure (including ventilation and other mechanical plant) are maintained and operated in accordance with maintenance standards as outlined in the Requiring Authority’s maintenance programme for the City Rail Link, so that operational noise and vibration levels received at noise sensitive receiver locations, and vibration levels comply with Conditions 63 and 64. . 65.2 The ONVMP shall set out procedures for: (a) The maintenance of rolling stock to minimise noise and vibration emissions including, but not limited to, the management of wheel roughness and flats, braking systems, cooling systems, suspension systems and any other significant source associated with the operation of locomotives; (b) The maintenance of tracks to minimise noise and vibration emissions, including, but not limited to, the management of curve squeal, rail roughness, joint constructions and any other significant source associated with the use of the tracks;

City Rail Link Notice of Requirement

Page 72


Condition Number

NoR Designati on Applies to

Condition

(c) The implementation of mitigation measures associated with the operation and maintenance of the City Rail Link, for the operational life of the City Rail Link; (d) The management of noise from the operation of the line, including, but not limited to, the use of audible warning devices and acceleration / deceleration controls (where relevant); and (e) The management of noise and maintenance of noise-generating equipment from stations and associated ventilation and mechanical plant infrastructure including, but not limited to, PA systems, fans and ventilation noise and audible warning devices. 65.3 The ONVMP shall be adhered to at all times. It may be updated or amended at any time with the approval of Auckland Council’s Compliance Monitoring Manager. 65.4 For the avoidance of doubt this does not apply to the North Auckland Line and Britomart Designations. Operational Noise and Vibration Management – MediaWorks 66.1 At least six months prior to the opening of the CRL, the Requiring Authority shall provide a report from a suitably qualified noise and vibration expert to Auckland Council’s Compliance Monitoring Manager and to MediaWorks. The report shall confirm the trackform mitigation applied to the project has been designed to ensure that operational noise and vibration will not exceed the levels as set out in Conditions 63A.1, 63A.2 and 66.5. 66.2 The Requiring Authority shall implement continuous vibration monitoring on the tunnel structure on the East Link Down Main line within 20m of the closest point of the CRL tunnel to Studio 1 to determine compliance with Conditions 63A.1 and 63A.2 during the operation of the CRL (but only for so long as MediaWorks remains located at the MediaWorks site). The monitoring regime shall: (a) Be based on measurements with an upper frequency limit of 500 Hz; Note: The upper monitored frequency band of 500Hz reflects the supplier’s permissible criteria specified for equipment operated by MediaWorks. (b) Ensure that measurement equipment and signal chain complies with the manufacturers guidelines for accuracy and calibration; 66

6

(c) Capture every train pass-by on the line which may be triggered by vibration level radio frequency tag, interrupted beam or any other practicable triggering method; (d) Ensure the retention of the RMS data for every train pass-by on the line; (e) Ensure the transmission of RMS data for every train pass-by to the Requiring Authority at an interval not exceeding 48 hours between data uploads to enable records to be viewed and interrogated as required without requiring access to the monitoring location; (f) Ensure that the Requiring Authority, Auckland Council’s Compliance Monitoring Manager and MediaWorks are alerted to RMS values exceeding a value at the tunnel monitoring location that corresponds to 90% of the limits specified in Condition 63A.1 for TV/Recording Studios to enable the Requiring Authority to instigate preventative maintenance of tracks and rolling stock with the aim of avoiding exceedences of the noise and vibration limits at the MediaWorks building. The ONVMP required by Condition 65 shall set out the method for determining the transfer function between the tunnel monitoring location and the floor of Studio 1, and what the vibration trigger level is (based on measurements on the tunnel structure) for investigation and corrective action measures relative to Condition 66.2(f) above. The transfer function shall be accurately determined prior to the railway becoming

City Rail Link Notice of Requirement

Page 73


Condition Number

NoR Designati on Applies to

Condition

operational using the tunnel monitoring location and the floor of Studio 1. 66.3 Conditions 63A.1, 63A.2 and 66.5 shall be complied with at the MediaWorks building for so long as MediaWorks remains located at the MediaWorks site. 66.4 Noise shall be measured in accordance with the requirements of NZS6801:2008 Acoustics - Measurement of Environmental Sound. Vibration shall be measured in accordance with the requirements of section 5.2.3 of BS6472-1:2008 Guide to evaluation of human exposure to vibration in buildings, except that all references to people, persons and body in that clause shall apply to equipment as well. 66.5In addition to compliance with the criteria set out in Condition 63A.1 relating to TV/Recording Studios, and for the purpose of monitoring the effects of vibration on camera shake, the vibration arising from train pass-bys shall at all times comply with a vibration limit of 1m/s2 between 5Hz and 500Hz when measured on the floor of the MediaWorks filming studios. 66.6 In the event of any exceedance of any noise or vibration in Conditions 63A.1 and 63A.2 during a Sensitive Times (as defined in Condition 35.1) measures to reduce the noise or vibration below the relevant limit in Condition 63A shall be implemented as soon as reasonably practicable. ADVICE NOTES

1 AN1

4 5 6

1 2 AN2

4 5 6 1 2

AN3

4 5 6 1 2

AN4

4

The Requiring Authority will require an Authority under the Historic Places Act 1993 to destroy, damage or modify any archaeological site. This Authority is required in advance of earthworks commencing in the area where the archaeological site is located. It is expected that there will be staged Section 12 Authority applied for to cover the earthworks programme. In the event of unanticipated archaeological sites or koiwi being uncovered the Requiring Authority shall cease activity in the vicinity until it has the relevant approvals, and consulted with the Historic Places Trust and relevant iwi interests. The Requiring Authority will need to acquire the relevant property interests in land subject to the designation before it undertakes any works on that land pursuant to the designation. That may include a formal Public Works Act 1981 land acquisition process. It is acknowledged that property rights issues are separate from resource management effects issues and that the resolution of property issues may be subject to confidentiality agreements between the Requiring Authority and the relevant landowners. Prior to construction if Network Utility Operators are carrying out works that do not require prior written consent of the Requiring Authority in accordance with condition 6 of this designation, they must carry out those works in accordance with the Corridor Access Request (CAR) Process (as set out in Part 4 of the National Code of Practice for Utility Operators’ Access to Transport Corridors 2011) where that process applies to the works being carried out. Under section 176 of the RMA no person may do anything in relation to the land subject to the designation that would prevent or hinder the Rail Link without the written approval of the Requiring Authority.

5 6 AN5

1 2

Some of the land is subject to existing designations. Nothing in these designation conditions negates the need for the Requiring Authority to adhere to the provisions of section 177 of the RMA.

City Rail Link Notice of Requirement

Page 74


Condition Number

NoR Designati on Applies to

Condition

4 5 Some of the land is subject to existing designations. Nothing in these designation conditions negates the need for the Requiring Authority to adhere to the provisions of section 177 of the RMA.

AN6

6

AN7

1

Modifications to Britomart Transport Centre to connect the City Rail Link tracks into the rail network are separate to this designation and are covered under the Britomart Transport designation.

AN8

6

Works required to connect the City Rail Link to the North Auckland Rail Line occurring within the North Auckland Rail Line designation are separate to this designation and are covered under the North Auckland Line Rail designation.

For the avoidance of doubt, the Requiring Authority shall obtain the written consent of the Minister of Corrections in accordance with section 177 of the RMA for any work authorised by the City Rail Link designation on the Mt Eden Corrections Facility site at 1 Lauder Road.

City Rail Link Notice of Requirement

Page 75


Appendix One to Designation Conditions (NoR for Designations 1, 2, 4, 5 and 6) Condition 36 of this designation requires as part of the CEMP process the confirmation of where and when building condition surveys will be undertaken in relation to vibration and settlement. Note that those buildings classed in the “heritage� category are covered under the Appendix Two below. In accordance with condition 46, at a minimum building condition surveys shall be considered for the following buildings:. No

Address

Property Known As

1

8-12 Albert Street

Quay West Hotel

2

17 Albert Street

Cohesive Technology House

3

22-26 Albert Street

The Stamford

4

74 Albert Street

Chifley Suites

5

76-84 Albert Street

City Gardens Apartments

6

103,105,107 Albert Street

Manhattan Apartments

7

109-125 Albert Street

Sky City - Grand Hotel & Convention Centre

8

106-108 Albert Street

Elliot Tower (Proposed)

9

128 Albert Street

Crown Plaza

10

103 Vincent Street

YWCA Accommodation

11

109 Vincent Street

The Rodney Apartments

12

113 Vincent Street

Winsun Heights Apartments

13

135 Vincent Street

Dynasty Gardens Hotel

14

150 Vincent Street

The City Lodge

15

156 Vincent Street

Eclipse Apartments

16

71-87 Mayoral Drive

Rendezvous Grand Hotel

17

29,39,41 Pitt Street

Hopetoun Delta Apartments

18

22-28 Beresford Square

The Beresford

19

259-281 Karangahape Road

Retail and Residential building

20

14 East Street

Residential Building

21

9 A-C Mercury Lane

Residential Building

22

18 East Street

Residential Building

23

153 Newton Road

Beatnik

24

10 Flower Street

Eden Terrace Apartments

25

1 Akiraho Street

Eden Oaks

26

21 Queen Street

Zurich House (Anzo Tower)

27

7 Albert Street

Retail and Office building

28

9-11 Albert Street

Food Alley

29

23-29 Albert Street

ANZ Centre

30

12-26 Swanson Street

Affco House Carpark

31

58 Albert Street

APN NZ Complex

City Rail Link Notice of Requirement

Page 76


No

Address

Property Known As

32

63 Albert Street

AMI House

33

65-69 Albert Street

Auckland District Court

34

38 Wyndham Street

Wyndham Towers

35

92-96 Albert Street

Former Telecom Tower

36

85 Albert Street

Retail and Office building

37

87-89 Albert Street

Albert Plaza

38

99 Albert Street

AA Building

39

135 Albert Street

ASB Building

40

120 Albert Street

BDO Tower

41

44-52 Wellesley Street West

Wellesley Centre

42

67-101 Vincent Street

Auckland Police Station

43

22 Dundonald Street

Soundcraft Ltd

44

3 Flower Street

TV3 Building

45

32 Normanby Road

Commercial Building

46

3 Enfield Street

Horse and Trap

47

101 Mount Eden Road

Hometune

48

1 Ngahura Street

Auckland Boxing Association

49

1 Queen Street

HSBC House

50

125 Queen Street

New World Supermarket tenancy

51

148 Quay Street

Tenham Investments and Body Corporate 184960

52

29 Customs Street West

AMP Centre

53

15-19 East Street

54

32 Akiraho Street

55

83 Albert Street

56

4 Kingston Street

57

6-12 Kingston Street

Bear Park Early Childhood Centre

City Rail Link Notice of Requirement

Page 77


Appendix Two to Designation Conditions (NoR for Designations 1, 2, 4, 5 and 6) Condition 41 of this designation requires as part of the CEMP process the confirmation of where and when building condition surveys will be undertaken in relation to Built Heritage (including those affected as a result of excavation). In accordance with condition 46, at a minimum building condition surveys shall be considered for the following buildings: No

Address

Property Known As

1

12 – 32 Customs Street

Customs House

2

2 Queen Street

Endeans Building

3

12 Queen Street

4

3 Albert Street

West Plaza

5

13 Albert Street Auckland Central

Yates Building

6

15 Albert Street

Link House

7

35 Albert Street Auckland Central

Price Buchanan Building

8

37 – 39 Albert Street Auckland Central

9

41 Albert Street

10

46 Albert Street

11

49 Albert Street Auckland Central

12

53 Albert Street Auckland Central

13

55 Albert Street

14

57 Albert Street

15

61 Albert Street Auckland Central

Shakespeare Hotel and Brewery

16

76 to 78 Albert Street Auckland Central

Bluestone Wall + toilets under wall

17

83 to 85 Albert Street Auckland Central

18

102 Albert Street

19

26, 34 – 36 Wyndham Street

Former Gas Co Building

20

9 – 11 Durham Street

Bluestone Store

21

37-43 Victoria Street West

22

51-53 Victoria Street West

23

61-65 Victoria Street West

24

66 Victoria Street West

London Dairy

25

68 Victoria Street West

J H Hannan

26

24 Wellesley Street West

Bledisloe House

27

15-31 Wellesley Street West

Former CPO - Britomart Transport Centre

New Zealand Herald

Martha’s Corner

Archibald and Sons Warehouse/ T & G Building

City Rail Link Notice of Requirement

Page 78


No

Address

Property Known As

28

42 Wellesley Street

Griffiths Holdings Building

29

33 Wyndham Street

30

Aotea Square Aotea Centre (rear section)

31

11 Mayoral Drive

Former Public Trust

32

105 Vincent Street

Auckland Chinese Presbyterian Church

33

133 Vincent Street

Juliette’s

34

53 Pitt Street

Former Central Ambulance Station

35

59 Pitt

36

65 Pitt Street

37

70 – 74 Pitt Street

The Chatham

38

78 Pitt Street Pitt Street

Wesleyan Church

39

78 Pitt Street

Wesleyan Bicentennial Hall

40

1 Beresford Square Auckland Central

Former Pitt Street Fire Station

41

16 – 18 Beresford Square

42

211-235 Karangahape Road

43

238 Karangahape Road

George Court Building

44

1 Cross Street

George Court Factory Building

45

243 Karangahape Road

Naval and Family Hotel

46

246-254 Karangahape Road

Hallenstein Brothers Building

47

251 – 253 Karangahape Road

48

256 Karangahape Road

49

257 Karangahape Road

50

258-266 Karangahape Road

51

268 Karangahape Road

52

259-261 Karangahape Road

53

270 Karangahape Road

54

283 Karangahape Road

Samoa House

55

9 Mercury Lane

Mercury Theatre former Kings Theatre

56

151 Newton Rd

Retail/Recording Studio

57

206-208 Symonds Street

58

210 Symonds Street Retail

Pitt Street Buildings (O’Malley’s Corner)

Mercury Theatre entrance - Norman Ng Building

Cheapskates/Penny Farthing Bike Shop French Café

City Rail Link Notice of Requirement

Page 79


No

Address

Property Known As

59

215 Symonds Street

Edinburgh Castle Building

60

221 Symonds Street

61

224 Symonds Street

62

227 Symonds Street

63

231 Symonds Street Retail

64

233 Symonds Street

65

235 Symonds Street

66

237 Symonds Street

67

239-241 Symonds Street

68

243 Symonds Street

69

245 Symonds Street

70

249 Symonds Street

71

253 Symonds Street

72

1-13 Mt Eden Road

73

15-17 Mt Eden Road

74

21 New North Road

75

14 New North Road

Villa Dalmacija

76

St Patrick’s Square 43 Wyndham Street

St Patrick’s Cathedral

77

59 Alex Evans Street

St Benedict’s Church

78

1 – 9 St Benedicts Street

St Benedict's Presbytery

79

6 St Benedicts Street

Residential

80

43 Wyndham Street & Hobson Street

St Patrick’s Presbytery

81

Beresford Square

Forrester’s Hall

Former Post Office

City Rail Link Notice of Requirement

Page 80


Proposed Draft Notice of Requirement Requiring Authority Designation Conditions – NoR for Designation 3 Condition Number

NoR Design ation Applies to

Condition

1.1 The City Rail Link Project (City Rail Designation 3) shall be undertaken in general accordance with the following: (a) The information provided by the Requiring Authority in the Notice of Requirement dated 23 August 2012 and supporting documents being: (i) Assessment of Environmental Effects report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 15 August 2012 Rev B); (ii) Supporting environmental assessment reports (contained in Volume 3 of the Notice of Requirement suite of documents, dated August 2012); (iii) The Concept Design Report (contained in Volume 2 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3); (iv) Plan sets: (i) Land requirement plans (contained in Volume 1 of the Notice of Requirement suite of documents, dated 15 August 2012); 1

3

(ii) Plans contained in the Concept Design Report Appendices (contained in Volume 3 of the Notice of Requirement suite of documents, dated 13 August 2012 Rev 3). (b) Except as modified by the following alterations: (i) Assessment of Environmental Effects (Reference CRL-SYW-RME-000-RPT0065, Design and Construction Memorandum (Reference CRL-SYW-RME-000MEM-0002) and Drawings CRL-SYW-RME-000-DRG-0120 to 0124 and 0128 to 0132 ‘Strata / Sub-Strata Alteration (CRL Designation 2 and 3). (ii) Assessment of Environmental Effects (Reference CRL-MTE-RME- 000-RPT0060 Revision 7 dated 9/11/16), Design and Construction Memorandum (Reference CRL-MTE-RME-000-MEM-0001 dated 9/11/16) and Drawing CRLSYW-RME-000-DRG-0133 Revision 1 dated 26/7/17) (‘Mt Eden Station Alteration’ - CRL Designation 3 and 6). 1.2 Where there is inconsistency between the documents listed above and these conditions, these conditions shall prevail.

2

3

2.1 In accordance with section 184(1) of the Resource Management Act 1991 (the RMA), this designation shall lapse if not given effect to within 10 years from the date on which it is confirmed. 3.1 The Requiring Authority shall, as soon as reasonably practicable, but no later than at completion of detailed design:

3

3

(a) Review the area and volume of land of NoR Designation 3 required to protect the structural integrity of the two tunnels (including the relevant considerations at Condition 5.5); (b) Identify any areas of designated land that are no longer necessary to protect the structural integrity, safety or operation of the two tunnels; and (c) Then give notice in accordance with Section 182 of the RMA for the removal of those parts of the designation identified in (b) above.

City Rail Link Notice of Requirement

Page 81


Condition Number

NoR Design ation Applies to

Condition

4.1 Under s 176(1)(b) of the Resource Management Act 1991 (RMA) no person may do anything in relation to the designated land that would prevent or hinder the City Rail Link, without the prior written consent of the Requiring Authority. 4.2 In the periods pre, during and post construction of the City Rail Link, the following activities undertaken by Network Utility Operators will not prevent or hinder the City Rail Link, and can be undertaken without seeking the Requiring Authority’s written approval under section 176(1)(b) of the RMA: (a) Maintenance and urgent repair works of existing Network Utilities; 4

3

(b) Minor renewal works to existing Network Utilities necessary for the on-going provision or security of supply of Network Utility Operations; (c) Minor works such as new property service connections; (d) Upgrades to existing Network Utilities within the same or similar location with the same or similar effects on the City Rail Link designation. 4.3 For the avoidance of doubt, in this condition an “existing Network Utility� includes infrastructure operated by a Network Utility Operator which was: (a) In place at the time the notice of requirement for the City Rail Link was served on Auckland Council (23 August 2012); or (b) Undertaken in accordance with this condition or section 176(1)(b) RMA process. 5.1 This designation does not authorise any CRL works but restricts development from proceeding without the approval of the Requiring Authority where that development would result in an adverse effect on the CRL in terms of safety, operation or construction. 5.2 The Requiring Authority will work with developers in a collaborative manner and may require alterations or changes to development proposals for the purpose in 5.1. 5.3 The Requiring Authority may require alterations or changes to any proposal for development including but not limited to construction of basements and foundations where such works disturb the ground in a way that is likely to result in loading changes and result in deformations or produce other risks to the integrity of the CRL structures.

5

3

5.4 Reasons shall be given by the Requiring Authority for these changes to demonstrate they are reasonably necessary to provide for safety, construction or operation of the CRL, 5.5 Any proposal for physical works or activities within the designation shall be provided to the Requiring Authority and will be assessed on the following: (a) Building height, size, mass and proximity to the CRL structures; (b) Foundation and basement designs; (c) Geotechnical conditions; (d) Separation between the CRL structures and the proposed development; (e) Nature of the activities including methods and staging of construction; (f) The predicted loading change on the CRL structures resulting from the development; and (g) Any other relevant information necessary to determine the likelihood and extent of any adverse effect that may occur as a result of the proposed development.

City Rail Link Notice of Requirement

Page 82


Condition Number

NoR Design ation Applies to

Condition

These factors will also be relevant considerations in the drawback of the designation as provided for in Condition 3.1. 5.6 That assessment shall be peer reviewed by an independent certified engineer, paid for by the Requiring Authority, and the findings supplied to the landowner/ developer and the Auckland Council for information. Advice Notes relating to the Designation

AN 1

AN 2

3

This is a designation for protection purposes only. It protects the City Rail Link infrastructure to be constructed, operated and maintained in a separate designation located beneath this designation. The use of the land within this designation is subject to the agreement of the Requiring Authority to protect the subterranean works below. Any person proposing to undertake physical works within this designation is required to contact the Requiring Authority and obtain its approval in accordance with provisions set out in section 176(1)(b) of the Resource Management Act 1991.

3

If Network Utility Operators are carrying out works that do not require prior written consent of the Requiring Authority in accordance with condition 6 of this designation, they must carry out those works in accordance with the Corridor Access Request (CAR) Process (as set out in Part 4 of the National Code of Practice for Utility Operators’ Access to Transport Corridors 2011) where that process applies to the works being carried out.

City Rail Link Notice of Requirement

Page 83


Diagram 1

City Rail Link Notice of Requirement

Page 84


LEGEND

KEY PLAN

NOTE: MAP CONTAINS INFORMATION SOURCED FROM LINZ (CROWN COPYRIGHT RESERVED). THIS MAP CONTAINS DATA DERIVED IN PART OR WHOLLY FROM SOURCES OTHER THAN AURECON AND THEREFORE, NO REPRESENTATIONS OR WARRANTIES ARE MADE BY AURECON AS TO THE ACCURACY OR COMPLETENESS OF THIS INFORMATION.

CRL ALIGNMENT PROPOSED NAL ALIGNMENT EXISTING NAL ALIGNMENT CRL DESIGNATION

NOTICE OF REQUIREMENT FOR A DESIGNATION UNDER SECTION 181 (1) OF THE RESOURCE MANAGEMENT ACT 1991 TO BE SHOWN AS (CITY RAIL LINK). ALL PLANS SUBJECT TO FINAL SURVEY.

KIWIRAIL DESIGNATION LAND TO BE DESIGNATED SURFACE

NORM R ANBY

EXISTING CITY RAIL LINK DESIGNATION WORKS SUBJECT TO FUTURE OUTLINE PLAN

OAD

EXISTING NAL DESIGNATION

4

EN

RO AD

PARCEL ID (REFER TABLE 1 TO CRL-SYW-RME-000-DRG-0101 AND 0102)

1

ED

PARCEL BOUNDARIES

MT

CRL DESIGNATION

ENFIEL

D ST

9

LAUDER ROAD

8 AKIRAH O ST

6 5 3

BOSTON ROAD

7

WA TE

1

R

2

ST

AD

BOS TON

D

MT

E

ED

HR

OA

D

pw:\\designshare.au.aurecon.info:PW_PROD_AU\Documents\Projects\23xxxx\239933 - City Rail Link (CDE)\01-WIP\Drawings\CRL-SYW-RME-000-DRG-0101.dwg

AU

NU

BU

GE

RN

NT

ST

ST

SE

VE

RN

ST

ROA

O NR

CK ST

JOIN LINE TO DRAWING CRL-SYW-RME-000-DRG-0102

MT EDEN ROAD

BU

RL

EIG

O SHADD

U ST

Auckland

FLOWE

R ST

NIKA

H ROAD

10/11/2016 4:54:41 p.m.

NEW NORT

10

0

20

40m

CLIENT

SCALE 1:1000

REV DATE REVISION DETAILS 1.0 26.07.16 FINAL FOR LODGEMENT

APPROVED B.NEWNS

SCALE

AS SHOWN

SIZE

A1

DRAWN

PRELIMINARY

NOT FOR CONSTRUCTION APPROVED

L.RUSBATCH

.

DESIGNED

DATE

AUCKLAND CITY RAIL LINK

PROJECT

NOTICE OF REQUIREMENT LAND REQUIREMENT PLAN

TITLE

C.HOWARD CHECKED

B.NEWNS

D.MCGAHAN 0

ORIGINAL SIZE

20mm

40

60

80

100

200

300

400

500

DOCUMENT 600

PROJECT

CRL

ZONE

SYW

DISCIPLINE

RME

ELEMENT

000

700

TYPE

DRG

SHEET

0101

REVISION

1.0

800


LEGEND

KEY PLAN

NOTE: MAP CONTAINS INFORMATION SOURCED FROM LINZ (CROWN COPYRIGHT RESERVED). THIS MAP CONTAINS DATA DERIVED IN PART OR WHOLLY FROM SOURCES OTHER THAN AURECON AND THEREFORE, NO REPRESENTATIONS OR WARRANTIES ARE MADE BY AURECON AS TO THE ACCURACY OR COMPLETENESS OF THIS INFORMATION.

CRL ALIGNMENT PROPOSED NAL ALIGNMENT EXISTING NAL ALIGNMENT CRL DESIGNATION

NOTICE OF REQUIREMENT FOR A DESIGNATION UNDER SECTION 181 (1) OF THE RESOURCE MANAGEMENT ACT 1991 TO BE SHOWN AS (CITY RAIL LINK). ALL PLANS SUBJECT TO FINAL SURVEY.

KIWIRAIL DESIGNATION LAND TO BE DESIGNATED SURFACE

CRL DESIGNATION

EXISTING CITY RAIL LINK DESIGNATION WORKS SUBJECT TO FUTURE OUTLINE PLAN

PARCEL ID (REFER TABLE 1 TO CRL-SYW-RME-000-DRG-0101 AND 0102)

1

EN

RO A

D

JOIN LINE TO DRAWING CRL-SYW-RME-000-DRG-0101

EXISTING NAL DESIGNATION

MT

ED

PARCEL BOUNDARIES

9

ENFIE LD

ST

8

BRENTWOOD AVE

WYNY

HO

OAD

ST

BREN

TWOO

D AVE

pw:\\designshare.au.aurecon.info:PW_PROD_AU\Documents\Projects\23xxxx\239933 - City Rail Link (CDE)\01-WIP\Drawings\CRL-SYW-RME-000-DRG-0102.dwg

DO

MI

NIO

NR

OA

D

M

N DE TE

AKI RA

AD RO

ARD R

7

FENTON ST

10

PORTERS AC EP

LA CE

AVE

RA ST NGAHU

T RURU S

KORARI

NEW

TH NOR

D ROA

NEW NORTH ROAD

ST

FLOWER

Auckland

ST H ROAD

10/11/2016 4:54:44 p.m.

NEW NORT

10

0

20

40m

CLIENT

SCALE 1:1000

REV DATE REVISION DETAILS 1.0 26.07.16 FINAL FOR LODGEMENT

APPROVED B.NEWNS

SCALE

AS SHOWN

SIZE

A1

DRAWN

PRELIMINARY

NOT FOR CONSTRUCTION APPROVED

L.RUSBATCH

.

DESIGNED

DATE

AUCKLAND CITY RAIL LINK

PROJECT

NOTICE OF REQUIREMENT LAND REQUIREMENT PLAN

TITLE

C.HOWARD CHECKED

B.NEWNS

D.MCGAHAN 0

ORIGINAL SIZE

20mm

40

60

80

100

200

300

400

500

DOCUMENT 600

PROJECT

CRL

ZONE

SYW

DISCIPLINE

RME

ELEMENT

000

700

TYPE

DRG

SHEET

0102

REVISION

1.0

800




Outline Plan of Works

Appendix D:

Page 38

Construction Environmental Management Plan

| Normanby Road Early Works


Outline Plan of Works

Appendix E:

Page 39

Construction Staging Drawings

| Normanby Road Early Works


Tree Removal

Key

Existing Sewer. New Sewer. New Stormwater.

S

S

SW

Retaining Wall.

Alternative Carpark for 32 Normanby.

Work Area.

Tree Removal

Client :

Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

A00

For Information

P Young

10/10/19

P Young

Construction Staging Normanby Utilities Early Works

P Young

COMPANY NUMBER : 6267870

Creator ID : CRL-EFC-CON- LKA-DRG

Stage 1 CRL

EFC

CON

LKA

DRG

800001

A00


Key

Existing Sewer. New Sewer. New Stormwater.

S

S

SW

Retaining Wall.

Alternative Carpark for 32 Normanby.

Work Area.

Client :

Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

A00

For Information

P Young

10/10/19

P Young

Construction Staging Normanby Utilities Early Works

P Young

COMPANY NUMBER : 6267870

Creator ID : CRL-EFC-CON- LKA-DRG

Stage 1 CRL

EFC

CON

LKA

DRG

800002

A00


Key

Existing Sewer. New Sewer. New Stormwater.

S

S

SW

Retaining Wall.

Alternative Carpark for 32 Normanby.

Work Area.

Client :

Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

A00

For Information

P Young

10/10/19

P Young

Construction Staging

P Young

Stage 2

Normanby Utilities Early Works

COMPANY NUMBER : 6267870

Creator ID : CRL-EFC-CON- LKA-DRG

CRL

EFC

CON

LKA

DRG

800003

A00


Bridge Foundations April (Easter) 2020

Stage 3.1

Install Utilities on Bridge Span while on the ground.

Retaining Wall April, May 2020

Install Utilities on Bridge Columns.

Stage 3.2

Stage 4.1

Key

July 2020 Existing Sewer. New Sewer.

New Stormwater.

September 2020

S

S

SW

Retaining Wall.

Alternative Carpark for 32 Normanby.

Work Area.

Utilities.

Client :

Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

A00

For Information

P Young

10/10/19

P Young

Construction Staging Normanby Utilities Early Works

P Young

COMPANY NUMBER : 6267870

Creator ID : CRL-EFC-CON- LKA-DRG

Stage 3 & 4 CRL

EFC

CON

LKA

DRG

800004

A00


Outline Plan of Works

Appendix F:

Page 40

Design Drawings

| Normanby Road Early Works


Approximate extent of proposed gravity wall

Approximate Scale 1:400 @ A3

Gravity Wall BST-01 Plan - Sketch 2 For Outline Plan 11/12/2019


Approximate width 1.7m

Approximate width 1.0m

Ground level

Concrete block retaining wall

4000mm

3200mm (maximum)

No fines concrete fill

Approximate Scale 1:20 @ A3

Gravity Wall BST-01 Cross Section - Sketch 1 For Outline Plan 11/12/2019


Approximate extent of proposed L Wall

Approximate Scale 1:200 @ A3

L Wall - Office Max Plan - Sketch 2 For Outline Plan 11/12/2019


Future ground level (to allow for new Normanby Road grade separated bridge

1800mm (maximum)

Estimated 250mm

Approximately 2000mm

Estimated 250mm

Existing ground level

Reinforced Concrete L Wall

Approximate Scale 1:20 @ A3

L Wall - Office Max Cross Section - Sketch 1 For Outline Plan 11/12/2019


CRL WESTERN LINE - SINGLE LINE ENABLING WORKS NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE DRAWINGS INDEX

N

DRAWINGS TITLE LOCALITY PLAN AND DRAWING LIST 3D VIEW GENERAL NOTES - SHEET 1 OF 2 GENERAL NOTES - SHEET 2 OF 2 GENERAL ARRANGEMENT - SHEET 1 OF 3 GENERAL ARRANGEMENT - SHEET 2 OF 3 GENERAL ARRANGEMENT - SHEET 3 OF 3 PILE LAYOUT COLUMN DETAILS TRUSS DETAILS - SHEET 1 OF 3 TRUSS DETAILS - SHEET 2 OF 3 TRUSS DETAILS - SHEET 3 OF 3 STAIR DETAILS BALUSTRADE DETAILS SERVICES BRACKETS CONSTRUCTION STAGING

NEW ROAD LAYOUT (ROAD RAISED)

T ON BOS

D ROA

80 10 0

DRAWING No. CRL-NAL-STR-000-DRG-2001 CRL-NAL-STR-000-DRG-2002 CRL-NAL-STR-000-DRG-2011 CRL-NAL-STR-000-DRG-2012 CRL-NAL-STR-000-DRG-2021 CRL-NAL-STR-000-DRG-2022 CRL-NAL-STR-000-DRG-2023 CRL-NAL-STR-000-DRG-2031 CRL-NAL-STR-000-DRG-2041 CRL-NAL-STR-000-DRG-2051 CRL-NAL-STR-000-DRG-2052 CRL-NAL-STR-000-DRG-2053 CRL-NAL-STR-000-DRG-2061 CRL-NAL-STR-000-DRG-2072 CRL-NAL-STR-000-DRG-2081 CRL-NAL-STR-000-DRG-2091

0 12 10

10

0 10

NEW PERMANENT ROAD BRIDGE

0 14 10

TEMPORARY STRUCTURE LOCATION WN L DO NA

EA

0 16 10

I UP NA L UP NA IN MA

LIN

ISTI N EX MAI

KD

N OW

N MAI

NG

IN MA

G TIN IS EX

0 18 10

L UP NA

ST

IN MA

Filename: BIM 360://251926 - CRL Normanby Road Bridge/CRL_NAL_STR_000_MD3_WESTERN LINE.rvt

) NCE AD N ENTRA O R ER I SO LAUD DEN PR E (MT

0 20 10

BY MAN NOR ROA

0 22 10

32 NORMANBY ROAD

D

2 10

40

THESE DRAWINGS ARE FOR “BUILDING CONSENT / CONSTRUCTION” CONDITIONAL ON COORDINATION AND INCLUSION OF ALL BUILDING CONSENT CONDITIONS RELATING TO THIS PROJECT. THESE DRAWINGS CANNOT BE USED FOR OFF-SITE FABRICATION AND/OR ON-SITE CONSTRUCTION UNTIL A BUILDING CONSENT HAS BEEN GRANTED AND ANY CONDITIONS OF THE CONSENT INCORPORATED IN THE FOR CONSTRUCTION DOCUMENTATION SET. SHOULD THE CONTRACTOR PROCEED WITH OFF-SITE FABRICATION OR ON-SITE CONSTRUCTION PRIOR TO BUILDING CONSENT THEY DO SO AT THEIR OWN RISK AND JASMAX, AURECON, MOTT MC DONALD, WILL NOT BE HELD LIABLE.

LOCATION PLAN Plot Date: 19/07/01 4:06:48 PM

Office:

1 : 400 CONTRACTOR MUST VERIFY ALL DIMENSIONS ON SITE BEFORE COMMENCING ANY WORK. NO BUILDING WORK SHALL PROCEED UNTIL BUILDING CONSENT HAS BEEN GRANTED FOR THE WORK DESCRIBED. DO NOT SCALE OFF THIS DRAWING. FOR ALL STRUCTURAL STEELWORK REFER TO STRUCTURAL ENGINEER'S DRAWINGS FOR VERIFICATION OF MEMBER SIZES

ISSUED FOR OUTLINE PLAN ORIGINAL DRAWING IN COLOUR

CLIENT

REV DATE REVISION DETAILS A 02.07.19 ISSUED 30% PRELIMINARY DESIGN (STAGE A)

APPROVAL

SCALE

SIZE

NOT TO SCALE

A1

DRAWN

KIWIRAIL DOCUMENT No.

PRELIMINARY

NOT FOR CONSTRUCTION

CITY RAIL LINK

PROJECT

NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE LOCALITY PLAN AND DRAWING INDEX

APPROVED

S. MARUEN

DATE

DESIGNED

TITLE

S. KOTHANDARAMAN CHECKED

DOCUMENT

ORIGINAL SIZE 0

20mm

40

60

80

100

200

300

400

500

600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

NAL

STR

000

DRG

2001

A

700

800


TO BOS

LEGEND:

TON RO AD

EXISTING GROUND SURFACE CRL TRENCH AND ROAD PROPOSED GROUND SURFACE

SCAFFOLD STAIR No. 1

OHLE SAFTY SCREENS FRP DECKING

EAST MAIN SPAN TRUSS

TO MT

EDEN R OAD

SCAFFOLD STAIR No. 2 SERVICES MAIN SPAN COLUMN No. 1

Filename: BIM 360://251926 - CRL Normanby Road Bridge/CRL_NAL_STR_000_MD3_WESTERN LINE.rvt

EXISTING SURFACE

MAIN SPAN COLUMN No. 2

SCAFFOLD STAIR FOOTING

WEST

Plot Date: 19/07/01 4:07:44 PM

Office:

SCAFFOLD STAIR FOOTING

ISSUED FOR OUTLINE PLAN ORIGINAL DRAWING IN COLOUR

CLIENT

REV DATE REVISION DETAILS A 02.07.19 ISSUED 30% PRELIMINARY DESIGN (STAGE A)

APPROVAL

SCALE

SIZE

NOT SHOWN

A1

DRAWN

KIWIRAIL DOCUMENT No.

PRELIMINARY

NOT FOR CONSTRUCTION

CITY RAIL LINK

PROJECT

NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE 3D VIEW

APPROVED

S. MARUEN

DATE

DESIGNED

TITLE

S. KOTHANDARAMAN CHECKED

DOCUMENT

ORIGINAL SIZE 0

20mm

40

60

80

100

200

300

400

500

600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

NAL

STR

000

DRG

2002

A

700

800


CL NEW NAL UP MAIN (MC40)

30624

STAIR ENTRANCE FROM FOOTPATH

10160

1400

NORMANBY ROAD

CL EXISTING NAL UP MAIN (MC40)

NEW NORMANBY ROAD BRIDGE (BY C3 ALLIANCE)

BOSTON ROAD CARPARK S ES C C D E A ROA T A RN TON E T S AL BO TO

CL ABUTMENT B

847 CLEARANCE

EXISTING RETAINING WALL TO BE REMOVED

WN MAIN NAL DO

P MAIN NAL U

162 CLEARANCE

STAIR ENTRANCE FROM FOOTPATH

CL CRL WALL 6A

IDGE Y ROAD BR NORMANB ALL US PILE W CONTIGUO

1400

CL NEW NAL DOWN MAIN (MC10)

ALL US PILE W CONTIGUO ES) N (3 No. PIL EXTENSIO

CL ABUTMENT A

32 NORMANBY ROAD

P MAIN NAL U

ING EXIST

N EXISTING TRANSFORMER TO BE RELOCATED

ING EXIST IN A M NAI UP

TRENCH HEADSTOCK TYP

MAIN OWN D K LIN EAST

CL CRL WALL 3

CL NEW EAST LINK DOWN MAIN (MC50)

ACCESS TO BE PROVIDED THROUGH EXISTING CARPARK TO BOSTON ROAD WHEN RETAINING WALL IS BUILT

CL EXISTING NAL DOWN MAIN (MC10)

PLAN 1 : 100

CL ABUTMENT A & CRL WALL 3

CL ABUTMENT B & CRL WALL 6A

30624 25520

2552

2552 TYP

MAIN SPAN TRUSS

RL 81.274 m

CL EXISTING NAL UP MAIN (MC40)

Filename: BIM 360://251926 - CRL Normanby Road Bridge/CRL_NAL_STR_000_MD3_WESTERN LINE.rvt

8000

5445

RL 69.824 m

1000

NEW RETAINING WALL (NORMANBY ROAD RIASED) TO BE INSTALLED AFTER TEMPORARY BRIDGE DEMOLITION

V*

NAL 010/10

MAIN SPAN COLUMN No. 1

NOTES:

CL NEW NAL DOWN MAIN (MC10)

3813

RL 69.950 m

8500

CL EXISTING NAL DOWN MAIN (MC10)

CL NEW EAST LINK DOWN MAIN (MC50) RL 69.841 m

1. FOR GENERAL NOTES REFER TO DRAWINGS CRL-NAL-STR-000-DRG-2011 AND 2012. 2. TEMPORARY BRIDGE COLUMN TO TRENCH HEADSTOCK DESIGNED AS A PINNED CONNECTION. THE C3 ALLIANCE IS TO DESIGN THE CRL TRENCH (HEADSTOCK AND PILES) FOR THE FOLLOWING ULS LOADS: N* = 360 kN VL* = 60 kN VT* = 5 kN 3. THE FOLLOWING ARE THE THRUST FORCES RESULTING FROM HIGH PRESSURE UTILITIES ONTO THE BRIDGE: N* = TBC V* = TBC 4. THE BRIDGE IS TO HAVE THE FOLLOWING CONNECTION CONDITIONS: F = FIXED CONNECTION R = RELEASED CONNECTION (PINNED) 5. THE FOLLOWING DEFLECTIONS HAVE BEEN CALCULATED. UTILITIES ON THE BRIDGE ARE REQUIRED TO ACCOMODATE THESE MOVEMENTS: 5.1 VERTICAL DEFLECTION: MID-SPAN DEFLECTIONS: SELF WEIGHT = 10mm SELF WEIGHT + LIVE LOAD = 18mm 5.2 LATERAL DEFLECTIONS: A. TRANSVERSE DEFLECTION (MID-SPAN): SELF WEIGHT + WIND (SLS) = 14mm SELF WEIGHT + SEISMIC (SLS) = 3mm B. LONGITUDINAL DEFLECTION (TOP OF COLUMN): SELF WEIGHT + SEISMIC (SLS) = 26mm C. LONGITUDINAL DEFLECTION (TOP OF HEADSTOCK): CRL TRENCH DEFLECTION = 50mm

EXISTING GROUND LEVEL

RL 70.120 m

CL NEW NAL UP MAIN (MC40)

RL 65.824 m

RL 65.250 m

8500 1400 WIDE x 900 DEEP HEADSTOCK (BY C3 ALLIANCE) 1200 DIA. CONTIGUOUS PILED WALL (BY C3 ALLIANCE)

RL 64.270 m SERVICES OVER TEMPORARY BRIDGE

Plot Date: 7/3/2019 10:06:47 AM

Office:

UTILITY CHORUS VECTOR ELECTRICITY VECTOR ELECTRICITY VECTOR FIBRE OPTIC VECTOR GAS WATER WATER

DETAILS 10 X 75mm DIA DUCTS WITH FIBRE OPTIC CABLE 1 X 400 V IN 1 X 100 DUCT 2 X 11 kV IN 2 X 150mm DUCTS 11 X 75mm DIA DUCTS 1 X 100mm IP20 HP GASMAIN 1 X 150mm DIA CLS 1 X 550mm DIA CLS

MIN.RADIUS (mm) 400 2000 2000 1000 400 370 580

ELEVATION

ISSUED FOR OUTLINE PLAN

1 : 100 (NEW PERMANENT BRIDGE NOT SHOWN FOR CLARITY)

ORIGINAL DRAWING IN COLOUR

CLIENT

REV DATE REVISION DETAILS A 02.07.19 ISSUED 30% PRELIMINARY DESIGN (STAGE A)

APPROVAL

KIWIRAIL DOCUMENT No. SCALE

SIZE

NOT SHOWN

A1

DRAWN

PRELIMINARY

NOT FOR CONSTRUCTION

CITY RAIL LINK

PROJECT

NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE GENERAL ARRANGEMENT - SHEET 1 OF 3

APPROVED

S. MARUEN

DATE

DESIGNED

TITLE

S. KOTHANDARAMAN CHECKED

PROJECT

DOCUMENT ORIGINAL SIZE 0

20mm

40

60

80

100

200

300

NEW RETAINING WALL (NORMANBY ROAD RIASED)

N*

1000

1800

NAL 010/09

COMPACTED GAP65 HARDFILL (SCAFFOLD STAIR FOUNDATION)

SCAFFOLD STAIR No. 2

1% FALL

V*

SERVICES DIVERTED ONTO TEMPORARY BRIDGE

PANTOGRAPH ZONE

OHLE SAFETY SCREEN

CONDUCTOR FALL ZONE

N*

SCAFFOLD STAIR No. 1

LEGEND:

2552

400

500

600

CRL

ZONE

NAL

DISCIPLINE

STR

ELEMENT

000

700

TYPE

DRG

SHEET

REVISION

2021

A 800


N TO MT EDEN ROAD

TO BOSTON ROAD CL CRL WALL 6A

CL CRL WALL 3

30624

510

25520

2552

CL ABUTMENT A

30

CL ABUTMENT B

30

2437

EQ

150x9 SHS TYP

9 No. AT C/C = 450

EQ

2552

EARTH CONNECTION PLATE DETAILS 1:5

SCAFFOLD STAIR No. 1

SCAFFOLD STAIR No. 2

EARTH CONCENTRATION PLATE LOCATION

EARTH CONCENTRATION PLATE LOCATION

PLAN 1 : 100

CL CHORD

(NEAR FACE SHOWN, FAR FACE SIMILAR) 15kN (1500KG) ANCHOR POINT FOR EMERGENCY UTILITIES MAINTENANCE ACCESS

2

CL CHORD

2437 150x9 SHS TYP

200x9 SHS TYP TOP CHORD

LUXTELLA S72XPL-106 LIGHTING

1 2022

200x9 SHS TYP SCAFFOLD STAIR No. 2

SCAFFOLD STAIR No. 1

150x9 SHS TYP

800 1000 GRADE C-D HEAVY DUTY SAFETY PLYWOOD H3.2 TREATED PLASTIC MESH (380 GSM U.V. STABILIZED HDPE

2023

TYPICAL HANDRAIL 48.3 ODx5.4 WT (HDG300)

1800

50 uPVC DUCT

2200

2000 PEDESTRIAN PATH

A

150x9 SHS TYP

2023

MAIN SPAN COLUMN No. 1

50mm THICK FRP PANEL

3350

MAIN SPAN COLUMN No. 2

EARTH CONCENTRATION PLATE LOCATION

3 No. 180 UB 18.1

900

574

570

2x150mm & 1x100m VECTOR ELECTRICITY

EARTH CONCENTRATION PLATE LOCATION

570

574

LEVEL (NO GRADE)

Filename: BIM 360://251926 - CRL Normanby Road Bridge/CRL_NAL_STR_000_MD3_WESTERN LINE.rvt

1x150mm LIGHTING AND CCTV DUCT 1x100 VECTOR GAS MAIN

200 UB 29.8

200x9 SHS TYP BOTTOM CHORD

1400 WIDE x 900 DEEP HEAD STOCK (BY C3 ALLIANCE) 1200 DIA. CONTIGUOUS PILED WALL (BY C3 ALLIANCE)

1x150mm VECTOR FIBRE OPTIC DUCTS

ELEVATION

CRADLE

1x550mm & 1x150mm WATER

150x9 SHS TYP

1 : 100

SECTION

(NEAR FACE SHOWN, FAR FACE SIMILAR)

1 : 20

1

10x80mm CHORUS DUCTS WITH FIBRE AND COPPER

TYPICAL SECTION

2022

NOTES: 1. FOR GENERAL NOTES REFER TO DRAWINGS CRL-NAL-STR-000-DRG-2011 AND 2012.

Office:

EARTHING AND BONDING:

Plot Date: 19/07/01 4:08:48 PM

1. EARTH CONNECTION PLATES ARE TO BE WELDED TO THE MAIN SPAN TRUSS. 2. ALL STRUCTURAL BOLTED JOINTS ARE NOT TO BE PAINTED IN ORDER TO ENSURE ELECTRICAL CONTINUITY FOR THE ENTIRE STRUCTURE.

ISSUED FOR OUTLINE PLAN ORIGINAL DRAWING IN COLOUR

CLIENT

REV DATE REVISION DETAILS A 02.07.19 ISSUED 30% PRELIMINARY DESIGN (STAGE A)

APPROVAL

SCALE

SIZE

NOT SHOWN

A1

DRAWN

KIWIRAIL DOCUMENT No.

PRELIMINARY

NOT FOR CONSTRUCTION

CITY RAIL LINK

PROJECT

NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE GENERAL ARRANGEMENT - SHEET 2 OF 3

APPROVED

S. MARUEN

DATE

DESIGNED

TITLE

S. KOTHANDARAMAN CHECKED

DOCUMENT

ORIGINAL SIZE 0

20mm

40

60

80

100

200

300

400

500

600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

NAL

STR

000

DRG

2022

A

700

800


2437 CL BRIDGE

CL COLUMN

CL COLUMN

30624 EQ

EQ

EQ

EQ

EQ

EQ

EQ

EQ

EQ

EQ

EQ

15 mm CAMBER

1800

3350

EQ

PRE-CAMBER DIAGRAM 1 : 200

RL TOP OF COLUMN CL COLUMN

400SHS12.5

12mm THK PLATE VANDAL BARRIER AT EACH END OF SERVICE BRIDGE

400SHS12.5 COLUMN HDG HOLD DOWN BOLTS, NUT AND LOCKNUT

150x9 SHS SET-OUT POINT

200UB22

HEADSTOCK (BY C3 ALLIANCE)

100

12mm THK PLATE UTILITY PROTECTION BARRIER AT EACH END OF TEMPORARY BRIDGE

BASE PLATE-SLIDING JOINT DETAIL TO BE CONFIRMED

LEVELING NUT 40mm NON-SHRINK GROUT

600

200x9 SHS

900

400x12.5 SHS

7669

20mm THICK ANCHOR PLATE

UTILITY PROTECTION BARRIER

Filename: BIM 360://251926 - CRL Normanby Road Bridge/CRL_NAL_STR_000_MD3_WESTERN LINE.rvt

1 : 25

CONTIGUOUS PILE WALL (BY C3 ALLIANCE)

1200

B CL TRANSOM

2023

HEADSTOCK (BY C3 ALLIANCE) RL TOP OF HEADSTOCK

150x9 SHS

DETAIL

200x9 SHS (BOTTOM CHORD)

1 : 10

B 2023

2237

Plot Date: 19/07/01 4:08:59 PM

Office:

CONTIGUOUS PILED WALL (BY C3 ALLIANCE)

DETAIL 1 : 10

CONTRACTOR MUST VERIFY ALL DIMENSIONS ON SITE BEFORE COMMENCING ANY WORK. NO BUILDING WORK SHALL PROCEED UNTIL BUILDING CONSENT HAS BEEN GRANTED FOR THE WORK DESCRIBED. DO NOT SCALE OFF THIS DRAWING. FOR ALL STRUCTURAL STEELWORK REFER TO STRUCTURAL ENGINEER'S DRAWINGS FOR VERIFICATION OF MEMBER SIZES

SECTION

2

1 : 25

ORIGINAL DRAWING IN COLOUR

NOTES: 1. FOR GENERAL NOTES REFER TO DRAWINGS CRL-NAL-STR-000-DRG-2011 AND 2012.

TYPICAL MAIN SPAN COLUMN

ISSUED FOR OUTLINE PLAN

2022

CLIENT

A 2022

REV DATE REVISION DETAILS A 02.07.19 ISSUED 30% PRELIMINARY DESIGN (STAGE A)

APPROVAL

SCALE

SIZE

As NOT AS indicated SHOWN SHOWN

A1

DRAWN 0

1

2

3

4

DATE

DESIGNED

SCALE 1:100 AT A1 SCALE 1:200 AT A3

20mm

40

60

80

100

NORMANBY ROAD TEMPORARY SERVICES AND PEDESTRIAN BRIDGE GENERAL ARRANGEMENT - SHEET 3 OF 3

TITLE

S. KOTHANDARAMAN CHECKED

DOCUMENT

ORIGINAL SIZE 0

CITY RAIL LINK

PROJECT

APPROVED

S. MARUEN

5m

PRELIMINARY

NOT FOR CONSTRUCTION

KIWIRAIL DOCUMENT No.

200

300

400

500

600

PROJECT

ZONE

DISCIPLINE

ELEMENT

TYPE

SHEET

REVISION

CRL

NAL

STR

000

DRG

2023

A

700

800


NORMANBY R

14 7

6

8

N

141.00 0 ARC

R.

72.014

141.0 00

EX NB SW13/4

R.

NB SW 01/1

3 5

2

1

10

11

9

13

R. 302.000 ARC 23.221

ISO A1 594mm x 841mm

4

12

ARC 89.39 7

0 70.

Ø900

LEGEND NB SW 08/4

DESIGNATION BOUNDARY KIWIRAIL BOUNDARY CRL TRACK ALIGNMENT STAGE 1A/1B

X

CRL TRACK ALIGNMENT FUTURE

X

Ø600

PROPOSED GRATED CESS DRAIN

X

Ø900

NB SW 02/1

PROPOSED KERB & CHANNEL

>>

PROPOSED CATCH DRAIN (ØV600x50)

X

PROPOSED CESS DRAIN (Ø500x300) PROPOSED CONCRETE CHANNEL

X

PROPOSED STORMWATER PIPE

X

NB SW 03/1

EXISTING STORMWATER PIPE X

X

ABANDONED STORMWATER PIPE

X

00 Ø3

NB SW 04/1

X X

Ø300

PROPOSED EXTENSION OF CUT AND COVER (BOX STRUCTURE)

NB SW 05/1

X

00 Ø6

CUT AND COVER

NB SW 08X/3 X

PROPOSED RAIN GARDEN

X

X

PROPOSED STORMWATER MANHOLE

0 60 Ø

X

EX NB SW13/3 EX NB SW13/1

X

XX

Ø90 0

PROPOSED SCRUFFY DOME PROPOSED STORMWATER SUPERPIT PROPOSED STORMWATER SUMP

X

LAUD

EXISTING STORMWATER PIPE

00 Ø3

Ø300

EX NB SW13/2

X

Ø600

ER RD

PROPOSED STORMWATER MEGAPIT

7

0 0.

NB SW 08/2

PROPOSED STORMWATER CATCHPIT

X

NB SW 06/1

Ø300

X

IL 2.61 DTR RL68.9

65.0 65.0

62.5

63.0 63.0

>>

>>

>>

>>

>>

>>

>>

>>

>>

>>

>>

>>

>>

>>

50

60

70

80

90

100mm

SCALE

SIZE

AS SHOWN

A1

DESIGNED REVISIONS

40

66.5

66.0

65.5

Ø1 35 0

65.0

TRS.L 20.000

30

62.0 62.0

0+698

>>

>>

>>

65.0

64.0

Ø300

>>

>>

>>

>>

>>

>> 64.5

63.5

Ø525

>>

SHEET 003

0 95 Ø1

>>

NORMANBY ROAD EARLY WORKS

/1 08 SW

CREATOR ID : CRL_NAL_320_00_LKA_DRG_100003

COMPANY NUMBER : 6267870 20

Ø1 950

Ø1950

Ø2200 x2240

>> TK SW 09/1

Ø375

FT

70.0 70.0 70.0 69.0 69.5 68.0 69.0 67.0 68.5 66.0 68.0 65.0 67.5 67.0 66.5 66.0 65.5 65.0 64.0 64.5 64.0

>>

65.0

64.0 64.0 64.5

>>

65.5

Ø300

Ø1 200

>>

65.5

65.0 65.5 66.0 65.0 68.0 67.5 67.0 66.5 69.5 69.0 68.5 67.0 68.0 69.0

65.0

Ø1950

Ø375

TK SW 11/3

TK SW 11/4

STAGE-A APPROVED

TK SW 11/2

ISSUED FOR OUTLINE PLAN

DRAWN A00 LINK ALLIANCE REVIEW DESCRIPTION

TITLE:

2019-11-22

R. CRUZ

AB

2019-11-07

CHECKED

DATE

APPROVED

DATE

A. WALKER

2019-09-17

This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.

NORTH AUCKLAND LINE

ZONE:

A. BURFORD

AB

CITY RAIL LINK

PROJECT:

D. DUMITRASCU A01 ISSUED FOR STAGE A

PROPOSED CLEANING POINT

0 95 75Ø1 Ø3

>>

Ø375

Ø525

TK SW 05/1

TK SW 09/2

0+598

71

END)

Ø525

TK SW 04/1

REV

10

Ø375

R

BARRIE

LANE

FOOTPA TH

CYCLE

E

R

E LAN

SHOU LDE

VEHICL

MEDIA N (TAPER ING

Ø525

FROM NORTH

TION)

Ø300

TK SW 10/1

Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

CLIENT:

0

TK SW 12/1

TK SW 10/2

Ø525

EXISTING SOAKHOLE PROPOSED C3 LAYOUT

Ø525 ERSEC

JOINS

VEHICL (WIDE E LANE NING TOWA RDS INT

1:500

A3

LANE

m

A1

1:250

25

LDER

12.5

TK SW 09/3

TK SW 03/1 NB SW 31/15

SHOU

0

TH

12.5 m

CYCLE

Ø225

10+140

6.25

R

Ø1950

10+120

0

TK SW 08/1

TK SW 01/1

Ø225

FOOTPA

TK SW 01/2

TK SW 08/2

SUBJECT TO ANOTHER PACKAGE SWMH

Ø150

NB SW 12/2

TK SW 08/3

BARRIE

Ø225

NB SW 10/1

NB SW 11/1 TK SW 07/1 Ø300

Ø300

10+180

TK SW 02/1

10+160

10+140

10+120

10+080

TK SW 06/1

X

ABANDONED STORMWATER CATCHPIT Ø300

10+240

X

ABANDONED STORMWATER MANHOLE

10+220

Ø4 50

Ø30 0

EXISTING STORMWATER CATCHPIT

UPGRADE 32 NORMANBY RD CONNECTION

NB SW 12/1

NB SW X 08/1

EXISTING STORMWATER MANHOLE

66.0

X

PROPOSED CONTOURS AT 0.05m INTERVALS

61.5

NORM ANBY

Ø1 200

X

TOP OF RAIL

PROVIDE RUNOFF TREATMENT AND STORAGE

65.5

RD

X

X X X

X

XX .0

X

X

X

MH WITH STORMFILTER 360

INVERT LEVELS EXISTING CONTOURS AT 1m INTERVALS EXISTING CONTOURS AT 0.2m INTERVALS PROPOSED CONTOURS AT 0.25m INTERVALS

CONNECT 32 NORMANBY RD INTO NEW DRAINAGE SYSTEM

50 Ø4

Ø3 00

NB SW 07/1

Ø600

X

NB SW 09/1

10+080

Last saved by: EBEN.DUPREEZ(2019-11-28) Last Plotted: 2019-12-03 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\ZZ C57 TOC Development\C5D C5 Works TOC Development\900 CAD-GIS\01_WIP\20-SHEET\320 Drainage\CRL-NAL-DRN-LKA-DRG-100003.dwg

X

PROPOSED RETAINING WALL (RAIL CORRIDOR)

NORMANBY ROAD LAYOUT PLAN SHEET 2 OF 2 PROJECT

DOCUMENT:

ZONE

DISCIPLINE

ORGANISTION

TYPE

SHEET

CRL - NAL - DRN - LKA - DRG - 100003

REVISION

A01


ARC 7 89.39

150mmØ PVC

ISO A1 594mm x 841mm

150 E W

WW NORMAN BY RDWW

72.014

00 141.0

10+240

10+220

DESIGNATION BOUNDARY

JOINS

10+200

LEGEND

10+180

CRL-NAL-UTI-C5-DRG-121002

5

WW36 - DIVERT AS SHOWN AND REMOVE REDUNDANT SECTION

KIWIRAIL BOUNDARY CRL TRACK ALIGNMENT FUTURE EXISTING KERB LINES (GIS) EXISTING BOUNDARY LINES PROPOSED WASTEWATER PIPE LINE

10+160

WW26 & WW37 - DIVERT AND REMOVE REDUNDANT SECTION

PROPOSED WASTEWATER MANHOLE

10+140

532612

150MM Ø

PROPOSED FLOW DIRECTION

15 0

MM Ø

1I N

450 E W

10+120

10+100

EXISTING WASTEWATER EXISTING SERVICE CONNECTION LINES

56

.3

EXISTING FLOW DIRECTION EXISTING WASTEWATER MANHOLE PROPOSED RETAINING WALL PROPOSED RETAINING WALL / WALL NIB

RETAINING WALL (DESIGNED BY OTHERS)

PROPOSED KERB & CHANNEL REMOVE / ABANDON PROTECT

150Ø EARTHENWARE PERMANENTLY REMOVE

PIPE DIAMETER AND MATERIAL

150 CI

WW27 & WW34 - DIVERT PROPOSED ALIGNMENT AS SHOWN

EW W 1 W 50

WW

WW

WW

WW

WW

WW

WW

WW

WW

W W

WW

S

WW

W W

WW31 - RAISE MANHOLES TO FINISHED LEVEL

30

68.41

504955

68.32

504956

68.36

504952

68.53

504951

68.56

532610

68.06

PV C

W

EXISTING MANHOLE IL TO BE LIFTED TO RL 68.70

1660732

1661953

PE

1.

1664081

15

WSL AND LINK ALLIANCE TO CONFIRM WHETHER CONVENTIONAL GRAVITY DESIGN OR PUMP STATION OPTION TO BE PURSUED.

RELAY PIPE LINE

532611 RISING MAIN

JOINS

0 E WW W

225

532610

15

375 P E

450 CI

NOTE

CRL-NAL-UTI-C5-DRG-121006

1660726

EW

532614

NU

EW

THE LOCATION OF SERVICES SHOWN ON THESE DRAWINGS ARE APPROXIMATE ONLY AND ARE BASED ON GIS INFORMATION PROVIDED BY THE RELEVANT SERVICE PROVIDERS. NO LIABILITY IS ACCEPTED FOR THE COMPLETENESS OR ACCURACY OF PLOTTED SERVICES.

PUMP STATION

ISSUED FOR OUTLINE PLAN

A3 Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document. READY TO ISSUE

A1

SELF CHECK DIGITAL DESIGN MANAGER

A3

10

20

30

40

50

60

CREATOR ID : CRL_NAL_810_00_LKA_DRG_121003 70

80

90

100mm

ALLIANCE REVIEW VERIFICATION

INITIAL

DATE

SCALE

SIZE

AS SHOWN

A1

DESIGNED REVISIONS

DELIVERY STAGE

COMPANY NUMBER : 6267870

70.56

NOTE

CRL-NAL-UTI-C5-DRG-121005

GE

225

NT

JOINS

1:500

CLIENT:

532614

150Ø

150Ø

25 m

A1

1:250

70.74

NORMANBY ROAD EARLY WORKS

2665775 12.5

2665775 1661487

EW

ST

1661487

0

67.27

WW27 & WW34 - PROTECT

0

12.5 m

68.81

532612

PUMP STATION

15

6.25

532611

RISING MAIN

WW31 - PROTECT

0

68.25

1660726

W

C6 SHAFT (BY OTHERS)

68.18

1660732

S

WW

S

MH 40/3 - MH 50/4 PW39 REALIGNMENT

INVERT LEVEL

S

WW

C

WW27 & WW34 - DIVERT ID NO. AND REMOVE 1661953

W W

WW S

RELAY PIPE LINE

300Ø PV

C

MH40/5B

W W

WW

C 300Ø PV

W W

504955

WW

300Ø PV

WW

WW26 & WW37 - PROTECT

MH40/7

WW

EXMH50/4 504956

MH40/6

EXISTING WW MANHOLES

MH40/5A WW

150 EW

225

Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_AU_w\60560778\CRL-NAL-UTI-LKA-DRG-121003.DWG Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\ZZ C57 TOC Development\C5D C5 Works TOC Development\900 CAD-GIS\01_WIP\20-SHEET\800 Utilities\CRL-NAL-UTI-LKA-DRG-121003.dwg

6

WW MHD/1

NEW INCOMING CONNECTION FROM MOUNT EDEN PRISON

0

3

0 ARC

504952

WW

2

1

R.

150Ø

CRL-NAL-UTI-C5-DRG-121004

JOINS

N

4

141.00

LAUDER RD

KEY PLAN

R.

504951

N

WW33 - PROTECT

STAGE-A APPROVED

DRAWN

FOR EXTERNAL REVIEW

A00 LINK ALLIANCE REVIEW REV

DESCRIPTION

TITLE:

AB

2019-11-22

AB

2019-11-07

CHECKED

DATE

APPROVED

DATE

A. WALKER

2019-09-17

R. CRUZ

This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.

NORTH AUCKLAND LINE

ZONE:

J. WORSLEY

A01

CITY RAIL LINK

PROJECT:

WASTEWATER WORKS LAYOUT PLAN SHEET 3 OF 5 PROJECT

DOCUMENT:

ZONE

CRL - NAL -

DISCIPLINE

ORGANISTION

TYPE

SHEET

UTI - LKA - DRG - 121003

REVISION

A01 A00


150 EW

N

4 2

1

3

6

5 R.

ISO A1 594mm x 841mm

N

KEY PLAN

141.00 0 ARC

R.

72.014

00 141.0

ARC 7 89.39

532577

LEGEND DESIGNATION BOUNDARY 225 Ø PVC

MHD/3

EXISTING BOUNDARY LINES PROPOSED WASTEWATER PIPE LINE PROPOSED WASTEWATER MANHOLE PROPOSED FLOW DIRECTION

532578

22

EXISTING WASTEWATER

5E

EXISTING SERVICE CONNECTION LINES

W

EXISTING FLOW DIRECTION

532580

EXISTING WASTEWATER MANHOLE

WW

PROPOSED RETAINING WALL PROPOSED RETAINING WALL / WALL NIB PROPOSED KERB & CHANNEL

WW

PROTECT

Ø PVC WW

150mm

PIPE DIAMETER AND MATERIAL

150 CI

532581

MH D/1 - MH D/4 WW ALIGNMENT

WW

WW

NORMANBY ROAD EARLY WORKS

EW

MHD/2

WW

WW

WW

22 5

WW33 - PROTECT

504950

150Ø

504952

WW

WW MHD/1

A3

1:500 Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document. READY TO ISSUE

A1

SELF CHECK DIGITAL DESIGN MANAGER

A3

COMPANY NUMBER : 6267870 20

30

40

50

60

CREATOR ID : CRL_NAL_810_00_LKA_DRG_121004 70

80

90

100mm

ALLIANCE REVIEW VERIFICATION

INITIAL

DATE

SCALE

SIZE

AS SHOWN

A1

DESIGNED REVISIONS

DELIVERY STAGE

10

0+618

m

.000 TRS.L 56

25

WW36 - DIVERT AS SHOWN AND REMOVE REDUNDANT SECTION

STAGE-A

A00 LINK ALLIANCE REVIEW REV

DESCRIPTION

68.56

504950

68.75

532577

68.22

532579

67.57

532578

67.45

532580

67.41

532581

67.67

THE LOCATION OF SERVICES SHOWN ON THESE DRAWINGS ARE APPROXIMATE ONLY AND ARE BASED ON GIS INFORMATION PROVIDED BY THE RELEVANT SERVICE PROVIDERS. NO LIABILITY IS ACCEPTED FOR THE COMPLETENESS OR ACCURACY OF PLOTTED SERVICES.

APPROVED

2019-11-22

AB

2019-11-07

CHECKED

DATE

APPROVED

DATE

A. WALKER

2019-09-17

R. CRUZ

This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.

NORTH AUCKLAND LINE

ZONE:

TITLE:

AB

CITY RAIL LINK

PROJECT:

DRAWN

FOR EXTERNAL REVIEW

68.53

504951

ISSUED FOR OUTLINE PLAN

J. WORSLEY

A01

INVERT LEVEL

504952

NOTE

JOINS

12.5

10+240

0 A1

10+220

1:250

12.5 m

214.654 TP 10+

6.25

10+180

0

10+200

NEW INCOMING CONNECTION FROM MOUNT EDEN PRISON

ID NO.

CRL-NAL-UTI-C5-DRG-122003

10+260

LAUDER RD

JOINS

0+598

150mmØ PVC

WW

EXISTING WW MANHOLES

WW NORMAN BY RDWW

150 E

W

504951

CLIENT:

0

EXISTING KERB LINES (GIS)

WW

NBY RD NORMA WW

WW

CRL TRACK ALIGNMENT FUTURE

WW

WW

REMOVE / ABANDON

JOINS

Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_AU_w\60560778\CRL-NAL-UTI-LKA-DRG-121004.DWG Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\ZZ C57 TOC Development\C5D C5 Works TOC Development\900 CAD-GIS\01_WIP\20-SHEET\800 Utilities\CRL-NAL-UTI-LKA-DRG-121004.dwg

150mm

KIWIRAIL BOUNDARY

MHD/4 532579

EW

WASTEWATER WORKS LAYOUT PLAN SHEET 4 OF 5 PROJECT

DOCUMENT:

ZONE

CRL - NAL -

DISCIPLINE

ORGANISTION

TYPE

SHEET

UTI - LKA - DRG - 121004

REVISION

A01 A00


KEY PLAN

0

EW

EW

15

ARC 7 89.39

LEGEND

H/S

PROPOSED WASTEWATER MANHOLE

H/S

PROPOSED FLOW DIRECTION

H/S

H/S

1I

N

56

.3

0

0M MØ

REMOVE / ABANDON

H/S

77

WW35 - DIVERT AND REMOVE

.9

28

H/S

.0 46 .0

N

H/S

9.2

H/S

MH40/3

H/S

WW33 - RELAY THIS SECTION OF PIPE WITH 225Ø uPVC

W W

35

.0

26

S

H/S

30

W W

W W

514654

H/

532748

.0

1I

.0

11

C PV

H/ S

.0

W

W W

S

25

0Ø 30

NORMANBY ROAD EARLY WORKS

H/S

40

15

0

0M

532749

H/S

45

EW

15

PIPE DIAMETER AND MATERIAL

150 CI

RETAINING WALL (DESIGNED BY OTHERS)

MH40/5B

W

0

W

EW

15 0

EW

15

RETAINING WALL

20 .0

S

PV C

W W

PROPOSED KERB & CHANNEL PROTECT

EW

1I N

PROPOSED RETAINING WALL / WALL NIB

400

H/S

WW35 - PERMANENTLY REMOVED

30

PROPOSED RETAINING WALL

10+

H/S

514655

WW27 & WW34 - DIVERT AND REMOVE

EXISTING FLOW DIRECTION EXISTING WASTEWATER MANHOLE

H/S

H/S

532615

MH40/5A

EXISTING SERVICE CONNECTION LINES

532750

H/S

15

EXISTING WASTEWATER

375 S T

0M MØ

380

15

532612

H/S

15

EW

EXISTING BOUNDARY LINES PROPOSED WASTEWATER PIPE LINE

532613

W 1 W 50

CRL TRACK ALIGNMENT FUTURE EXISTING KERB LINES (GIS)

H/S

W27 & WW34 - DIVERT IGNMENT AS SHOWN

W W

15

.0

EXISTING WW MANHOLES

W W

10

.0

S

H/

24

12

5-7

ID NO.

INVERT LEVEL

532614

70.56

5.0

MH40/3A

5 37

JOINS

0.0

NC

CO

514656

532614

WW27 & WW34 - PROTECT

W 15

AT

0

ER

EW 15 0

ST

514650

8

6.25

12.5 m

0

12.5

150

16-18

25

READY TO ISSUE

A1

SELF CHECK DIGITAL DESIGN MANAGER

20

30

40

50

60

CREATOR ID : CRL_NAL_810_00_LKA_DRG_121006 70

80

90

100mm

ALLIANCE REVIEW VERIFICATION

INITIAL

DATE

SCALE

SIZE

AS SHOWN

A1

DESIGNED REVISIONS

DELIVERY STAGE

10

73.65

514654

69.87

532615

67.78

514655

67.79

532613

67.51

532612

67.27

514649

67.02

532748

67.95

532749

67.83

532750

67.82

532747

66.45

ISSUED FOR OUTLINE PLAN

A3 Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.

A3

74.31

514656

THE LOCATION OF SERVICES SHOWN ON THESE DRAWINGS ARE APPROXIMATE ONLY AND ARE BASED ON GIS INFORMATION PROVIDED BY THE RELEVANT SERVICE PROVIDERS. NO LIABILITY IS ACCEPTED FOR THE COMPLETENESS OR ACCURACY OF PLOTTED SERVICES.

95

1:500

COMPANY NUMBER : 6267870

514650

NOTE

4

EW

m

A1

1:250

E

20

6

0

M

22

T

N DE

RD

EW

CLIENT:

0

KIWIRAIL BOUNDARY

1

10+

CRL-NAL-UTI-C5-DRG-121003

I

10+3 60

Ø1

MM

5

DESIGNATION BOUNDARY

W

Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_AU_w\60560778\CRL-NAL-UTI-LKA-DRG-121006.DWG Last saved by: RUBY.CRUZ1(2019-11-06) Last Plotted: 2019-11-06 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\ZZ C57 TOC Development\C5D C5 Works TOC Development\900 CAD-GIS\01_WIP\20-SHEET\800 Utilities\CRL-NAL-UTI-LKA-DRG-121006.dwg

0

150

65. N1

5

EW

10+34

H/S

W

0E

6

72.014

10+320

225

532747

514649

15

3

00 141.0

EW

2

1

0 ARC

MHD/6 WW

EW

141.00

5

10+300

22

10+260

WW36 - DIVERT AS SHOWN AND REMOVE REDUNDANT SECTION

WW

10+280

MHD/5

225

225 E W

ENFIE LD ST

N

4

R.

ISO A1 594mm x 841mm

225

R.

3

N

25-27

STAGE-A APPROVED

DRAWN

FOR EXTERNAL REVIEW

A00 LINK ALLIANCE REVIEW REV

DESCRIPTION

TITLE:

AB

2019-11-22

AB

2019-11-07

CHECKED

DATE

APPROVED

DATE

A. WALKER

2019-09-17

R. CRUZ

This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.

NORTH AUCKLAND LINE

ZONE:

J. WORSLEY

A01

CITY RAIL LINK

PROJECT:

WASTEWATER WORKS LAYOUT PLAN SHEET 5 OF 5 PROJECT

DOCUMENT:

ZONE